CONSTRUCTION CONTRACTS - PowerPoint PPT Presentation

1 / 83
About This Presentation
Title:

CONSTRUCTION CONTRACTS

Description:

Construction Contracts. Provides, based on what is known at the time of contract, for what is ultimately Deliverable, by When and at what Price; Deals with a – PowerPoint PPT presentation

Number of Views:292
Avg rating:3.0/5.0
Slides: 84
Provided by: coz52
Category:

less

Transcript and Presenter's Notes

Title: CONSTRUCTION CONTRACTS


1
CONSTRUCTION CONTRACTS
  • 2014

2
Contracts
It is not the beauty of a building you should
look at its the
construction of the foundation that will stand
the
test of time. -
Unknown
3
Construction Contracts
  • Provides, based on what is known at the time of
    contract, for what is ultimately Deliverable, by
    When and at what Price
  • Deals with a relationship (not necessarily
    founded on good faith, mutual cooperation and
    trust) just as much as it deals with the
    Deliverable.
  • Defines or restricts the extent to which the
    common law would otherwise govern the
    relationship.
  • Defines the relationship - it is not a mere
    formality in the process.

4
Construction Contracts
  • The Deliverable To define the Deliverable, with
    the degree of accuracy possible at the time, and
    to allow the Deliverable to evolve in a
    controlled manner
  • The Price To define the Price of the Deliverable
    based on what is known and what ought to be
    reasonably foreseeable to an experienced
    contractor at the time, and to provide for the
    Price to change in a controlled manner

5
Construction Contracts
  • The When To define the Time for Completion of
    the Deliverable based on what is known and what
    ought to be reasonably foreseeable to an
    experienced contractor at the time, and to allow
    the Time for Completion to change in a controlled
    manner
  • The Risks To respectively allocate the
    foreseeable and unforeseeable / likely and
    unlikely risks to each of the Parties and
  • Possible Disputes To provide a mechanism to
    principally avoid, but to otherwise effectively
    deal with disputes.

6
THOUGHT FOR THE DAY
  • The type of contract form to be used will depend
    on the Employers preference as well as the
    Works to be executed
  • Many employers use standard form contracts
    developed and published by industry-based
    organisations
  • The idea of standard form contracts is to include
    provisions which are beneficial to both parties
    to the contract in accordance with good practice
  • Some contracts are, however, not based on the
    approach of good practice
  • Therefore it is important to know the three Rs

7
THOUGHT FOR THE DAY
  • The type of contract form to be used will depend
    on the Employers preference as well as the
    Works to be executed
  • Many employers use standard form contracts
    developed and published by industry-based
    organisations
  • The idea of standard form contracts is to include
    provisions which are beneficial to both parties
    to the contract in accordance with good practice
  • Some contracts are, however, not based on the
    approach of good practice
  • Therefore it is important to know the three Rs
  • Rights

8
THOUGHT FOR THE DAY
  • The type of contract form to be used will depend
    on the Employers preference as well as the
    Works to be executed
  • Many employers use standard form contracts
    developed and published by industry-based
    organisations
  • The idea of standard form contracts is to include
    provisions which are beneficial to both parties
    to the contract in accordance with good practice
  • Some contracts are, however, not based on the
    approach of good practice
  • Therefore it is important to know the three Rs
  • Rights
  • Responsibilities

9
THOUGHT FOR THE DAY
  • The type of contract form to be used will depend
    on the Employers preference as well as the
    Works to be executed
  • Many employers use standard form contracts
    developed and published by industry-based
    organisations
  • The idea of standard form contracts is to include
    provisions which are beneficial to both parties
    to the contract in accordance with good practice
  • Some contracts are, however, not based on the
    approach of good practice
  • Therefore it is important to know the three Rs
  • Rights
  • Responsibilities
  • Risks

