Title: Building Commissioning: It
1Building CommissioningIts a Process For a
ReasonPresented by Rick Scivally CHFM, CHSP,
CBCP, LEED AP
2Presentation Goals
- Provide a basic understanding of the
commissioning process and the importance of
following it - Describe the importance of providing detailed
information to all involved parties throughout
the Commissioning Process
3What is Building Commissioning
-
- ASHRAE Guideline 0-2005, The Commissioning
Process, defines commissioning as "a
quality-oriented process for achieving,
verifying, and documenting that the performance
of facilities, systems and assemblies meet
defined objectives and criteria".
4Building Commissioning
- A building commissioning professional should be
brought to the team right after the Architect and
Design Engineers are selected. This is not
absolutely necessary, but doing so will save
numerous headaches, changes and potential
increases in scope, design and construction fees
down the road.
5Commissioning Authority/Agent
- An entity identified by the Owner who leads,
plans, schedules and coordinates the
commissioning team to implement the Commissioning
Process. - Source ASHRAE Guideline 0-2005
6Phases of the Commissioning Process
- Pre Design
- Design
- Construction
- Occupancy and Operations
- Continuous Commissioning
7Pre-Design PhaseOwners Project Requirements
(OPR)
- A written document that details the functional
requirements of a project and the expectations of
how it will be used and operated. These include
project goals, measurable performance criteria,
cost considerations, benchmarks, success
criteria, and supporting information. - Source ASHRAE Guideline 0-2005
8Pre-Design PhaseOPR
- Created by a multi-disciplinary team of end
users, maintainers and senior management - Can be created by the owner and owner's team
members before any other contract Design Team
members are selected - Describes the systems and system components to be
included in the commissioning process. Must be as
specific and detailed as possible - Includes how building performance will be
monitored through measurement and verification - Used to create the Basis of Design documents
- Must become a living document
9Pre-Design PhaseExamples of a Poor OPR
- All energy consuming devices shall be
independently metered - Energy consuming systems shall perform more
efficiently than required by applicable energy
codes/standards - All building components and systems to be
included in the commissioning process
10Pre-Design PhaseBasis of Design (BOD)
- A document that records the concepts,
calculations, decisions, and product selections
used to meet the Owners Project Requirements and
to satisfy applicable regulatory requirements,
standards, and guidelines. The document includes
both narrative descriptions and lists of
individual items that support the design process. - Source ASHRAE Guideline 0-2005
11Pre-Design Phase - BOD
- Created by the members of the Design Team, not
just the Architect and Design Engineers - Usually not as large of a group as required by
the OPR - Needs to include how performance of energy
consuming systems will be measured and verified - Is a living document that should reflect and
change with the OPR
12Pre-Design PhaseExamples of a Poor BOD
- All HVAC systems are to be designed in accordance
with all applicable ASRAE guidelines - Occupied/unoccupied settings to be determined by
owner after occupancy - Mechanical contractor to determine sequence of
operation of all mechanical systems - Mechanical contractor to supply a fully
functional and integrated automated HVAC control
system
13Design Phase
- Creation of commissioning specifications for
systems/components to be included in the process - Creation of contractors checklists
- Ongoing plan review against the OPR and BOD
documents
14Design PhaseCommissioning Specifications
- Do
- Clearly define the expectations of
contractor/subcontractors participation in the
commissioning process - Include all performance testing, checklist
completion and documentation that will be
required of the contractor/subcontractor - Include Project Closeout requirements including
training and OM manual requirements - Include 6 and 12 month warranty expiration
performance verification requirements
15Design PhaseCommissioning Specifications
- Don't
- Repeat or emphasize penalty clauses for delays or
retesting in the technical sections. These should
be in the General Performance section. - Name subcontractors by trade. Many organizations
have several trades in their portfolio. - Define who will witness testing beyond the owner
or their representative.
16Design Phase3 Dimensional Energy Modeling
- A computer generated model to calculate
anticipated sensible and latent heat loads, their
relationships, environmental and physical
conditions of the built environment, building use
and occupancy in an effort to determine the
energy consumption of a proposed structure and/or
system and the effects design modifications may
have on it.
17Design Phase3 Dimensional Energy Modeling
- Input Elements
- Mechanical Systems
- Total Building Envelope
- Building Orientation
- Building Location and Elevation
- Building Use and Occupancy Type
- Heat Relationships and Transfer Slab to Ground,
Floor to Floor, Through the Roof and Side to Side - Other Exterior Conditions That may Effect Energy
Consumption
18Design Phase3 Dimensional Energy Modeling
- These two show the ability to view the building
by construction type figure on the left is
standard view, figure on the right uses color
to denote different wall, roof, and window
construction assemblies. In this example, half of
level 1, and levels 2 and 3 are parking garage.
19Design Phase3 Dimensional Energy Modeling
- This shows the
- end-use consumption
- profile, graphed by
- hour, so you can see
- the hourly consumption
- fluctuation for various
- end-uses. These are
- the peak days for a six
- month period of time.
20Design Phase3 Dimensional Energy Modeling
- This shows which
- end-uses (lighting,
- cooling, etc.) are
- using the most
- electricity/gas,
- by month
- Energy Modeling Data Provided Courtesy of Telios
Engineers and Consultants
21Commissioning During Construction
- Issues log to be created and reviewed at all
construction meetings - Checklist completed by installing contractors. A
percent of system components should be evaluated
by the Commissioning Agent. - Installation methods and quality of systems to be
commissioned are inspected and verified - System performance and operation is verified
during and after substantial completion - Controls point to point checks
- TAB
22Commissioning During Construction Most Common
Issues
- Flex duct is crimped
- Metal duct is not fully insulated. Pay special
attention to duct top and hard to reach locations - Smoke/fire dampers are not installed correctly
- Access and service doors are blocked or
inaccessible - Location of supply diffusers and return grills
- Temperature set up/back not working properly
- Temperature and lighting occupied/unoccupied
settings not working properly - Software programming issues
23Occupancy and Operations
- Corrections of outstanding issues
- Issues log still in use
- Staff training on proper use of building control,
systems and components - Next season operation and performance
verification - Performance and operations verification prior to
the 12 month warranty expiration - Final Commissioning report issued
24Continuous Commissioning
- A continuation of the Commissioning Process well
into the Occupancy and Operations Phase to verify
that a project continues to meet current and - evolving Owners Project Requirements. Continuous
Commissioning Process activities are ongoing for
the life of the facility. - Source ASHRAE Guideline 0 - 2005
25Cost of Commissioning
- Commissioning new buildings range from 0.5
percent of the total construction cost for
relatively simple projects such as office
buildings to 7.5 for complex laboratories and
medical facilities - This does not include potential additional cost
associated with design changes such as additional
metering devices for MV. - Source National Institute of Building Sciences
26Cost of Not Commissioning
- There are numerous white papers on commissioning
and return on investment available on the
internet. There have also been numerous studies
published which identify the cost of not properly
commissioning a building and the importance of
continuous commissioning once all of the upfront
work has been done.
27