Title: AGENDA
1LRD Phase 2C (3 - 30 Days)
2LRD Phase 2C (3 - 30 Days)
ISB IN Grissom AFB Phase 2B O6 (NAD) Phase 2C
O4-O5 (NAD)
RFO IN Indianapolis, IN Phase 2B O6 (LRC CDR)
Phase 2C O5-O6 (NAD)
LRD HQ - Cincinnati, OH O6 (LRD)
- State EOC - USACE Office/RFO
- Installation Support Base (ISB)
RFO OH WPAFB, OH Phase 2B O5 (LRH) Phase 2C
O5-O6 (NAD)
RFO KY Greenville, KY Phase 2B O6 (LRL CDR)
Phase 2C O6 (NAD)
LRD FWD - Nashville, TN O7 (LRD CDR), O5 (LRE CDR)
ISB KY Greenville, KY O6 (NAD), O4-O5 (LRL)
RFO TN Jackson, TNPhase 2C O6 (LRH CDR)
HQ USACE FWD - D.C. O6 (LRB CDR)
ISB TN Arnold AFB O5 (NAD), O4-O5 (LRP)
3RFO TN Phase 2C (3 - 30 Days)
RFO TN
4RFO KY - Phase 2C (3 - 30 Days)
RFO KY
RFO TN
LRP PRT
5RFO IN Phase 2C (3 - 30 Days)
RFO IN
LRC
RFO KY
LRH PRT
RFO TN
LRP PRT
NAN PRT
6RFO OH - Phase 2C (3 - 30 Days)
RFO OH
RFO KY
LRH PRT
RFO TN
LRP PRT
7LRD Phase 2C (3 - 30 Days)
- Mission Main effort
- Civil Works assessment and restoration
- Re-establish commercial navigation on Ohio,
Tennessee and Cumberland rivers - ESF 3 missions in TN, KY, OH, IN
- - RFO/EFO are established
- - PRT deployment
- Temp emergency power missions throughout NMSZ
- Fully integrated into TN/KY response
capabilities and recovery planning - Regional collaboration with State, Federal and
industry stakeholders
- Movements
- RFO/EFO establishments
- LRH TN RFO
- NAD KY RFO
- NAD OH RFO
- NAD IN RFO
- PRT Deployments TN/KY RFO
- Full integration of NAD support
(LRD/Districts/RFOs) - LNO Deployments
- Support to MTSRU
- Sustainment operations
- Specified, Implied and Essential Tasks
- E - Initiate emergency Contracting activities
- S Integration with USCG MTRSUs
- S - Active RSOI procedures
- I - Perform route clearance missions with debris
PRT - I Creation of emergency civil works
supplemental funding requests - I Conduct 24/7 operations
- Command, Control, Communication
- Full integration of NADs leadership and
support - Reorganizational change with TN SEOC, TN RFO,
KY SEOC, KY RFO as separate reporting entities to
report directly to LRD HQ - MTSRU fully established and supported
- ISBs established and under LRD control
- State-level integration (District, SEOC, RFO
coordination) - Long-term Sustainability planning
8LRD Phase 2C (3 - 30 Days)
- Constraints
- WWPC capability gap creating limited ability to
acquire generators - PRT sustainment/coverage past initial deployment
- Transition plan for recovery operations from
region to national - Lack of national navigation priorities
- Require economy of force/risk management
planning cant do everything - Capability to sustain long-term efforts
- Gaps/Concerns/Recommendations
- HQ/LRD - Task force power continues planning with
FEMA - HQ Create a ready-reserve plan through ESF 3
Cadres/SMEs - SME/Cadres produce and expand PRTs just in time
- Regional efforts toward on-the-job training
- IN/OH do not have temp power PRT (low risk)
- HQ - Addresses national recovery plan in future
OPORD - HQ/LRD continued planning and ultimate creation
of playbook (navigation center of expertise) - HQ/LRD CDRs need to identify and manage risk
9North Atlantic Division support to LRD during
NMSZ response
- Essential for level of response required and
sustainability of effort - Requires senior leader C2 effort, RFO operations,
technical and staff support (LRD and Districts)
to navigation and civil works, administrative - Fully integrated into response/recovery plans
two Division fight - Specified Missions
