Title: Restructured APDRP


1
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
RAPDRP A IN KARNATAKA Feb 2014

2
PROGRESS SO FAR . .
3
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
Go-Live Status of ESCOMs of Karnataka
Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative Town Integration ( Full Stack with MDA Energy Audit) Schedule Cumulative
Month Up to Jan 13 Up to Feb 13 Up to Mar 13 Up to Apr 13 Up to May 13 Up to Jun 13 Up to Jul 13 Up to Aug 13 Up to Sep 13 Up to Oct 13 Up to Nov 13 Up to Dec 13 Up to Jan 14
Target 10 18 40 40 50 50 50 50 53 55 75 91 98
Achieved 6 10 31 31 46 46 46 46 46 46 46 51
ESCOM MBC live Full Stack with Energy Audit
BESCOM 25 11
CESC 12 5
GESCOM 21 11
HESCOM 29 23
MESCOM 11 1
TOTAL 98 51
Module wise / ESCOMs Wise Status as on Jan 2014
4
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
CRITICAL ISSUES OF PROJECT IMPLEMENTATION
Issues Status
System Stabilization Stabilization of the RAPDRP System post Data Centre Crash on 25th Oct 2013 and 5th Nov 2013 Performance of online system and reconciliation of the offline application.
Software Simplification Driven by BESCOM in consultation with other ESCOMs. Progress so far.
GIS Deployment of GIS based integrated Network analysis Module NEPLAN pending from ITIA Incremental data updates on Network and Consumers.
MDAS The legacy meter replacement to DLMS meters is in progress. Modem installation is in progress. (Module wise progress)
5
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
CRITICAL ISSUES OF PROJECT IMPLEMENTATION
Issues Status
Energy Audit SIM card not communicating in some cases Modems burnt at sites- CPRI report awaited Gaps in GIS Incremental update and PART B network up gradation
Training Effective end user training to be imparted. ESCOMs identified Super user not trained. Training environment to be deployed by ITIA for hands on training.
GIS Additional licenses and servers Currently application server can cater to 40 concurrent web user at the bandwidth of 512kbps. Maximum concurrency of 217 users at peak hours at present (Without Bangalore 46 SDO going live) ITIA requested for Change request . BESCOM Board has opined to constitute a committee to deliberate the issue .
6
Thank you
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
7
Module wise / ESCOMs Wise Status as on
Jan 2014
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
progress taken SDO wise
ESCOM Total Towns Total SDOs Office Infrastructure Office Infrastructure Primary Network Primary Network Secondary Network Secondary Network MBC Go Live MBC Go Live GIS Network Approved GIS Network Approved GIS Consumer Approved GIS Consumer Approved Meter-Modems installed Meter-Modems installed Full Stack Go-Live Full Stack Go-Live
BESCOM 25 73 73 100 73 100 73 100 73 100 73 100 73 100 61 84 27 40
CESC 12 19 19 100 19 100 19 100 19 100 19 100 19 100 6 32 19 100
GESCOM 21 23 23 100 23 100 21 91 23 100 23 100 23 100 17 74 23 100
HESCOM 29 37 37 100 37 100 26 70 37 100 37 100 37 100 26 70 37 100
MESCOM 11 17 17 100 17 100 10 59 17 100 17 100 16 94 1 6 4 24
Total 98 169 169 100 169 100 149 88 169 100 169 100 168 99 111 66 110 65
  • CCC Operational across ESCOMs except MESCOM

8
Process Simplification Update
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
Priority Priority Priority Priority Priority Priority
Current Status High Low Medium NA Grand Total
Closed 14 30 16 8 68
In Progress 22 7 10 39
Open 7 8 12 27
Duplicate 2 14 16
Pending Sign-Off 1 1
Pending Clarification 2 4 2 8
Grand Total 48 49 40 22 159
 
  • Of the 159 observations, 94 have been closed
  • The remaining 65 items are planned to be
    completed by Feb 2014

9
Process Simplification Update
Restructured Accelerated Power Development
and Reforms Programme (R-APDRP)
Module In Progress Open Closed Duplicate Pending Sign-Off Pending Clarification Grand Total
Connection Management 10 1 15 2 2 30
GIS 11 9 19 5 44
IDAM 1 1
MBC 1 1
MDASEA 1 1
MIS 2 4 2 8
NEPLAN 1 1
System Security 1 1
WAMS 12 10 39 9 1 1 72
Grand Total 36 21 78 16 1 7 159
  • Of the 159 observations, 94 have been closed
  • The remaining 65 items are planned to be
    completed by Feb 2014