Title: Shoppes at Park Place Option
1Shoppes at Park Place Option
June 27, 2012
1
2Background
- March 2012 PSTA Approves Policy to Staff all
PSTA Restrooms - April 2012
- Pinellas Park Confirms 100K only for
Constructing Restroom. No Operating Assistance. - Mall requires restroom or no or very reduced bus
traffic. No Operating or Capital Assistance. No
interest in building retail. - May 2012
- PSTA Completes Rider Survey, Identifies
Re-Routing Solution - PSTA Receives Tentative Acceptance of Re-Routing
Plan by City Mall. - June 2012 PSTA Receives Improved Operating
Revenue Forecasts
2
3Shoppes at Park Place - 5
4PSTAs Highest Activity Bus Stops
No. Stop/Terminal Estimated Daily Boardings 2/2012
1 Grand Central Terminal 5,526
2 Park Street Terminal 2,396
3 Williams Park 2,277
4 Tyrone Square Mall 1,219
5 Shoppes at Park Place 991
6 Tri-City Plaza (US19 in Largo) 945
7 75th Gulf Blvd. 905
8 Largo Mall 550
9 Gateway Mall 476
10 Clearwater Beach/Pier 60 401
11 Clearwater Mall 379
12 Seminole Mall 345
13 Johns Pass 334
14 PSTA Facility 293
15 Countryside Mall 284
16 Bay Pines Medical Center 196
17 Indian Rocks Shopping Center 174
4
5(No Transcript)
6(No Transcript)
7Rank Both Directions Both Directions Trips Affected Per Day New Location for Transfer
1 Rte. 19 (U.S. 19) Route 74 (Park/Gandy) 0 No Change
2 Rte. 19 (U.S. 19) Route 52 (49th Street) 45 Roosevelt/19
3 Rt. 52 (49th Street) Route 74 (Park/Gandy) 37 49th Park
4 Rt. 52 (49th Street) To Shoppes _at_ Park Pl. 35 NA
4 Rt. 19 (U.S. 19) Route 75 (54th Ave.) 19 62nd Ave/19
5 Rt. 52 (49th Street) Route 11 (28th Street) 16 PSTA (M-F)
6 Rt. 11(28th Street) Route 74 (Park/Gandy) 13 On-Street 19/74
7 Rt. 52 (49th Street) Route 75 (54th Ave.) 11 49th 54th Ave.
8 Total 176
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12Estimated Costs
Item Option A Route Alignment Option B Build Restroom Option C Build Mid-County Terminal
Facility Capital Cost 200,000 400,000
- Less Pinellas Park Capital Contribution (100,000) (100,000)
Road Repair Fence 30,000 30,000 30,000
Total Net One-Time Capital Costs 30,000 130,000 330,000
Route Realignment Costs 15,000 0 0
Contracted Custodial 35,000 35,000
Contracted Security 30,000 30,000
Customer Service Representatives 140,000
Total Annual Operating Costs 15,000 65,000 205,000
Recommended
12
13Benefits/Issues with Mid-County Terminal
- Benefits
- Can be afforded thanks to increased revenues.
- Will be significant improvement in Medicaid TD
Pass Distribution for Mid-County Riders. - Mid-County Terminal meets needs of Highest
Ridership Region of County - Complies with PSTA Policy.
- Issues
- If Major LRT Station Constructed East of US 19,
Terminal may be relocated in approx. 10 Years
13