RBI Methodology - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

RBI Methodology

Description:

RBI Methodology Risk Based Inspection API 580 581 Introduction Although the term RBI has been adopted relatively recently, the practice of planning plant ... – PowerPoint PPT presentation

Number of Views:697
Avg rating:3.0/5.0
Slides: 31
Provided by: Gior214
Category:

less

Transcript and Presenter's Notes

Title: RBI Methodology


1
RBI Methodology
Risk Based Inspection
  • API 580 581

2
Introduction
  • Although the term RBI has been adopted
    relatively recently, the practice of planning
    plant inspection based on the risk of failure is
    not new. Most operators base the scope and depth
    of their inspection plans on the rate of
    in-service damage and the consequence of failure,
    within a traditional time-based inspection
    programme. (Same operators can rightly claim that
    their plant inspections have always been
    risk-based).
  • The term RBI refers to a structured, team-based
    assessment process with the aim of targeting
    inspection by considering the Risk of Failure
    (RoF), which is a combination of the Likelihood
    of Failure (LoF) and Consequence of Failure (CoF).

3
RBI Risk Based Inspection
  • Is based on the norms API 581 RP 580
  • Developed by API (American Petroleum Institute)
    in collaboration with
  • - DOW
  • - SHELL
  • - FINA
  • - TEXACO
  • - EXXON
  • - .

4
Objective of RBI Methodology
  • Increase safety
  • Increase the productivity of inspection
  • Decrease the losses of production
  • Reduce the direct costs of inspection
  • Change the frequencies of inspections in base to
    the risk
  • Prevent catastrophic damages

5
RISK
  • Definition of the Risk
  • Risk (RoF)
  • Likelihood of Failure (LoF)
  • x
  • Consequence of Failure (CoF)

6
Risk Based Inspection
  • Consent of
  • Define the critical state for every single ITEM
  • Create a priority for the Inspections basing on
    the critical state
  • Focus the attention on the expected damages

7
RBI Methodology
  • RBI Methodology developed by different
    companies, varied in the details, but it is
    founded however on fundamental step
  • Background to RBI
  • Assessment Personnel
  • Damage Mechanism Assessment
  • Risk Assessment
  • Inspection Planning and Risk Mitigation
  • Updating RBI Assessment

8
RBI Methodology
9
Background to RBI
  • RBI study is designed around the systematic,
    inductive assessment process of identifying
    historical, active or potential damage mechanism
    in each equipment. The process is a bottom up
    procedure where one damage mechanism id
    considered at a time. Once the feasible damage
    mechanisms have been identified, their
    probabilities (likelihood) of leading to
    component failure are determined and their
    effects on the components are recorder and
    analysed to yield a calculated failure
    consequence.

10
Assessment Personnel
  • All RBI systems have the following common
  • elements
  • Assessment preparation
  • Information Gathering
  • Damage Mechanism Review
  • Risk Assessment
  • Inspection Plans
  • Inspection Review.

11
Assessment preparation
  • Since RBI is a team-based approach, the first
    step in the introduction of an RBI programme is
    to identify and assemble a competent Study Team.
    The RBI team should include staff with knowledge
    of plant operation, process hazards, risk
    assessment and inspection techniques.

12
Typical RBI team
  • Inspection engineer(s)
  • Material and corrosion engineer(s)
  • Maintenance engineer(s)
  • Process engineer(s)
  • Operations engineer(s)
  • Safety engineer(s)
  • Team leader, typically a RBI specialist(s).

13
Information Gathering
  • Are necessary the following information
  • Operational manual
  • PID
  • Sketches of project of the equipment
  • Pipe class
  • Property of the fluids
  • Design and operating conditions
  • Special instructions and History inspection

14
Damage Mechanism Assessment
  • The Study Team will need to review the historical
    and generic date relevant to each item of
    equipment. This will include consideration of
    previous inspection reports (if available) to
    determine the known or expected damage
    mechanisms.
  • The review should consider damage mechanisms
    which may lead to failure, their expected rates
    of deterioration and the general location where
    damage may arise.
  • Wherever quantitative rates of damage are not
    available, an element of expert judgement will
    need to be exercised by the Study Team.

15
Risk Assessment
  • The failure likelihood and the failure
    consequence are calculated on the basis of
    quantitative Likelihood Factors (LF) and
    Consequence Factors (CF).

