Title: EMSL Update: Reviews, Action Plan


1
EMSL Update Reviews, Action Plan Progress
  • BER Advisory Committee
  • Fall 2005

2
Outline
  • Routine review of BER facilities to ensure proper
    and effective operation
  • BERAC SC Office of Project Assessment conducted
    reviews of EMSL
  • Outcomes
  • Responses
  • Accomplishments
  • Paths forward

3
Two-headed reviewMay 2005
  • BERAC (Michelle Broido, Chair)
  • Relationship, Science, Structure, User Model,
    Prioritization, Capital Equipment, non-BER
    funding
  • SC Office of Project Assessment (Daniel Lehman)
  • Management, Oversight, Resources, non-BER
    funding, Self assessment

4
Results
  • BERAC review of EMSL science found
  • The science conducted in the EMSL is of very
    high quality, and a significant amount is,
    indeed, cutting edge. It is appropriate for BER
    to support this Laboratory that is a national
    resource.
  • Need for reinvigorated User Scientific advisory
    committees
  • BERAC and OPA found
  • Lack of a shared vision for EMSL
  • Need for prioritization/decision making plan
  • Need for standardized user access protocol
  • OPA found
  • Need for enhanced managerial resources
  • Need for improved communications among all
    parties
  • Need for improved financial reporting systems
  • Need to understand the impact of non-BER funding
    within EMSL
  • Need for extensive benchmarking

5
Responses
  • Charged by Ray Orbach with resolving identified
    issues within six months (i.e., by close of 2005)
  • EMSL brought on additional administrative and
    managerial staff
  • EMSL developed a formal Action Plan
  • Implemented project management process
  • Approved and monitored by PNSO BER

6
Responses (continued)
  • BER, PNSO, PNNL and EMSL became much better
    acquainted
  • Weekly conference calls, monthly visits
  • November 2005 BER/PNSO Progress Assessment visit
  • EMSL quarterly visits to Germantown
  • EMSL Action Plan was added to Dr. Deckers
    Watch List
  • Monthly briefings by PNSO/BER on progress

7
Path forward
  • Shared vision/mission is in place
  • EMSL valued as a National Scientific User
    Facility
  • BER, PNSO, PNNL EMSL are well connected and
    aligned
  • Numerous plans documents revised, updated
    and/or created
  • Action Plan will be complete on time (12/31/2005)
  • Next step is implementation
  • BER will revisit EMSL this spring to evaluate
    implementation