Title: Civista Medical Center
12006-2007 Thesis Presentation
- Civista Medical Center
- La Plata, MD
Thad Maugle Construction Management
2Presentation Outline
- Project Overview
- Infection Control Risk Assessment
- Technical Analyses
- Mechanical Steam Turbine vs. PRV
- Electrical Aluminum vs. Copper Conductors
- Acknowledgement
- Questions / Comments
3Project Overview
- Location La Plata, MD
- Building Occupant Civista Health, Inc.
- Scope
- Addition 122,864 SF
- Renovations 36,303 SF
- Occupancy Function
- Institutional I-2
- Medical Care
- Size 159,167 SF of total construction
- Number of stories above grade / total levels 4
/ 4 - Dates of Construction 12/1/04 - 8/1/07 (33
months) - Total Project Cost 43,941,344
- Project Delivery Method CM _at_ Risk w/ GMP
4Project Overview (contd)
- Existing Site Conditions
- Foundation
- Augered CIP Concrete piles
- Structure
- Elevated CIP Concrete
- Building Envelope
- Precast Stone Masonry Units w/ Modular Face Brick
5Project Overview (contd)
- Mechanical System
- Electrical System
- 480/277V Lighting, Major Mech. Equip., Building
Equip. - 208/120V Lighting, Small Mech. Equip., Small
Building Equip. - Building Service 15 kV service
6Infection Control Risk Assessment
- Problem
- Civista requires an ICRA plan that is properly
sequenced. - Goal
- Formulate an ICRA plan unique to Civista
- Sequence an area of renovations
- Analysis Techniques
- Overview of ICRA
- Formulate ICRA plan for Civista renovation
7Background
- Infection Control Risk Assessment (ICRA)
- A strategic plan intended to identify and
alleviate potential risks associated with the air
quality environment during the construction phase
of a project - Interim Life Safety Measures (ILSM)
- A series of actions required to be taken to
temporarily compensate for hazards posed by
existing Life Safety Code deficiencies or
construction activities, allowing for safe
execution of the ICRA. - American Institute of Architects (AIA) Guidelines
for Design and Construction of Healthcare
Facilities - Introduced ICRA in 2001
- Joint Commission for Accreditation of Health Care
Organizations (JCAHO) - Mandated ICRA in 2001
8Implications of ICRA
- Owner
- Responsible for budget and ICRA completion prior
to the commencement of work - Construction Management Team
- Preconstruction planning and implementation of
the infection control measures - Monitoring, documentation, and quality control
- Trade Contractors
- Abide by the provided infection control measures
- Monetary penalties may result otherwise
9ICRA Analysis
- Step 1
- Identify Type of Construction Project Activity
(Type A-D) - Step 2
- Identify the Patient Risk Group
10ICRA Analysis
- Step 3
- Match the Patient Risk Group with the planned
Construction Project Type to find the Class of
Precautions or level of infection control
activities required.
11Suggested Infection Control Actions
- Dust proof plastic barrier with door and frame to
be installed. Contains demo debris and dust, and
protects patients - Air vents inside the work area will be sealed
with plastic sheeting - Dust mats to be placed at entrances and exits of
work areas - Negative air pressure to be maintained within
work area utilizing HEPA equipped air filtration
units - Construction debris to be transported in tightly
covered containers - Inside work area to be completely cleaned prior
to removal of plastic barrier - After removal of plastic barrier, area to be
cleaned again with disinfectant - All staff in the area to be briefed prior to the
commencement of work
12Suggested Interim Life Safety Measures
- Forms submitted and approved.
- Fire door exits to be maintained for clear access
at all times. - Hospitals existing life safety systems not to be
interrupted. - Additional fire fighting equipment to be
available. - Staff to be briefed prior to the commencement of
work. - Install dust proof plastic barriers to contain
demo debris and protect occupants - Properly cover loads of debris
- Clean interior area enclosed by barriers
- Remove temporary barriers upon completion
- Clean and disinfect entire area upon removal of
temporary barriers
13Additional ICRA Provisions Unique to Civista
14Decision Tree
- Invasive Work
- Layout work plan
- Use containment
- Shield patients visitors
- Use dust mats
- Signage as needed
- Cover trash during removal
- Type of Containment
- 1-14 days Plastic Wall
- Affecting existing utilities?