10
THOUGHT FOR THE DAY
  • The type of contract form to be used will depend
    on the Employers preference as well as the
    Works to be executed
  • Many employers use standard form contracts
    developed and published by industry-based
    organisations
  • The idea of standard form contracts is to include
    provisions which are beneficial to both parties
    to the contract in accordance with good practice
  • Some contracts are, however, not based on the
    approach of good practice
  • Therefore it is important to know the three Rs
  • Rights
  • Responsibilities
  • Risks
  • Within standard form contracts you will find your
    three Rs within the General Conditions of
    Contract read together with the amendments
    thereto as set out in the Contract Data and
    Special / Particular Conditions

11
THOUGHT FOR THE DAY
  • The type of contract form to be used will depend
    on the Employers preference as well as the
    Works to be executed
  • Many employers use standard form contracts
    developed and published by industry-based
    organisations
  • The idea of standard form contracts is to include
    provisions which are beneficial to both parties
    to the contract in accordance with good practice
  • Some contracts are, however, not based on the
    approach of good practice
  • Therefore it is important to know the three Rs
  • Rights
  • Responsibilities
  • Risks
  • Within standard form contracts you will find your
    three Rs within the General Conditions of
    Contract read together with the amendments
    thereto as set out in the Contract Data and
    Special / Particular Conditions
  • The obvious benefit of the standard form is
    common understanding and the resultant efficiency
    in Tender and Execution Phases.

12
THOUGHT FOR THE DAY
  • The role players are
  • Employer
  • Main Contractor
  • Sub-contractor
  • (Designer / Supplier / Manufacturer etc)
  • Importantly
  • Familiarise yourself with the contract
  • Be aware of all changes to standard form
    contracts
  • Strict compliance

13
  • Integrity,quality,consistency.

14
  • Standard Forms

15
Available standard forms
  • What Standard Forms are available for use (and
    required to be used by State Owned Entities)

16
Available standard forms
  • The FIDIC Suite (latest is 1999)
  • Silver Book EPC
  • Yellow Book Design Build
  • Red Book Construction Work and
  • Green Book Minor Work.

17
Available standard forms
  • New Engineering Contract

18
Available standard forms
  • New Engineering Contract
  • Engineering and Construction Contract

19
Available standard forms
  • New Engineering Contract
  • Engineering and Construction Contract
  • Construction Short Contract

20
Available standard forms
  • New Engineering Contract
  • Engineering and Construction Contract
  • Construction Short Contract
  • Joint Building Contracts Committee Series 2000
    (5th Edition 2007)

21
Available standard forms
  • New Engineering Contract
  • Engineering and Construction Contract
  • Construction Short Contract
  • Joint Building Contracts Committee Series 2000
    (5th Edition 2007)
  • Principal Building Agreement

22
Available standard forms
  • New Engineering Contract
  • Engineering and Construction Contract
  • Construction Short Contract
  • Joint Building Contracts Committee Series 2000
    (5th Edition 2007)
  • Principal Building Agreement
  • N/S Subcontract

23
Available standard forms
  • New Engineering Contract
  • Engineering and Construction Contract
  • Construction Short Contract
  • Joint Building Contracts Committee Series 2000
    (5th Edition 2007)
  • Principal Building Agreement
  • N/S Subcontract
  • General Conditions of Contract for Construction
    (2004)

24
Available standard forms
  • The standard forms of contracts can, and usually
    will, be changed to fit the different
    requirements for different projects or to suit
    the requirements of a particular employer
  • These conditions may change the rights and
    responsibilities of the employer and contractor

25
Global reachlocal specialistknowledge.
26
  • Before Signing

27
Before signing
  • Completion Date

28
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus

29
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based

30
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based
  • Bond Requirements
  • Performance
  • Retention
  • Advanced Payments

31
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based
  • Bond Requirements
  • Performance
  • Retention
  • Advanced Payments
  • Penalties

32
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based
  • Bond Requirements
  • Performance
  • Retention
  • Advanced Payments
  • Penalties
  • Material Terms

33
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based
  • Bond Requirements
  • Performance
  • Retention
  • Advanced Payments
  • Penalties
  • Material Terms
  • Programming Requirements

34
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based
  • Bond Requirements
  • Performance
  • Retention
  • Advanced Payments
  • Penalties
  • Material Terms
  • Programming Requirements
  • Entitlements to Extension of Time and Additional
    Costs
  • Variation Orders
  • Omissions
  • Delays

