Johnson Creek Covered Bridge - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Johnson Creek Covered Bridge

Description:

Johnson Creek Covered Bridge – PowerPoint PPT presentation

Number of Views:59
Avg rating:3.0/5.0
Slides: 20
Provided by: Kentuc3
Category:

less

Transcript and Presenter's Notes

Title: Johnson Creek Covered Bridge


1
Johnson Creek Covered Bridge
2
Construction Statistics Review Update
  • In service since May 1, 2005
  • 2386 projects active in system
  • 640 finals paid in 2007 for 4,137,168
  • 935 Change Orders approved in 2007
  • Progress Estimates for payments in 2007 of
    1,054,764,758
  • 1614 subcontract approved in 2007

3
SiteManager DWR
  • Summary of DWR Quantities on website updated
    bi-weekly with pay estimates. This can also be
    created within SiteManager and send from RE
    office

The CSV File can be loaded into Excel for summary
information and assisting in checking final. In
Excel, it can filter on each Pay Item to check
for weigh sheets, etc.
http//transportation.ky.gov/construction/sm/dwr/
4
Pending Pay Estimates Links
  • ARCHIVED http//transportation.ky.gov/constructio
    n/sm/est/PENDING/archive/
  • Current http//transportation.ky.gov/construction
    /sm/est/PENDING/

5
Approved Pay Estimates Links
  • ARCHIVED http//transportation.ky.gov/constructio
    n/sm/est/EST_ARCH/
  • Current
  • http//transportation.ky.gov/construction/sm/est/

6
Approved Pay Estimates Links
  • Check EFT numbers

http//transportation.ky.gov/construction/sm/est/p
ayments2008.xls
7
Question
  • What can be done to provide a better pay plane
    for subcontractors for work done?
  • Pay estimates DWR csv on web. Our contract is
    with prime.

8
Question
  • BETTER PLAN TO ADDRESS A QUICKER TURN AROUND TIME
    ON RECEIVING PAYMENTS FOR WORK PERFORMED .
  • State Highway Engineer Gilbert Newman addressed
    change order issue. Residents with their
    inspectors keep track of work items. Need to
    coordinate with RE if you feel you have completed
    work not on pay estimate

9
SiteManagerChange Orders
  • During SiteManager Review, Resident Engineer
    should forward by e-mail a copy of change order
    to Contractor before sending for signature.
  • This will allow them to check supplemental prices
    included in the change order.

10
Change Order Signature Report
  • Resident Engineer is to sign the change order on
    requested by line and mail, deliver or fax to
    contractor for signature and further submittal to
    State Highway Engineers Office.
  • Contractor is to send change order with original
    signature (no fax or copy) to
  • State Highway Engineers Office
  • 6th Floor TCOB
  • 200 Mero Street
  • Frankfort, KY 40622

11
Change Order Signature Report
  • DSHE for Project Delivery forwards to State
    Highway Engineer for signature approval
  • If approved, Change order then sent to account
    for uploading program funding.
  • After funding finally secured the Change Order is
    put in APRV status and payment can be made on
    items. Approved Change order copies then mailed
    out.

12
Payment for Change Order Items
  • After Change Order has been put in APRV status,
    payment can be made on items included in the
    change order. They are now part of the contract.

2008 Standard Bid Item List Project let after
1/1/08
http//transportation.ky.gov/construction/ITEMS/IT
EMS08.xls
13
Question
  • PLEASE ADDRESS THE LENGTH OF TIME THAT IT TAKES
    TO GET A CHANGE ORDER PROCESSED. EXAMPLE-WORK
    DONE IN SEPTEMBER OCTOBER ON CHANGE ORDER
    STILL NOT PROCESSED.
  • State Highway Engineer Gilbert Newman addressed
    this issue. Residents will keep current one
    Change Order submittals.

14
DBE payment information
  • Required to pay within 7 days of receipt of
    payment from KYTC. We pay every two weeks!
  • Submit copy of check with Contract ID reference
    to
  • Office of Civil Rights Small Business
    Development
  • DBE Payments
  • 6th Floor West TCOB
  • 200 Mero Street
  • Frankfort, KY 40601

15
Potential Final Estimates
  • 143 Contracts needing Corrective Work Completed
    to get Formal Acceptance

http//transportation.ky.gov/construction/projects
/correct/correctbycont.pdf
16
Final Estimates
  • Project Engineer will send copy when finished
    checking. Please let them know of any problems.
    They will forward to district in 15 days after
    sending to contractor, so let them know if you
    have a problem with quantities!
  • When Final Release sent from Central Office,
    Contractor has 60 days to respond. If any errors
    or disagreements be sure to send notice to both
    Director of Construction Central Office and
    District Construction.
  • Signing and sending Final Release as soon as
    possible speeds up final payment!!!

17
Question
  • What should a Contractor do to get a job closed
    out after 5 years?
  • Contact TEBM for Construction Director of
    Construction. We are trying to get current on
    our Finals!

18
Pre-Qualified Contact Link
  • http//transportation.ky.gov/Contract/Pqbook.pdf
  • Provide the Resident Engineer an e-mail at
    Pre-Construction meeting for submitting Change
    Orders and Pay Estimates.

Poor sign placement erection (not a Road
Construction Project!!)
19
Robert C. Lewis, PE Assistant State Highway
Engineer 200 Mero Street W6-17-02 Frankfort, KY
40622 E-mail Bob.lewis_at_ky.gov Cell
502-330-3470 Office 502-564-3730 ext 3084
Write a Comment
User Comments (0)
About PowerShow.com