Title: X-ray Overview
1X-ray Overview
John Arthur LCLS Photon Systems Manager
- XTOD current status
- XES current status
- Schedule to first experiments
- Coordination with LUSI
- Transition from project to facility
- Beyond the LCLS baseline
2Status in June 2008
- XTOD is assembling instruments at LLNL
- All mirrors have been ordered
- Soft X-ray mirrors arriving meet figure spec
- XES is working on final designs
- Stoppers and doors are being built
- 2d detector plan is updated prototype under test
at Cornell, SLAC working on packaging and
interface to DAQ
3XTOD
4X-ray front end
- Front end X-ray optics being assembled at LLNL
- Optics/diagnostics through preliminary or final
design review
5 mm collimator
Soft X-Ray Offset mirror system
Hard x-ray Monochromator (K Spectrometer)
Gas Detector
Solid Attenuator
Direct Imager
Pulse Energy Thermal Detector
Slit
Hard X-Ray Offset mirror system
Gas Attenuator
e-
Gas Detector
Start of Experimental Hutches
Muon Shield
5FEE Diagnostic Hardware Status
- Fixed Mask / Slit
- In house, Integrated testing
- Attenuator
- Under assembly
- Gas Detectors
- In house/integrating
- Thermal Sensor
- Vessel on order
- Sensors in fabrication
- Direct imager
- Vessel on order
- Cameras, scintillators, filters in house
- K monochromator in final design
- Pop-in Monitors in design
- Controls
- 4 of 5 FY08 FEE racks complete
- FEE Vacuum Rack gt75
- 98 of all other controls h/w received
6The first SOMS mirror meets its specification for
long spatial period flatness
- Total budget for long scale curvature is lt 20 nm
tangential, lt 5 nm sagittal - - limits intensity asymmetry due to reflections
to lt 10 - Allocation to fabrication errors was 10 nm
tangential, 4 nm sagittal - - contour plot shows SOMS 1 meets this
requirement
Contour plot with 10x175 mm2 mask
9nm
Color map of 250x50 mm2 SOMS 1 figure
Figure, nm
0
Sagittal axis, mm
Tangential axis, mm
10
0
175
See detailed figure budget in ESD 1.5-122,
HOMS SOMS Opto-mechanical Design
7Integrated EPICS control system under development
8X-ray Endstation Systems
NEH nearly ready for occupants
9XES Status June 08
- AMO Instrument final design phase
- Drawings gt60 complete
- All ESDs are completed
- Controls PDR 4/08
- AMO Preliminary Hazard Analysis Document being
finalized - Long-lead procurements starting
- Mechanical Systems
- PPS stoppers and hutch doors in fabrication
- Ready for installation in 7/09
- XES laser system
- PRDs for Laser system and LSS completed
- ESD for Laser transport controls 3/08
- PDR for laser and transport system May 21
- Quotes are in hand for tables and laser
components - Laser SOP reviewed by LSO and LSC May 6
- Installation
- Cable plant are being designed, contracts are
being placed
10AMO Instrument
John Bozek jdbozek_at_slac.stanford.edu
11AMO Schedule
- Begin long lead procurements 5/08
- Final Design complete 8/08
- Procurements 10/08
- Start Receiving hardware 12/08
- Receive XES Laser 3/09
- Install Laser 4-6/09
- AMO Assembly and test 12/08 -- 4/09
- Install AMO (phase 1) in hutch 5/09 6/09
- Test AMO 7/09
- Final readiness test 7/09
- 1st x-rays to AMO instrument 7/09
- AMO Phase 2 installed by 11/09
- ? No float in schedule for early science in 7/09
12Cornell 2D Detector
- LDAC Review in May 08 showed good progress
- Demonstrated a working bump-bonded detector
- Detailed testing of chip is continuing
- Go-forward plan is being reviewed
- Integration with SLAC DAQ system
- Mechanical packaging will be done at SLAC
- Coordinated with CXI
- Received bump bonded chip at SLAC in May 08
- Delivery of Final Detector at SLAC in Spring 2009
13Detector Mechanical Design Concept
Light shroud (cover removed)
Cooling coil
- Quadrant board
- Combines 16 ASICs
- 1 FPGA/quadrant
- Double detector package
- 4 ASICs
- 2 pixel array detectors
Martin Nordby, Matt Swift PPA Mech. Eng.
14LCLS Installation and Commissioning Time-Line
First Light in FEE
FEH Hutch BO
First Light in FEH
PPS Cert. LTU/Dump
LTU/Und/Dump Install
CD-4 (7/31/2010)
X-Rays in NEH
FEE/NEH Install
FEH Install
PEP-II run ends
now
J
F
M
A
M
J
J
A
S
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
O
N
A
A
M
2008 2009
2010
Down
PPS
LTU/Und Comm.
Re-commission Inj/BC2 to SL2
NEH Operations/ Commissioning
Linac/BC2 Commissioning
FEE Comm.
April 18, 2008
15Coordination with LUSI
- Photon Systems working closely with LUSI
- Both managed by J. Galayda
- Close proximity in Bldg 280
- Shared engineering/design resources
- Interface Working Group meets bi-weekly
- Formal relationship set by Interface Control
Documents
16Transition from Project to Facility
- Responsibility for operation of LCLS instruments
and LCLS X-ray science lies with the Experimental
Facilities Division (XFD) - Head, responsible for User outreach Jochen
Schneider - Deputy, responsible for LCLS science Jerry
Hastings - Responsible for User operations John Arthur
Group includes Photon Systems and LUSI staff
(about 20 today) Growing quickly but thoughtfully
(hiring now)
17Beyond the initial LCLS configuration
- Policy for outside groups which propose to add
instrumentation to the LCLS facility - Must offer a significant addition of general
utility to LCLS - Must get support of LCLS (with evaluation by SAC)
- Then group and LCLS negotiate with funding
agencies - Then group and LCLS decide final layout and
timeline, sign MOU - Some access priority can be negotiated, within
limits which guarantee plentiful access by
general users - All new instrumentation reverts to LCLS
ownership/management after early operation
18First example of addition to LCLS
- SXR instrument Soft X-ray Materials studies
- Consortium led by Anders Nilsson (SLAC/Stanford)
and Wilfried Wurth (CFEL/Univ Hamburg) - Institutions Stanford, Univ Hamburg, LBNL, BESSY
- Monochromatic soft-X-ray line to complement AMO
line - No end station in initial configuration
(consortium will loan) - Fast-track schedule operation in late 2009
- Status preparing Design Report for LCLS review
in July - If approved, get MOU by September
19Where to put SXR?
Plan 1, with AMO in Hutch 2
Plan 2, moving AMO to Hutch 1
20Summary
- XTOD is building instruments at LLNL XES is in
final design phase - This is a busy time for both groups
- The schedule to reach early science in July 2009
is tight, though risks to CD-4 milestones are
very small - LCLS is transitioning from project to facility
- SXR instrument is first example of a proposal for
additional capability beyond LCLS baseline