- Plan outages
15Wall Mount Configuration
- Minimizes number of wall penetrations by running
cable and wiring down from the ceilings instead
of through the walls
16Outage Request Forms
- Existing utilities and systems will be affected
- (Ex.) Sheaves and belts on Air Handling Unit
(AHU) 7 need replaced and upgraded - Affects occupied space being renovated
- Requires schedule and approved system outage
- Isolate areas - ventilation temporarily out of
service - Highly sensitive at-risk patients may need to be
moved to a more stable environment for the time
being.
172nd Floor East Wing Sequencing
- Risk Type
- C work generates moderate to high levels of
dust - Patient Type
- Highest Risk
- Description
- Additional Plumbing and sprinkler piping required
above ceilings in patient rooms of the 2nd floor - Sequencing will involve two rooms at a time
182nd Floor East Wing Sequencing - (1)
- Sequence 1, 2, 3, 6, 7, 8
- General Trades
- Remove furniture
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Cut drywall for tie-ins
- Lay out piping on ceilings
- Cut drywall ceiling for piping
- Cut drywall ceiling in toilet room for
sprinkler piping and head - Remove drywall debris
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
192nd Floor East Wing Sequencing (2)
- Sequence 1, 2, 3, 6, 7, 8
- General Trades
- Remove furniture
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Cut drywall for tie-ins
- Lay out piping on ceilings
- Cut drywall ceiling for piping
- Cut drywall ceiling in toilet room for
sprinkler piping and head - Remove drywall debris
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
202nd Floor East Wing Sequencing (3)
- Sequence 1, 2, 3, 6, 7, 8
- General Trades
- Remove furniture
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Cut drywall for tie-ins
- Lay out piping on ceilings
- Cut drywall ceiling for piping
- Cut drywall ceiling in toilet room for
sprinkler piping and head - Remove drywall debris
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
212nd Floor East Wing Sequencing (4)
- Sequence 4 5
- Can be accomplished after normal hours
without disturbance to staff - General Trades
- Remove supplies from the supply room
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Demo drywall ceiling in the supply room
- Remove drywall debris
- Install plastic covering on the walls and
floors in rooms to be worked that night - Remove ceiling tiles as required
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
- Install sprinkler heads
222nd Floor East Wing Sequencing (5)
- Sequence 4 5
- Can be accomplished after normal hours
without disturbance to staff - General Trades
- Remove supplies from the supply room
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Demo drywall ceiling in the supply room
- Remove drywall debris
- Install plastic covering on the walls and
floors in rooms to be worked that night - Remove ceiling tiles as required
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
- Install sprinkler heads
232nd Floor East Wing Sequencing (6)
- Sequence 1, 2, 3, 6, 7, 8
- General Trades
- Remove furniture
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Cut drywall for tie-ins
- Lay out piping on ceilings
- Cut drywall ceiling for piping
- Cut drywall ceiling in toilet room for
sprinkler piping and head - Remove drywall debris
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
242nd Floor East Wing Sequencing (7)
- Sequence 1, 2, 3, 6, 7, 8
- General Trades
- Remove furniture
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Cut drywall for tie-ins
- Lay out piping on ceilings
- Cut drywall ceiling for piping
- Cut drywall ceiling in toilet room for
sprinkler piping and head - Remove drywall debris
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
252nd Floor East Wing Sequencing (8)
- Sequence 1, 2, 3, 6, 7, 8
- General Trades
- Remove furniture
- Construct plastic dust barrier
- Install floor protection
- Install HEPA filters in both rooms
- Cut drywall for tie-ins
- Lay out piping on ceilings
- Cut drywall ceiling for piping
- Cut drywall ceiling in toilet room for
sprinkler piping and head - Remove drywall debris
- Plumbing Contractor
- Lay out piping on ceilings