- TN SEOC Liaison Cell (NAD CG and support staff)
- KY SEOC C2
- KY RFO
- OH RFO
- IN RFO
- OH RFO
- TF Recovery (SES) Lead
- TF Civil Works (SES) Lead
- TF Special Projects Lead
- TF ESF 3 Lead
- TF ESF 3, Debris OIC
- LRD G3 and G33(x2)
- ISB (x4) C2
10North Atlantic Division (NAD) support LRD during
NMSZ response
Rank Required Location
0-7 1 TN EOC
SES 2 LRD G-3
0-6 5 LRD G-3/RFOs
0-5 1 LRD G-3/RFOs
0-4 6 ISBs
Civilians 86 LRD G-3
Engineers 84 LRD Districts
Support from school house to support LRD during
NMSZ response
Rank Required Location
0-3 21 Ft. Leonard Wood
11LRD Fall 2015 NMSZ Navigation Focus Exercise
- PURPOSE
- Conduct a Rehearsal of Concept exercise focusing
on navigation on LRD lakes and rivers. - FOCUS
- Primary focus will be on transportation of
commodities (coal, petroleum, grains) across 400
miles of navigable waterways (Ohio, Tennessee to
include the Great Lakes) post 7.6 magnitude
destructive earthquake and related aftershocks
while concentrating on port and waterway
restoration, bridge and utility obstruction
removal and hazardous waste recovery and disposal
as well as debris recovery and disposal to
include emergency dredging operations to maintain
the required navigation channel. - SCOPE
- Host a half day NMSZ discussion for USACE only
with focus NMSZ planning for FY16 through FY 18
in support of FEMAs National Regional Planning
Strategic Intent - Host a one (1) day ROC drill for LRD Area of
Operations of all major players and organization.
- Focus on earthquake, preparedness, response,
preparedness and recovery activities with focus
on Navigation - DATE
- TBD Fall 2015 in Cincinnati, Ohio area
12(No Transcript)
13LRD Navigation Mission Analysis
- Channels
- - 216 river miles
- - Loss of width and depth
- Bridges
- - 10 bridges
- Aerial Power
- - 15 crossings
- Power Generation
- - Cumberland City Steam Plant
- Commercial Docks
- - One downstream of Barkley
- - Six upstream of Barkley
- Tennessee River
District Flood RiskMgmt Navigation Other Total
Buffalo 1 1 0 2
Chicago 0 1 1 1
Detroit 9 1 0 10
Huntington 35 9 20 64
Louisville 20 15 9 44
Nashville 7 4 0 10
Pittsburgh 16 23 0 39
CELRD Total 88 54 30 171
- Include Locks without Dams
- Barkley is both FRM and NavigationLevees
Retention Ponds
14LRD Request for Information (RFIs) to HQ USACE
- Request LRD be relieved of specified task to
provide HQ USACE Power LNO - Recommend HQ USACE pre-designate additional DTOS
assets to support efforts in TN, KY, IN, and OH - USR and Infrastructure Assessment PRTs
integration process - Using Debris PRT for Route Clearance
- Expiration of World Wide Power Contract (WWPC)
impact - Task and purpose for USACE FWD element
- Provide guidance for Long-Term Recovery Concept
of Operation (post phase 2C 30 days) - Procedure for Battle Captain request (21 O3s
from Fort Leonard Wood Captains Career Course) - - Process to request Title 10 (Active
Duty/USAR) / FEST teams to support LRD Operations - - Use of DOD/NORTHCOM Assets/Habitual
Associations - - Integration of 416th TEC, USAR
- Adjudication of Permanent Cadre/Team
Leaders/Assistant Team Leaders/ Local Government
Liaisons - USACE acreage at projects for joint use as
staging area for ARNG/USAR missions - Integration of dual status commanders in USACE HQ
OPLAN - Rules of Engagement (ROE) for earthquake
aftershocks - Navigation Assessments priority
- Timeline for updated HQ OPLAN 2010-70 dtd 21 DEC
2010 USACE Response to a Catastrophic Earthquake
in the New Madrid Seismic Zone