Title: TANZANIA ELECTRIC SUPPLY COMPANY LIMITED


1
TANZANIA ELECTRIC SUPPLY COMPANY LIMITED
  • Tanzania Electricity Power Projects and Available
    Opportunities
  • PRESENTATION TO TEXTILE DEVELOPMENT UNIT (
    TEXTILE INDUSTRY LEADERS TANZANIA)
  • NEW AFRICA HOTEL - DAR ES SALAAM, TANZANIA
  • By
  • Managing Director- TANESCO
  • Eng. Felchesmi J. Mramba

2
Contents
  1. Introduction
  2. Background and History of TANESCO
  3. Current Status
  4. Ongoing and Upcoming Projects
  5. Current Projects.
  6. Conclusion

3
1. Introduction
4
1. Introduction ()
  • Area 945, 203 km2
  • Tanzania is in East Africa has a population of
    45 million people (NBS census 2012).
  • Population growth 3
  • GDP USD33.23 billion in 2013 (World Bank)
  • Customer base 1,409, 966 (as at 31/12/2014)
  • Access to electricity 36
  • Connectivity 27 (as at 31/12/2014)
  • Maximum Demand 934.62MW ( as at December 2014)

5
Introduction ()Future Power Demand 2015 2025
(PSMP 2012)
2015 2020 2025
NATIONAL DEMAND 935 3,423 4,574
SOUTHERN POWER POOL (MOZAMBIQUE ZAMBIA) 100 100
EAST AFRICA POWER POOL (RWANDA BURUNDI) 50 50
ETHIOPIA Import Import
TOTAL 935 3,573 4,724
6
Introduction
Available Energy Sources
S/NO ENERGY RESOURCE POTENTIAL DEVELOPED TO POWER
1 Gas 55Tcf 441MW
2 Hydro Various sites 4.7GW 562MW
3 Geothermal 58 sites 5,000MW None
4 Coal 1.9 billion tons None
5 Uranium Oxide 24,550 tons None
6 Wind 7 sites Average wind speed 5 8m/s None
7 Biomass wood fuel and agricultural waste 500MW 35MW
8 Solar Several sites Average daily solar insolation 4.6/kWh/m2 About 4MW
9 Tidal Under study None
7
2. Background and History of TANESCO
  • A vertically integrated Parastatal organization
    under the Ministry of Energy and Minerals
  • Established in 1964
  • Incorporated under the Companies Ordinance Cap
    212 (now Company Act)
  • Directed by the Board of Directors
  • The Ministry of Energy and Minerals (MEM) is
    responsible for policy formulation and overall
    sector supervision.

8
2. Background and History of TANESCO
  • The Energy and Water Utilities Regulatory
    Authority (EWURA) is the sector regulator.
  • TANESCO Core business are Generation,
    Transmission and Distribution of electricity
  • Sales electricity to the mainland and bulk power
    supply to the Island of Zanzibar.

9
Current Status ()
  • Power Generation Mix
  • The installed capacity in the main grid is
    1226.24MW. Hydro 561.84 MW (46) and Thermal
    664.4 MW (54).
  • Capacity of thermal plants (Gas 441MW Fuel Oil
    223.4 MW)
  • Off-grid stations total capacity is 73.77 MW
  • Highest grid system demand is 934.62 MW recorded
    in December 2014 .

10
Current Status ()
  • .
  • Transmission System
  • Transmission network comprises of 2,732 km of
    220kV lines 1,555.79 km of 132 kV lines and
    578.7 km of 66 kV lines, totalling 4,866.85km by
    the end of December 2014.
  • Distribution System
  • Total distribution network (MV lines) is 20,704
    km, constituting 15,176 km of 33kV line, 5,528km
    of 11kV lines and 40,094 km of low voltage (400
    and 230V) lines.