- Core drill roof
- Install hangers and piping
- Perform pipe testing
- Sprinkler Contractor
- Install hangers and piping
26Steam Turbine vs. PRV
- Problem
- Pressure Reducing Valve (PRV) used to reduce
steam pressure. - Goal
- Redesign pressure reducing equipment from PVR to
non-condensing backpressure steam turbine. - Analysis Techniques
- Overview of steam turbine system
- Size equipment
- Conduct energy analysis
- Conduct cost analysis
27Non-Condensing Backpressure Steam Turbine
- Non-condensing (backpressure)
- Operates above or in excess
- of atmospheric pressure
- Used where low steam loads are required
- Steam passes over turbine blades, spins turbine
blade shaft which directly connected to an
electrical generator, generates electricity - Low efficiencies (15-35)
28Sizing the Steam Turbine
- Given Variables
- Inlet Pressure (Pi) 60 psig 14.7 atm pressure
74.7 - Outlet Pressure (Po) 10 psig 14.7 atm
pressure 24.7 - Total Capacity (m) 3590 lb/hr
- Temperature of Steam (T1) est. 300oF (227oF to
307oF) - Efficiency Rate (n) est. 20 (15 to 35)
- Find Power Rate
- Q m h
29Sizing the Steam Turbine (contd)
- Find Enthalpy Using Steam Tables
- hi 269.8 BTU/lb
- ho 1190 BTU/lb
- h ho hi 920.5 BTU/lb
- Q m h 3,635,975 BTU/hr
- Factor in Efficiency
- Q x n 3,635,975 BTU/hr x 0.20 727,197 BTU/hr
- Convert to kW
- 727,197 BTU/hr x (1 kW) / (3412 BTU)
213.13 kW - Equipment can now be sized according to kW
output
30Cost and Energy Analysis
- Impractical to operate at full capacity
- Assumed
- 40 max capacity during Summer months (Jun
Oct) 85.25 kW - 60 max capacity during Winter
- months (Nov May) 127.88 kW
- Chart would be most useful in the presence of
steam charts
31Cost and Energy Comparison
w/ Pressure Reducing Valve
w/ Steam Turbine
- 5,044,064 kWh consumed
- 491,575.76
- 5,759,158 kWh consumed
- 508,907.24
32Cost and Energy Comparison
- Steam Turbine estimated performance over 9 month
period - Saves over 17,000
- Saves over 715,000 kWh
- Cycle produces no emissions
- Could be greater savings based on actual
efficiency of equipment and actual capacity used.
33Aluminum vs. Copper Conductors
- Problem
- Civista wired with copper.
- Reliable but expensive.
- Goal
- Redesign copper feeders with Aluminum Alloy
(AA-8000 series) alternative. - Analysis Techniques
- Compare material properties
- Resize feeders and conduit
- Conduct cost analysis
- Conduct schedule comparison
34Background
- Copper shortage 1965
- Aluminum was a cheaper alternative
- Steel receptacle screws replaced brass
- Aluminum to steel connection far more sensitive
than copper to brass - Thermal expansion and creep
- Oxidation Resistance - hot
- Corrosion
- Faulty connections, even fires resulted
- No contractor wants to take the risk
35Material Composition
- Previous Aluminum Classifications
- AA-1350
- EC (Electrical Conductor) aluminum
- 99.5 pure aluminum
- Current Aluminum Alloy Classification
- AA-8000 series
- 0.001 to 0.3 zinc
- 0.001 to 0.03 titanium
- 0.001 to 0.5 manganese
- 0.03 to 0.4 silicon
- Combination yields excellent strength
resistance to corrosion
36Problems / Solutions
- Improper Installation
- Use appropriate tools (i.e. stripping wire)
- Wrap wire in a clockwise manner (i.e. tightens
while being screwed in placed) - Sufficiently tightened (i.e. adequate contact
area at the connection) - Oxidation / Corrosion
- AA-8000 series - thermal expansion and creep
similar to copper - Proper tightening
- Oxide inhibitor
37(No Transcript)
38(No Transcript)
39(No Transcript)
40Cost and Schedule Comparison
- Saves over 8,000 in conductor and conduit costs
of feeders - Saves 4 days in construction time
- Savings would be greater when including branch
circuits
41Acknowledgements
- AE Faculty
- Dr. Michael Horman
- Dr. James D. Freihaut
- Professor Richard Mistrick
- Professor Kevin Parfitt
- Industry Contacts
- Ben Alexander - Gilbane Building Co.
- Greg Dunkle - Gilbane Building Co.
- Mike DuLaney - Gilbane Building Co.
- Melanie Townsend - Gilbane Building Co.
- Dan Kerr - McClure Company
- Gary Hall - Civista Health, Inc.
- Fellow AE Students
- Alexis Kreft
- David Potchek
- Andrew Rhodes
...and most importantly, family and friends
42Questions ???