Title: Green Emotion WP 4
1Green EmotionWP 4 Grid Evolution, Task 1 -
Functional and Design Requirements of
Infrastructure
- Presented by Philip LeGoy ESB ecars
- 3rd Stakeholder Forum, 22 November 2011, Paris
2Overview of installed EV Charge Point
infrastructure
- Work Package 4 Grid Evolution
- WP4 Objective
- Use the numerous on-going demonstration field
trials and infrastructure roll outs of the
consortium of project partners to develop the
tools and requirements of an EV charging grid
infrastructure - Which provides for adequate capacity
- Which is user friendly to the EV customer and
provides for their needs - Which is developed with broadly accepted economic
and technical principles and agreed standards of
safety
3Overview of installed EV Charge Point
infrastructure
- Work Package 4 Grid Evolution
- The Proposed system for WP4
- Will integrate all existing standards and
incorporate new standards which are currently
under development - Will be fully integrated with the transmission
and distribution grid - Will facilitate EV charging by any EV customer,
traveling anywhere in Europe - Will enable the provision of EV power
requirements to Renewable Energy Resources - There are 5 tasks in WP4
4Overview of installed EV Charge Point
infrastructure
- Work Package 4 Grid Evolution
- Tasks 1 to 5
- Pan-European requirements on recharging
infrastructure including installation and
operational aspects - EV charge management inclding Communication
protocols - The smart (distribution) grid from demonstration
to mass market deployment - Guidelines for infrastructure deployment from
utility perspective - Survey of new functionalities
5Overview of installed EV Charge Point
infrastructure
- Work Package 4 Grid Evolution
- Task 1 undertaken by ESB ecars
- Functional and Design Requirements of
Infrastructure - This task is designed to collect data on the
hardware, software and costs of installation of
infrastructure as installed across Europe - There are two surveys that have been distributed
to project participants and a few selected
stakeholders. - The first survey is a Technical Survey for
infrastructure - The second is a Cost/Price Survey for cost/price
of installed infrastructure - Data collected will be passed to other Tasks in
the Green eMotion project for integration,
analysis and evaluation - The deadline for final report for this task is
T12 - February 2012
6Overview of installed EV Charge Point
infrastructure
- Work Package 4, Task 1 Data Collection
- Brief Update of data collected at present
- Infrastructure data shows there are 3 major
categories - Public and On Street Charging Infrastructure
- Fast Charging Infrastructure
- Home Charging Infrastructure
7Overview of installed EV Charge Point
infrastructure
- Work Package 4, Task 1 Data
- Public/Private and On Street Charging
- Generally specified is the mode 3 type 2 socket
- Some mode 1, mode 2 Schuko and legacy 3 pin
sockets are installed - Most installations are equipped with GPRS, PLCs
and electrical gear - In street charge post meters are generally
specified as revenue grade meters - Generally all participants have chosen a 22kW,
3?, 32A, 230V AC design. - Street posts vary from 3.52kW per socket to 44kW
per socket
8Overview of installed EV Charge Point
infrastructure
- Work Package 4, Task 1 Data
- Public Fast Charging
- Generally DC Fast Charging is the method used
across the project participants. - Generally specified as 50kW mode 4 CHAdeMO
- Most installations are equipped with GPRS, PLCs
and electrical gear - Some have a 44kW, 3?, 63A, 230V AC unit that also
fast charges EVs - Generally specified AC 44kW Mode 3 Type 2
- Currently one participant have reported they have
installed 1 battery swap station and they are in
the process of installing 9 more
9Overview of installed EV Charge Point
infrastructure
- Work Package 4, Task 1 Data
- Home Charging
- Generally the participants are installing 13A to
32A home charge points. - Generally specified for utility pilot projects
are AC Mode 3 Type 2 - Customers have installed a variety of
configurations - Generally multiple tariffs are available to
customers - Generally a separate dedicated circuit is
installed in the customers home distribution
system inside the boundary of the customer meter
10Overview of installed EV Charge Point
infrastructure
- Work Package 4, Task 1 Data
- Price/Cost of Public/Private and Street Charging
- The average costs of Public/Private charging
infrastructure vary as shown in the data
collected so far. - The variation in costs goes from 3200 to 7000
including installation and ancillary equipment on
a per charge post basis.
11Overview of installed EV Charge Point
infrastructure
- Work Package 4, Task 1 Data
- Price/Cost of Fast Charging
- DC Fast Charging
- DC charging units vary in price from 13k to
50k. - Installation costs vary from 3500 to 6000
- AC Fast Charging
- No information yet
12Overview of installed EV Charge Point
infrastructure
- Work Package 4, Task 1 Data
- Price/Cost of Home Charging
- Home charging units vary from 770 to 1500
including installation
13Preliminary Conclusions
- Generalized Preliminary Conclusions
- In general there is a trend toward Mode 3, Type 2
street post infrastructure at about 22kW per
socket for Public/Private and street charging - In general there is a trend toward fast charging
of the DC variety - Home charging appears to be Mode 3, Type 2 which
is being installed for the most part, by the
participants in their pilot projects, in all
areas across Europe - The data shows in southern Europe there are some
Mode 1 and Mode 2 Schuko sockets being installed
14Work Package 4, Task 1
External Stakeholders are invited to participate
in one or both surveys. If this is something you
would be interested in please let me know after
the meeting. From ESB ecars Thank You for Your
Time Questions?