Title: X-Ray Endstations Overview


1
X-Ray Endstations Overview
John Arthur
2
The Endstation Systems will provide
Personnel protection systems (PPS) Keep people
safe from x-rays, lasers, etc. Machine
protection systems (MPS) Keep delicate machine
safe from clumsy people Network and computer
support Cables, networks, servers, data
storage Beamline controls Hardware,
software Synchronized laser system fs laser
system synchronized to FEL Prototype
detectors Basic experimental chambers Instrument
ation for initial atomic physics experiments
3
Where the Endstation Systems are located
Near Expt Hall
Far Expt Hall
250 m
4
The Near Experimental Hall
5
The Near Experimental Hall
Shops, setup space
FEL beam
Experimental hutches
Laser room above hutches
6
The Far Experimental Hall
7
The Far Experimental Hall
Office and shop space
Experimental hutches
FEL beams
Laser room
8
The FEH is underground
21
30 9
9
Placement of the endstation systems
10
Placement of the endstation systems
Controls System Inst. Alignment
Laser Systems
NEH
North-Hutch
FEH
Laser Room
Tunnel
Hutch 1
Hutch 2
Hutch 3
FEE
Center Hutch
South-Hutch
Laser Room
Atomic Physics Experiments
Mechanical/Vacuum X-Ray Detectors
11
Work Breakdown Structure for the endstation
systems
12
Principal divisions and staffing
Science Advice
Project Planning
J. Hastings
J. Scholes
Management
J. Arthur S. Moeller
Mechanical, Vacuum
Controls
Lasers
Detectors
Atomic Physics
9 people
2 people
2 people
1 person
2 people
13
Staffing profile
Year FY04 FY05 FY06 FY07 FY08
Total XES staff 2 6 14 17 17
who is hired management group heads controls group everyone else
14
Example of task schedule FEE cabling
Installation schedule tied to completion of
conventional construction in 2007
15
COST Report Construction, RD
Grand Total 17.9M
16
COST Report Commissioning
Grand Total 670k
17
Major endstation systems milestones
Level 2 PPS certified in NEH 10-07 PPS certified
in FEH 1-08 LCLS start operation 9-30-08 Level
3 FY04 TDR Complete detailed schedule EIR
review Complete 2D detector statement of
work Award initial RD funding for 2D
detector FY05 Design review 1 for 2D
detector FY06 Network final design review Laser
final design review Order lasers Design review 2
for 2D detector
FY07 Start installation in NEH Start
installation in FEH Beamline controls final
design review Laser operating in NEH Laser
operating in FEH Complete installation in
NEH FY08 Complete beamline controls Complete
network and cabling Complete mech/vacuum Complete
acceptance tests of detectors First atomic
physics experiment