35
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based
  • Bond Requirements
  • Performance
  • Retention
  • Advanced Payments
  • Penalties
  • Material Terms
  • Programming Requirements
  • Entitlements to Extension of Time and Additional
    Costs
  • Variation Orders
  • Omissions
  • Delays
  • Limitation of Liability

36
Before signing
  • Completion Date
  • Contract Price
  • Lump Sum / Re-measurable
  • CPA?
  • Cost Plus
  • Payment Structures Progress / milestone based
  • Bond Requirements
  • Performance
  • Retention
  • Advanced Payments
  • Penalties
  • Material Terms
  • Programming Requirements
  • Entitlements to Extension of Time and Additional
    Costs
  • Variation Orders
  • Omissions
  • Delays
  • Limitation of Liability
  • Resolution of Anticipated Disputes

37
  • Integrity,quality,consistency.

38
  • Contract Phases

39
Contract Phases
40
Contract Phases
41
Contract Phases
42
Contract Phases
43
Contract Phases
44
Global reachlocal specialistknowledge.
45
  • Its not just a contract

46
Construction Contracts its not just a
contract
  • An evolving merx against a backdrop (very often
    over an extended period of time) of evolving
    circumstances (both unforeseeable and
    foreseeable, albeit not always predictable).
  • Reasonable programming.
  • Breach (albeit not material) is expected. A
    degreed of breach is the rule rather than the
    exception and events or circumstances giving rise
    to disputes are common place not because of the
    nature of the industry players but rather the
    nature of activity.
  • Risk is considered (not avoided at all costs),
    understood and allocated.

47
Construction Contracts its not just a
contract
  • Principal Drivers Traditional Time, Cost and
    Quality modern approach includes Health
    Safety.
  • Quality Workmanship and Performance (as
    appropriate).
  • Time and Cost are moving targets - One of the
    Parties has to accept the risk. The extent / lack
    of planning and the proper allocation of risk
    are a key factors in Time and Cost optimisation.
  • Health Safety statutory requirements and
    corporate policy considerations. The concept of
    best practice and zero harm is most often
    required and/or adopted in mature jurisdictions
    and by responsible corporations.

48
Construction Contracts its not just a
contract
  • Main Contractor Rights
  • Timeous Payments

49
Construction Contracts its not just a
contract
  • Main Contractor Rights
  • Timeous Payments
  • Variations or alterations

50
Construction Contracts its not just a
contract
  • Main Contractor Rights
  • Timeous Payments
  • Variations or alterations
  • Extensions of Time

51
Construction Contracts its not just a
contract
  • Main Contractor Rights
  • Timeous Payments
  • Variations or alterations
  • Extensions of Time
  • Access to the Employer

52
Construction Contracts its not just a
contract
  • Main Contractor Rights
  • Timeous Payments
  • Variations or alterations
  • Extensions of Time
  • Access to the Employer
  • Dispute Resolution Mechanisms

53
Construction Contracts its not just a
contract
  • Main Contractor Rights
  • Timeous Payments
  • Variations or alterations
  • Extensions of Time
  • Access to the Employer
  • Dispute Resolution Mechanisms
  • Termination of the Contract

54
Construction Contracts its not just a
contract
  • Main Contractor Rights
  • Timeous Payments
  • Variations or alterations
  • Extensions of Time
  • Access to the Employer
  • Dispute Resolution Mechanisms
  • Termination of the Contract
  • Appointment of sub-contractors

55
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works

56
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works
  • Guarantees and insurances

57
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works
  • Guarantees and insurances
  • Administrative procedures
  • Reporting on progress
  • Updated programmes
  • Substantiation of claims
  • Contemporaneous documents

58
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works
  • Guarantees and insurances
  • Administrative procedures
  • Reporting on progress
  • Updated programmes
  • Substantiation of claims
  • Contemporaneous documents
  • Notifications
  • Early Warning
  • Notice of Claim Time periods
  • Fully detailed claim

