Title: Harmonized SBD-Works
1WORLD BANK
Seminar on Procurement of Goods, Works and
Consultancy Contracts financed from World Bank
Loans and IDA Credits, February 27 - March 3,
2006, Zagreb, Croatia.
2 Harmonized SBD-Works Module Objectives
- Review Standard Bidding Documents
- Procurement of Works
- When to use it?
- How to use it?
3SBD Table of Contents
SECTION SUBJECT I INSTRUCTIONS TO
BIDDERS II BID DATA SHEET III EVALUATION
QUALIFICATION CRITERIA (two alternatives w
w/o pre-qualification) IV BIDDING
FORMS V ELIGIBLE COUNTRIES VI WORKS
REQUIREMENTS VII GENERAL CONDITIONS (OF
CONTRACT) FIDIC GC 1999 with adaptations under
licence agreement VIII PARTICULAR
CONDITIONS IX ANNEX TO THE PARTICULAR CONDITIONS
- CONTRACT FORMS USERS GUIDE
4When to Use it?
- Procurement of Works (large contracts)
- May include supply/installation of some plant
- Design provided by Employer
- Alternative SBDs
- Civil Law Version of SBD
- SBD for Smaller Contracts
5How to Use it?
- Sections I (ITB) and VII (GC) w/o changes
- Sections II (BDS), III (EQC), VI (WR), VIII (PC)
to be filled suitably
6BID DATA SHEETCritical Entries
- Pre-Bid Meeting (ITB 7.4)
- Alternative Bids (ITB 13)
- Fixed or Adjustable Prices (ITB 14.5)
- Source and Date of Exchange Rates for Conversion
of Currencies (ITB 32.1)
7EVALUATION AND QUALIFICATION CRITERIA
- Bid Evaluation Criteria, and
- Bidder Qualification Criteria
- are applied separately!
8BID EVALUATION CRITERIA
- Technical Compliance/ Non Compliance
- Bid Price
- Alternative Completions Time and/or Technical
Alternatives evaluated in accordance with ITB/BDS - Adjustments for non material deviations if any
- No Use of Merit Point System
9BIDDER QUALIFICATION CRITERIA
- Two alternatives
- Pre-Qualification
- No Pre-Qualification
10FOLLOWING PRE- QUALIFICATION
- Verification of Continued Qualification
- Financial Resources (to meet Cash Flow
Requirement) - Personnel Requirements
- Equipment Requirements
- In Principle all Pass/Fail Criteria
11IF NO PRE- QUALIFICATION
- Eligibility Requirements
- Historical Contract Non Performance
- Financial Situation
- Historical Financial Performance
- Average Annual Construction Turnover
- Financial Resources
- Experience
- General Construction Experience
- Specific Construction Experience
- Personnel Requirements
- Equipment Requirements
- All Pass/Fail Criteria
12PARTICULAR CONDITIONS
- Part A - Contract Data
- Time for Completion
- Performance Security
- Sections of Works
- Delay Damages (LDs)
- Advance Payment and Reimbursement
- Retention Money
- Payment for Plant/Material
- Maximum Liability of Contractor to Employer
- Insurance Specifics
- Resolution of Disputes Mechanism Dispute Board
13PARTICULAR CONDITIONS
- Part B Specific Provisions
- Provision on Import Duties on Contractors
Equipment
14Appendix to Bid
- Includes Critical Contract Data
- Schedule of Adjustment Data (Price Adjustment)
for local and foreign currency payments - Summary of Payment Currencies (breakdown) for the
various Sections of Works