Title: CONSTRUCTION CONTRACTS
1CONSTRUCTION CONTRACTS
2Contracts
It is not the beauty of a building you should
look at its the
construction of the foundation that will stand
the
test of time. -
Unknown
3Construction Contracts
- Provides, based on what is known at the time of
contract, for what is ultimately Deliverable, by
When and at what Price - Deals with a relationship (not necessarily
founded on good faith, mutual cooperation and
trust) just as much as it deals with the
Deliverable. - Defines or restricts the extent to which the
common law would otherwise govern the
relationship. - Defines the relationship - it is not a mere
formality in the process.
4Construction Contracts
- The Deliverable To define the Deliverable, with
the degree of accuracy possible at the time, and
to allow the Deliverable to evolve in a
controlled manner - The Price To define the Price of the Deliverable
based on what is known and what ought to be
reasonably foreseeable to an experienced
contractor at the time, and to provide for the
Price to change in a controlled manner
5Construction Contracts
- The When To define the Time for Completion of
the Deliverable based on what is known and what
ought to be reasonably foreseeable to an
experienced contractor at the time, and to allow
the Time for Completion to change in a controlled
manner - The Risks To respectively allocate the
foreseeable and unforeseeable / likely and
unlikely risks to each of the Parties and - Possible Disputes To provide a mechanism to
principally avoid, but to otherwise effectively
deal with disputes.
6THOUGHT FOR THE DAY
- The type of contract form to be used will depend
on the Employers preference as well as the
Works to be executed - Many employers use standard form contracts
developed and published by industry-based
organisations - The idea of standard form contracts is to include
provisions which are beneficial to both parties
to the contract in accordance with good practice - Some contracts are, however, not based on the
approach of good practice - Therefore it is important to know the three Rs
7THOUGHT FOR THE DAY
- The type of contract form to be used will depend
on the Employers preference as well as the
Works to be executed - Many employers use standard form contracts
developed and published by industry-based
organisations - The idea of standard form contracts is to include
provisions which are beneficial to both parties
to the contract in accordance with good practice - Some contracts are, however, not based on the
approach of good practice - Therefore it is important to know the three Rs
- Rights
8THOUGHT FOR THE DAY
- The type of contract form to be used will depend
on the Employers preference as well as the
Works to be executed - Many employers use standard form contracts
developed and published by industry-based
organisations - The idea of standard form contracts is to include
provisions which are beneficial to both parties
to the contract in accordance with good practice - Some contracts are, however, not based on the
approach of good practice - Therefore it is important to know the three Rs
- Rights
- Responsibilities
9THOUGHT FOR THE DAY
- The type of contract form to be used will depend
on the Employers preference as well as the
Works to be executed - Many employers use standard form contracts
developed and published by industry-based
organisations - The idea of standard form contracts is to include
provisions which are beneficial to both parties
to the contract in accordance with good practice - Some contracts are, however, not based on the
approach of good practice - Therefore it is important to know the three Rs
- Rights
- Responsibilities
- Risks
10THOUGHT FOR THE DAY
- The type of contract form to be used will depend
on the Employers preference as well as the
Works to be executed - Many employers use standard form contracts
developed and published by industry-based
organisations - The idea of standard form contracts is to include
provisions which are beneficial to both parties
to the contract in accordance with good practice - Some contracts are, however, not based on the
approach of good practice - Therefore it is important to know the three Rs
- Rights
- Responsibilities
- Risks
- Within standard form contracts you will find your
three Rs within the General Conditions of
Contract read together with the amendments
thereto as set out in the Contract Data and
Special / Particular Conditions
11THOUGHT FOR THE DAY
- The type of contract form to be used will depend
on the Employers preference as well as the
Works to be executed - Many employers use standard form contracts
developed and published by industry-based
organisations - The idea of standard form contracts is to include
provisions which are beneficial to both parties
to the contract in accordance with good practice - Some contracts are, however, not based on the
approach of good practice - Therefore it is important to know the three Rs
- Rights
- Responsibilities
- Risks
- Within standard form contracts you will find your
three Rs within the General Conditions of
Contract read together with the amendments
thereto as set out in the Contract Data and
Special / Particular Conditions - The obvious benefit of the standard form is
common understanding and the resultant efficiency
in Tender and Execution Phases.
12THOUGHT FOR THE DAY
- The role players are
- Employer
- Main Contractor
- Sub-contractor
- (Designer / Supplier / Manufacturer etc)
- Importantly
- Familiarise yourself with the contract
- Be aware of all changes to standard form
contracts - Strict compliance
13- Integrity,quality,consistency.
