Title: Top Three Renewable Transmission Projects
1Arizona Corporation Commission Fifth Biennial
Transmission Assessment Commission Decision
70635 Open Hearing
Top Three Renewable Transmission
Projects Southwest Transmission Cooperative, Inc.
Jim Rein/Bruce Evans
November 23, 2009 Docket E-00000A-09-0066
1
2Outline of Presentation
- Factors influencing SWTC Decision for Top Three
- General Policy Comments
- General Discussion on Project Funding and Impact
to SWTC Member Systems - SWTCs Top Three Projects
3Factors influencing SWTC Decision
- ACC Decision No. 70635 ordered that all
Commission-regulated utilities shalldevelop ways
in which new transmission projects can be
identified, approved for construction, and
financed in a manner that will support the growth
of renewables in Arizona. - SWTC feels that its top three renewable
transmission projects will help to support the
growth of renewables in Southeast Arizona. The
projects provide - Access to existing or planned transmission
projects in the short term, when most needed by
renewable developers coming into the area. - Ability for joint participation with other
entities, which can ease the costs to SWTC Member
Systems. - Potential for renewable energy to get to markets
in Arizona. - Ability to accommodate SWTC Member System current
and future RES requirements. - Ability to accommodate the 600 MW of potential
renewable solar development identified by the
RTTF in Southeast Arizona.
4General Policy Comments
- SWTC is supportive of efforts AZ Stakeholders
have made to comply with ACC Order No. 70635 and
was involved with efforts of RTTF sub-committees. - SWTC is in support of policy comments discussed
by others - Types of renewable transmission projects
- Project timing
- Definition of RTPs
- SWTC is supportive of efforts to build Renewable
Transmission Projects (RTPs) to support SWTC
Member System Renewable Energy Standard (RES)
requirements. SWTC can currently meet these
needs through its existing transmission system.
5General Policy Comments (Cont.)
- And, SWTC is generally supportive of efforts to
build RTPs to not only meet RES but also for
more intra-Arizona use and export to markets. - However, SWTC is limited in its ability to
construct RTPs or provide funding for joint
utility RTPs, unless a need can be tied directly
to the Member Cooperative Systems, as per RUS
Regulations.
6SWTC Project Process
7Project Funding and Impact to SWTC Member Systems
- SWTC transmission system was designed to reliably
and economically deliver resources to SWTC Member
Systems. - Expansion to the SWTC transmission system,
through RUS funding, must be tied to Member
System needs for reliable service and expected
load growth. - Funding through the Rural Utilities Service (RUS)
is the only viable mechanism SWTC has to fund
projects. To secure funding outside of RUS, SWTC
must use a lien accommodation process, which
also requires approval by RUS.
8Project Funding and Impact to SWTC Member Systems
(Cont.)
- Simultaneous with the filing of its Top Three
Projects, SWTC filed a new rate case with the
Commission. The new rate is needed to meet
revenue requirements as a result of declining
revenues. - As a result of the declining revenues, some SWTC
projects have been deferred including the San
Manual Interconnect Project. - Two of the top three projects would have a
significant impact upon the proposed rates to the
SWTC Member Systems.
9SWTC Top Three Renewable Transmission Projects
- San Manuel Interconnect Project
- Apache to Bicknell 230 kV Line Upgrade
- Western Saguaro-Apache 115 kV Line Upgrade (SOI
Proposed Project)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13San Manuel Interconnect Project
14San Manuel Interconnect Project
- Project is shovel-ready - approved by ACC Line
Siting Committee on May 12, 2009, Case 142, and
approved by the Commission on July 9, 2009.
Estimated in-service date is 2014. - Total estimated cost is 4,201,359. Will be
funded through RUS loan process. Impact to SWTC
ratepayers is minimal. - Tie-in to San Manuel constructed at 230 kV, but
operated at 115 kV. - Can accommodate approximately 240 MW from
Renewable Generation locating near San Manuel
(77 Solar in APS Queue). - SWTC willing to work with third-party entities to
upgrade its 115 kV line to allow for additional
export of renewable energy to markets.
15Apa-Bicknell 230 kV Line Upgrade
16Apa-Bicknell 230 kV Line Upgrade
- 2 Segments planned for upgrade from 795 ACSR to
1272 ACSS conductor (slight difference as filed
in SWTC 2009 ACC Ten Year Plan) - Apache to Butterfield (2016)
- Butterfield to Bicknell (2017)
- Total estimated cost is approximately
19,600,000. Will be funded through RUS loan
process. Impact to SWTC ratepayers is
substantial 11.2 increase above current rate
increase proposal - The future upgrades could provide an additional
450 MW that would support renewable generation in
the area. - SWTC willing to work with third-party entities to
allow for interconnections to the upgraded line
for export of renewable energy to markets.
17Western Sag-Apa 115 kV Line Upgrade
18Western Sag-Apa 115 kV Line Upgrade
- Concept is to upgrade the existing WAPA Saguaro
to Apache 115 kV Line to a double circuit 230 kV
Line. Use 954 ACSS or 1272 ACSS conductor as per
WAPA standards. - SWTC and TEP proposed this project for upgrade in
the Western SOI process. Western may choose to
not to fund this project, however, SWTC and TEP
have been participating in discussions with
another entity that has expressed interest in
funding the project. - Project will be shovel ready within time frame
required as renewable resource projects develop
in southeast Arizona. - Upgrades could provide additional transmission
transfer capability of as much as 1000 MW that
would support renewable generation in the area. - Total estimated cost (subject to change) is
approximately 205,045,360. Funding to be
through aegis of Western. - SWTCs current estimated share of the cost is
61,162,041. Impact to SWTC ratepayers is
substantial 35 increase above current rate
increase proposal. SWTC would expect that
additional entities would show interest in the
line, thus reducing costs to ratepayers.
19Questions?