Title: A6: Team Rallye Potable Water Still
1A6 Team RallyePotable Water Still
- Presented by
- Nicole Del Rey
- November 9, 2006
Nicole Del Rey Mike McConnell Tim Rodts
Eric Sabelhaus
2Design Status
3Design Status
- Power (assembled)
- ? Pedals ? Intermediate Gears? Generator
- Heat Source
- (assembled and tested)
- Heating bowl ? Sand ? Baby bottle
- Condensing
- (assembled and tested)
- ? Tygon tubing, 2nd baby bottle (tested well)
- Intelligence (purchased)
- ? Temperature Sensor with Display
4Prototype Status
5Updated Schedule
UPDATED SCHEDULE (11/07/2006)
6Budget
Item Purchaser Price Receipt Total Price
Generator 126.00 352.95
Chair Sabelhaus 5.29
Bikes (2) N/A 2.00 N
Temp. Sensor LCD battery McConnell N
Temp. Sensor McConnell 13.73
base Nicole 5.75
HDPE Sabelhaus 90.51
Screws/Chair back rod, angle iron, L-brackets, 4 large, 4 small McConnell 28.08
Glass tubes Nicole 5.29
Sprocket sleeve N/A 2.00 N
2x6 and screws Sabelhaus 10.91
Ceramic tile, L-brackets, nuts/bolts Nicole 21.27
Power cord, nuts/bolts Nicole 11.75
Screws/Nuts/Bolts for condenser stand, ceramic tile and adhesive Nicole 23.07
batteries, screws Nicole 7.30
7Action Items from last week (Week 11)
8-1-
- TASK Prepare Temperature Sensor
- ACTION
- Consulted with Mr. Brownell to find out that
current temperature sensors were NOT usable - New Sensors were ordered and received
- LCD, battery and wires have been located
9-2-
- TASK Create 3-Way Interface
- Generator output wire/Voltmeter leads/Female
outlet - ACTION
10-3-
- TASK Create driveshaft/sprocket interface
- ACTION Contacted Value Tool Engineering to help
us add a hub and set screw to a sprocket we had
from one of our bikes
11Action Items for this week (Week 12)
12-1-
- TASK Temperature Sensor Set-up
-
- ACTION
- Assemble wires, LCD and Power source
- Attach the sensor to the polluted water container
- Program the Micro controller
13-2-
- TASK Finish Assembly and Test Prototype
- ACTION
- Finish mounting Generator
- Finish mounting Condensor Supports
- Test Prototype
14-3-
- TASK Finish Documentation
- ACTION
- Updates on the website
- Assign parts of Executive summary
- Start working on demonstation presentation
materials