16
Likelihood of Failure (LoF)
  • The answers to the LF questions are assigned a
    series of values and associated weighting and the
    combination of all these determines the
    Likelihood of Failure (LoF), derived for each
    equipment in turn.
  • The LoF formula is specifically of the following
    form
  • LoF LF2 S (LFi)
  • LF2 Failure likelihood (within a given period
    of time)
  • LFi represents several factors that are
    considered to
  • contribute to the overall Likelihood of
    Failure.

17
LFi Factors
  • LF1 Current condition
  • LF2 Failure likelihood
  • LF3 Inspection Effectiveness
  • LF4 Shutdown Frequency
  • LF5 Operational Stability
  • LF6 Operation in Relation to Design
  • LF7 Recurring Repairs

18
Consequence of Failure (CoF)
  • The answers to the Consequence Factors (CF)
    questions are assigned a series of values and
    associated weightings and the combination of
    these results is the Consequence of Failure
    (CoF), derived for each item in turn.
  • The CoF formula is specifically of the following
    form
  • CoF (FM x CF1 x CF2) (CF3 x CF6)
  • CF4 (CF5 x CF7) CF8 CF9

19
FM Factor
  • In addition to other consequence factors the
    consequence calculation also consider the failure
    mode of an assigned damage mechanism. Each damage
    mechanism knowledge base is assigned one of three
    failure modes, i.e. Leakage, Leakage or
    Rupture, Rupture.

20
CFi Factors
  • CF1 Product Loss
  • CF2 Pressure Factor
  • CF3 Explosion/Fire Damage Potential
  • CF4 Toxicity
  • CF5 Effect of Failure on Production
  • CF6 Location of Component
  • CF7 Time Taken to Rectify Failure
  • CF8 Threat Personnel/Environment
  • CF9 Engineered Safety Systems

21
Weight of Factors
22
Risk Matrix
  • The resultant Likelihood of Failure (LoF) is
    plotted on the vertical axis, and the Consequence
    of Failure (CoF) is plotted on the horizontal
    axis, as an assessment point on a dimensionless
    five-by-five Risk Plot. The Lof axis is grouped
    into five relative Likelihood Categories, ranging
    from 1 to 5 (approximately 10-2/yr to 10-7/yr),
    and the CoF axis is grouped into five relative
    Consequence Categories, ranging from A to E. In
    this way, the Risk of Failure (RoF) is considered
    to increase with increasing LoF and CoF.

23
Risk Matrix
5
4
Risk
Likelihood
3
2
1
B
C
D
E
A
Consequence
24
Inspection Planning
  • After the risk assessment, the Study Team
    develops action plan based on all of expected
    damage mechanisms. The inspection plane consider
    the inspection interval and the scope of
    inspection.
  • The proposed inspection plane are designed to
    provide an assurance that the residual risk of
    the equipment is in accordance with the ALARP
    principle, i.e. the aim of assessing and managing
    equipment is to reduce the RoF to As Low As is
    Reasonably Practicable (ALARP).

25
Risk Mitigation
  • The RBI methodology systematically leads the
    Study Team through the process of risk
    mitigation, by considering several mitigation
    action. The impact of each mitigation action can
    be evaluated, for subsequent collective appraisal
    of the benefits of the proposed action, using the
    ALARP principle. An appropriate strategy to
    manage the integrity of each equipment is
    therefore developed.

26
Updating RBI Assessment
  • RBI Study can be used to justify extending the
    periods between inspections. The RBI process
    relies on a feedback loop to update the
    inspection plan, such that it is relevant to the
    actual condition of the plan. The feedback stage
    provides continuing confidence that damage dose
    not exceed expectations and ensures that plan
    inspections take account of operational
    experience.
  • Once an inspection plan has been developed during
    a session, future inspection of the equipment
    should be carried out to confirm that damage
    rates are within expectations and to identify any
    unexpected damage. The inspection should be
    carried out by competent staff and the results
    recorded and re-evaluated.

27
FeedBack of the Study
Plant Operation
Plant Operation
Shutdown/ Inspection
Inspection Plan Rev.0
Inspection Reporting
Inspection Plan Rev.1
Start RBI
Maintenance Shutdown
Maintenance Shutdown
Base RBI Assessments
Review RBI Assessments
28
Risk vs TimeNo Inspection Plan
180 months
120 months
60 months
29
Risk vs Time With Inspection Plan
180 months
120 months
60 months
30
  • DONEGANI ANTICORROSIONE SRL
  • VIA G. FAUSER 36/A
  • 28100 NOVARA
  • Tel. 0321677411
  • Fax. 0321677444
  • E-mail segreteria_at_donegant.it
  • Web www.donegant.it
Write a Comment
User Comments (0)
About PowerShow.com