14 15Available standard forms
- What Standard Forms are available for use (and
required to be used by State Owned Entities)
16Available standard forms
- The FIDIC Suite (latest is 1999)
- Silver Book EPC
- Yellow Book Design Build
- Red Book Construction Work and
- Green Book Minor Work.
17Available standard forms
18Available standard forms
- New Engineering Contract
- Engineering and Construction Contract
19Available standard forms
- New Engineering Contract
- Engineering and Construction Contract
- Construction Short Contract
20Available standard forms
- New Engineering Contract
- Engineering and Construction Contract
- Construction Short Contract
- Joint Building Contracts Committee Series 2000
(5th Edition 2007)
21Available standard forms
- New Engineering Contract
- Engineering and Construction Contract
- Construction Short Contract
- Joint Building Contracts Committee Series 2000
(5th Edition 2007) - Principal Building Agreement
22Available standard forms
- New Engineering Contract
- Engineering and Construction Contract
- Construction Short Contract
- Joint Building Contracts Committee Series 2000
(5th Edition 2007) - Principal Building Agreement
- N/S Subcontract
23Available standard forms
- New Engineering Contract
- Engineering and Construction Contract
- Construction Short Contract
- Joint Building Contracts Committee Series 2000
(5th Edition 2007) - Principal Building Agreement
- N/S Subcontract
- General Conditions of Contract for Construction
(2004)
24Available standard forms
- The standard forms of contracts can, and usually
will, be changed to fit the different
requirements for different projects or to suit
the requirements of a particular employer - These conditions may change the rights and
responsibilities of the employer and contractor
25Global reachlocal specialistknowledge.
26 27Before signing
28Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
29Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
30Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
- Bond Requirements
- Performance
- Retention
- Advanced Payments
31Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
- Bond Requirements
- Performance
- Retention
- Advanced Payments
- Penalties
32Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
- Bond Requirements
- Performance
- Retention
- Advanced Payments
- Penalties
- Material Terms
33Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
- Bond Requirements
- Performance
- Retention
- Advanced Payments
- Penalties
- Material Terms
- Programming Requirements
34Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
- Bond Requirements
- Performance
- Retention
- Advanced Payments
- Penalties
- Material Terms
- Programming Requirements
- Entitlements to Extension of Time and Additional
Costs - Variation Orders
- Omissions
- Delays
35Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
- Bond Requirements
- Performance
- Retention
- Advanced Payments
- Penalties
- Material Terms
- Programming Requirements
- Entitlements to Extension of Time and Additional
Costs - Variation Orders
- Omissions
- Delays
- Limitation of Liability
36Before signing
- Completion Date
- Contract Price
- Lump Sum / Re-measurable
- CPA?
- Cost Plus
- Payment Structures Progress / milestone based
- Bond Requirements
- Performance
- Retention
- Advanced Payments
- Penalties
- Material Terms
- Programming Requirements
- Entitlements to Extension of Time and Additional
Costs - Variation Orders
- Omissions
- Delays
- Limitation of Liability
- Resolution of Anticipated Disputes
37- Integrity,quality,consistency.
38 39Contract Phases
40Contract Phases
41Contract Phases
42Contract Phases
43Contract Phases
44Global reachlocal specialistknowledge.
45 46Construction Contracts its not just a
contract
- An evolving merx against a backdrop (very often
over an extended period of time) of evolving
circumstances (both unforeseeable and
foreseeable, albeit not always predictable). - Reasonable programming.
- Breach (albeit not material) is expected. A
degreed of breach is the rule rather than the
exception and events or circumstances giving rise
to disputes are common place not because of the
nature of the industry players but rather the
nature of activity. - Risk is considered (not avoided at all costs),
understood and allocated.
47Construction Contracts its not just a
contract
- Principal Drivers Traditional Time, Cost and
Quality modern approach includes Health
Safety. - Quality Workmanship and Performance (as
appropriate). - Time and Cost are moving targets - One of the
Parties has to accept the risk. The extent / lack
of planning and the proper allocation of risk
are a key factors in Time and Cost optimisation. - Health Safety statutory requirements and
corporate policy considerations. The concept of
best practice and zero harm is most often
required and/or adopted in mature jurisdictions
and by responsible corporations.