59
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works
  • Guarantees and insurances
  • Administrative procedures
  • Reporting on progress
  • Updated programmes
  • Substantiation of claims
  • Contemporaneous documents
  • Notifications
  • Early Warning
  • Notice of Claim Time periods
  • Fully detailed claim
  • Security

60
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works
  • Guarantees and insurances
  • Administrative procedures
  • Reporting on progress
  • Updated programmes
  • Substantiation of claims
  • Contemporaneous documents
  • Notifications
  • Early Warning
  • Notice of Claim Time periods
  • Fully detailed claim
  • Security
  • Instructions

61
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works
  • Guarantees and insurances
  • Administrative procedures
  • Reporting on progress
  • Updated programmes
  • Substantiation of claims
  • Contemporaneous documents
  • Notifications
  • Early Warning
  • Notice of Claim Time periods
  • Fully detailed claim
  • Security
  • Instructions
  • Subcontracts
  • Claims

62
Construction Contracts its not just a
contract
  • Main Contractor Responsibilities
  • Completing and Maintaining Works
  • Guarantees and insurances
  • Administrative procedures
  • Reporting on progress
  • Updated programmes
  • Substantiation of claims
  • Contemporaneous documents
  • Notifications
  • Early Warning
  • Notice of Claim Time periods
  • Fully detailed claim
  • Security
  • Instructions
  • Subcontracts
  • Claims
  • Compliance

63
Construction Contracts its not just a
contract
  • Main Contractor Risks
  • Financial Loss
  • Errors in calculations
  • Poor management
  • Delays

64
Construction Contracts its not just a
contract
  • Main Contractor Risks
  • Financial Loss
  • Errors in calculations
  • Poor management
  • Delays
  • Penalties

65
Construction Contracts its not just a
contract
  • Main Contractor Risks
  • Financial Loss
  • Errors in calculations
  • Poor management
  • Delays
  • Penalties
  • Insolvency of Employer

66
Construction Contracts its not just a
contract
  • Main Contractor Risks
  • Financial Loss
  • Errors in calculations
  • Poor management
  • Delays
  • Penalties
  • Insolvency of Employer
  • Termination of the contract
  • Recovery of damages

67
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works

68
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor

69
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor
  • Weaker position

70
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor
  • Weaker position
  • Similar rights to those in Main Contract

71
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor
  • Weaker position
  • Similar rights to those in Main Contract
  • Warning lights in contract
  • Reduction of / set-off from certified payments
  • Pay when paid
  • No DAB / Arbitration Procedure

72
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor
  • Weaker position
  • Similar rights to those in Main Contract
  • Warning lights in contract
  • Reduction of / set-off from certified payments
  • Pay when paid
  • No DAB / Arbitration Procedure
  • Retention percentages

73
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor
  • Weaker position
  • Similar rights to those in Main Contract
  • Warning lights in contract
  • Reduction of / set-off from certified payments
  • Pay when paid
  • No DAB / Arbitration Procedure
  • Retention percentages
  • Defects liability periods

74
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor
  • Weaker position
  • Similar rights to those in Main Contract
  • Warning lights in contract
  • Reduction of / set-off from certified payments
  • Pay when paid
  • No DAB / Arbitration Procedure
  • Retention percentages
  • Defects liability periods
  • Changes to notification periods

75
Construction Contracts its not just a
contract
  • Sub-Contractor
  • Three Rs will mainly depend of Scope of Works
  • Responsibility is towards Main Contractor
  • Weaker position
  • Similar rights to those in Main Contract
  • Warning lights in contract
  • Reduction of / set-off from certified payments
  • Pay when paid
  • No DAB / Arbitration Procedure
  • Retention percentages
  • Defects liability periods
  • Changes to notification periods
  • Time barring

76
Construction Contracts its not just a
contract
  • Important
  • Notification Procedure
  • Time barring
  • Strict Compliance

77
  • Integrity,quality,consistency.

78
dispute now what?
79
Dispute now what?
  • Claims procedure
  • Determination
  • Dispute
  • DAB / Arbitration
  • Court

80
Difference in approachpractical example
81
Difference in approachpractical example
82
questions?
83
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com