MESA COUNTY WHITEWATER PUBLIC IMPROVEMENT
DISTRICT
Collection system and initial service area is
located on the southwest side of Highway 50. All
future expansion of the system will be
development driven.
2
MESA COUNTY WHITEWATER PUBLIC IMPROVEMENT
DISTRICT SERVICE TIMELINE
  • Construction of Collection System to be
    complete March 2009
  • Selection of Design firm for Lift Station and
    Force Main to Clifton Sanitation to be Awarded in
    March 2009
  • Public Meetings will be held during the Design
    Phase
  • Approval of User Fees and Tap Fees for the
    District Summer of 2009. Public will be
    Notified.
  • Estimated time for Construction of Lift Station
    and Force Main Fall of 2009
  • Estimate Completion of Construction early 2010.
  • Property Owners who are able to be served will
    be notified and tap applications and fees will be
    collected at that time.
  • Any additional questions please contact Julie
    Constan or Connie Hahn of Mesa County Public
    Works/Engineering at 970-244-1765.