48Construction Contracts its not just a
contract
- Main Contractor Rights
- Timeous Payments
49Construction Contracts its not just a
contract
- Main Contractor Rights
- Timeous Payments
- Variations or alterations
50Construction Contracts its not just a
contract
- Main Contractor Rights
- Timeous Payments
- Variations or alterations
- Extensions of Time
51Construction Contracts its not just a
contract
- Main Contractor Rights
- Timeous Payments
- Variations or alterations
- Extensions of Time
- Access to the Employer
52Construction Contracts its not just a
contract
- Main Contractor Rights
- Timeous Payments
- Variations or alterations
- Extensions of Time
- Access to the Employer
- Dispute Resolution Mechanisms
53Construction Contracts its not just a
contract
- Main Contractor Rights
- Timeous Payments
- Variations or alterations
- Extensions of Time
- Access to the Employer
- Dispute Resolution Mechanisms
- Termination of the Contract
54Construction Contracts its not just a
contract
- Main Contractor Rights
- Timeous Payments
- Variations or alterations
- Extensions of Time
- Access to the Employer
- Dispute Resolution Mechanisms
- Termination of the Contract
- Appointment of sub-contractors
55Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
56Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
- Guarantees and insurances
57Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
- Guarantees and insurances
- Administrative procedures
- Reporting on progress
- Updated programmes
- Substantiation of claims
- Contemporaneous documents
58Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
- Guarantees and insurances
- Administrative procedures
- Reporting on progress
- Updated programmes
- Substantiation of claims
- Contemporaneous documents
- Notifications
- Early Warning
- Notice of Claim Time periods
- Fully detailed claim
59Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
- Guarantees and insurances
- Administrative procedures
- Reporting on progress
- Updated programmes
- Substantiation of claims
- Contemporaneous documents
- Notifications
- Early Warning
- Notice of Claim Time periods
- Fully detailed claim
- Security
60Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
- Guarantees and insurances
- Administrative procedures
- Reporting on progress
- Updated programmes
- Substantiation of claims
- Contemporaneous documents
- Notifications
- Early Warning
- Notice of Claim Time periods
- Fully detailed claim
- Security
- Instructions
61Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
- Guarantees and insurances
- Administrative procedures
- Reporting on progress
- Updated programmes
- Substantiation of claims
- Contemporaneous documents
- Notifications
- Early Warning
- Notice of Claim Time periods
- Fully detailed claim
- Security
- Instructions
- Subcontracts
- Claims
62Construction Contracts its not just a
contract
- Main Contractor Responsibilities
- Completing and Maintaining Works
- Guarantees and insurances
- Administrative procedures
- Reporting on progress
- Updated programmes
- Substantiation of claims
- Contemporaneous documents
- Notifications
- Early Warning
- Notice of Claim Time periods
- Fully detailed claim
- Security
- Instructions
- Subcontracts
- Claims
- Compliance
63Construction Contracts its not just a
contract
- Main Contractor Risks
- Financial Loss
- Errors in calculations
- Poor management
- Delays
64Construction Contracts its not just a
contract
- Main Contractor Risks
- Financial Loss
- Errors in calculations
- Poor management
- Delays
- Penalties
65Construction Contracts its not just a
contract
- Main Contractor Risks
- Financial Loss
- Errors in calculations
- Poor management
- Delays
- Penalties
- Insolvency of Employer
66Construction Contracts its not just a
contract
- Main Contractor Risks
- Financial Loss
- Errors in calculations
- Poor management
- Delays
- Penalties
- Insolvency of Employer
- Termination of the contract
- Recovery of damages
67Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
68Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
69Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
- Weaker position
70Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
- Weaker position
- Similar rights to those in Main Contract
71Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
- Weaker position
- Similar rights to those in Main Contract
- Warning lights in contract
- Reduction of / set-off from certified payments
- Pay when paid
- No DAB / Arbitration Procedure
72Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
- Weaker position
- Similar rights to those in Main Contract
- Warning lights in contract
- Reduction of / set-off from certified payments
- Pay when paid
- No DAB / Arbitration Procedure
- Retention percentages
73Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
- Weaker position
- Similar rights to those in Main Contract
- Warning lights in contract
- Reduction of / set-off from certified payments
- Pay when paid
- No DAB / Arbitration Procedure
- Retention percentages
- Defects liability periods
74Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
- Weaker position
- Similar rights to those in Main Contract
- Warning lights in contract
- Reduction of / set-off from certified payments
- Pay when paid
- No DAB / Arbitration Procedure
- Retention percentages
- Defects liability periods
- Changes to notification periods
75Construction Contracts its not just a
contract
- Sub-Contractor
- Three Rs will mainly depend of Scope of Works
- Responsibility is towards Main Contractor
- Weaker position
- Similar rights to those in Main Contract
- Warning lights in contract
- Reduction of / set-off from certified payments
- Pay when paid
- No DAB / Arbitration Procedure
- Retention percentages
- Defects liability periods
- Changes to notification periods
- Time barring
76Construction Contracts its not just a
contract
- Important
- Notification Procedure
- Time barring
- Strict Compliance
77- Integrity,quality,consistency.
78dispute now what?
79Dispute now what?
- Claims procedure
- Determination
- Dispute
- DAB / Arbitration
- Court
80Difference in approachpractical example
81Difference in approachpractical example
82questions?
83(No Transcript)