11
4. Ongoing and Upcoming Projects
Kinyerezi I Under Construction
12
Ongoing and Upcoming Projects
S/NO PROJECT DESCRPTION SOURCE OF FUNDING PROJECT COST STATUS COMPLETION DATE
1 Kinyerezi I - 150MW gas fired power plant GoT USD 183m Construction 90 completed SEPTEMBER 2015
2 Kinyerezi II 240MW gas fired power plant GoT - 15 JBIC 85 Contractor Sumitomo Corporation USD 344million GoT is soliciting funds for financing the 15 of the contract value of the project 2017
3 Kinyerezi III 600MW gas fired power plant China Power Investment (CPI) USD 401million JV Company formed and feasibility study is under review TBA
4 Kinyerezi IV 330MW gas fired power plant Poly Technology Inc. of China USD 400million. Preliminary feasibility study is under review TBA
5 Somanga Fungu 320MW Gas Fired Power Plant Kilwa Energy - IPP USD 365.6 Million Investor working with banks to achieve financial closure 2017
13
Ongoing and Upcoming Projects
S/NO PROJECT DESCRPTION SOURCE OF FUNDING PROJECT COST STATUS COMPLETION DATE
6 GeoWind 50MW Wind Power Plant at Singida Exim Bank of China USD 136 Million Discussion to conclude financial closure is in progress 2017
7 150MW Solar PV in Shinyanga Not yet secured USD 185million Under System review and equipment design 2019
8 400MW gas fired power plant at Mtwara with Symbion (T) Symbion USD 396.577million Feasibility study is under review 2019
9 87MW hydropower plant to be developed at Kakono in Kagera Region Not yet secured Estimated cost USD 379.4million Feasibility Study completed Solicitation of financing in progress 2019
10 44.8MW hydropower plant to be developed at Malagarasi river in Kigoma Not yet secured Estimated cost USD 149.5million Feasibility Study completed Solicitation of financing in progress 2020
14
Ongoing and Upcoming Projects
S/NO PROJECT DESCRPTION SOURCE OF FUNDING PROJECT COST STATUS COMPLETION DATE
11 400kV Iringa Shinyanga transmission project (Backbone) IDA, AfDB, JICA, EIB and Korea EDCF USD 470 Million Construction 20 completed June 2016
12 400kV North East Grid Dar Chalinze Tanga - Arusha GoT - 15 Exim Bank of China 85 USD 692.7million GoT is soliciting funds for financing the 15 of the contract value of the project 2017
13 200kV Makambako Songea transmission line SIDA GoT USD 111.43million Distribution component 5 completed 2017
14 400kV North West Grid Phase 1 Mbeya - Sumbawanga Financing not firmed USD 259.2million Contract for upgrading the feasibility study from 220kV to 400kV by SWECO Signed 2018
15 400 kV Singida-Arusha transmission line AfDB, JICA USD 258.82 million Valuation of properties for compensation has started 2018
15
Ongoing and Upcoming Projects
S/NO PROJECT DESCRPTION SOURCE OF FUNDING PROJECT COST STATUS COMPLETION DATE
16 400 kV Chalinze-Dodoma transmission line Financing not firmed Estimated USD 175 million Procurement of Consultant for feasibility study is in progress 2018
17 220 kV Bulyanhulu-Geita transmission line Arab Bank for Economic Development in Africa (BADEA), OFID GoT USD 30million Contract signing with Consultant for project supervision completed 2017
18 220kV T/L Geita Nyakanazi transmission line KfW, AFD, EU GoT Euro 29million TZS 5billion Contract signing with Consultant for project supervision is underway 2017
19 Improving the reliability of Electric power supply in the city of Dar es Salaam Finish EUR. 21.8million Construction 70 completed October, 2015
16
Ongoing and Upcoming Projects
S/NO PROJECT DESCRPTION SOURCE OF FUNDING PROJECT COST STATUS COMPLETION DATE
20 Tanzania Energy Development and Access Expansion Project (TEDAP) - Transmission IDA USD 34,252,345.78 Construction 70 completed March, 2016
21 Tanzania Energy Development and Access Expansion Project (TEDAP) - Distribution IDA USD 43,543,460.07 Construction 60 completed June, 2016
22 Electricity V AfDB GoT USD 51.25million Construction 85 completed October, 2015
17
Ongoing and Upcoming Projects.
S/NO PROJECT DESCRPTION SOURCE OF FUNDING PROJECT COST STATUS COMPLETION DATE
23 New 132kV Kilimanjaro Arusha Transmission Line and Rehabilitation of Kiyungi Substation. Korean Export-Import Bank through EDCF USD 20,176,384 Construction 85 completed December, 2015
24 Rehabilitation of Hale Hydro Plant 21MW Co-financed by SIDA (60 grant) and GoT (40 commercial loan) SEK 197 Million The contract for the technical consultant has been signed 2019
25 Rehabilitation and Upgrade of Grid Network. AFD EUR. 53.0M Procurement of Consultant for supervision of the project is underway 2017
26 Project for Reinforcement of Power Distribution in Dar es salaam Region JICA Japanese Yen 4.41 Billion equivalent to USD 38 Million Contract signing with Consultant for project supervision is underway 2017
18
Future Grid Map by 2035
19
ZAMBIA TANZANIA KENYA (ZTK) TRANSMISSION LINE
20
  • 5 .CURRENT PROJECTS FUNDED BY KOREANS

S/No. PROJECT DESCRIPTION SOURCE OF FUNDING PROJECT COST STATUS COMPLETION DATE
1. Power transmission line expansion project between Kilimanjaro and Arusha Korea Exim Bank EDCF fund (also supported by World Bank, JICA, AfDB) USD 25 Million On-going March, 2016
2. Power transmission line expansion project between Iringa and Sinyanga Korea Exim Bank EDCF fund (also supported by World Bank, AfDB, JICA, EIB) USD 36 Million On-going TBA
21
6. Conclusion
  • The current situation shows that there is
    intensive investment in generation, transmission
    and distribution of Power in Tanzania which will
    stabilise Power availability in the Country.
  • The Government of Tanzania still invites
    potential investors to invest in Electric Power
    Generation, Transmission, and Distribution to
    curb the future demands.

22