Title: Energy Commission Review of Power Plants
1Energy Commission Review of Power Plants
Southern California Reliability
2015 Integrated Energy Policy Report Workshop on
Southern California Electricity
Reliability University of California,
Irvine August 17, 2015 Roger Johnson Siting,
Transmission and Environmental Protection
Division Roger.Johnson_at_energy.ca.gov / (916)
654-5100
2Southern California Power Plants
3NRG Puente
- Mandalay Generating Station replacement of Units
12 with - 262 MW GE Frame 7HA CTG
- City of Oxnard
- Information Hearing 8/27/2015
- CEC Decision expected 6/2016
- OTC compliance date 12/31/2020
- PPA - Yes
4AES Alamitos
- Alamitos Generating Station Replacement
- 640 MW air-cooled combined cycle
- 400 MW LMS 100 simple cycle
- City of Long Beach
- AFC supplement expected 2015
- CEC Decision 2016
- OTC compliance date 12/31/2020
- PPA Yes (640 MW)
5NRG El Segundo
- El Segundo Units 12 replaced on 8/2013
- with 560 MW fast-start combined cycle.
- City of El Segundo
- El Segundo Units 34 Replacement
- 449 MW (1 fast-start air-cooled combined
- cycle and 2 simple cycle peakers)
- Final Staff Assessment 8/2015
- CEC Decision expected late 2015
- OTC compliance date 12/31/2015
- PPA - No
6AES Redondo Beach
- Redondo Beach Generating Station Replacement
- 496 MW (3-on-1 air-cooled combined cycle)
- City of Redondo Beach
- PSA workshops 5/2015
- CEC Decision 2016
- OTC compliance date 12/31/2020
- PPA - No
7AES Huntington Beach
- Huntington Beach Generating Station Replacement
- 644 MW air-cooled combined cycle
- 200 MW LMS 100 simple cycle
- City of Huntington Beach
- Amendment to CEC Decision expected 9/2015
- OTC compliance date 12/31/2020
- PPA- Yes (644 MW)
8NRG Carlsbad
- Encina Power Station Replacement
- City of Carlsbad
- Petition to Amend filed 4/23/2013 for 632 MW (6
LMS 100 simple cycle) and removal of Encina
Generating Station - CEC Decision 7/2015
- Storage tank demolition underway
- Start of Construction TBD
- OTC compliance date 12/31/2017
- PPA Yes (500 MW)
9Pio Pico
- 300 MW simple cycle project approved by CEC
9/12/2012 - San Diego County (Otay Mesa)
- Project construction started 2/2015
- Operation expected 9/2016
10Wellhead
- Wellhead
- 98 MW (2 LM 6000)
- City of Stanton
- AFC expected in 2015 after CPUC approves PPA
- PPA - Yes
11Status of Southern California Power Plants
Project Capacity Development Status Schedule OTC Compliance Date
Puente 262 MW Info Hrng 8/2015 CEC Decision 2016 12/31/2020
El Segundo 1 El Segundo 2 560 MW 449 MW Operational 8/2013 FSA 8/2015 N/A CEC Decision 2015 N/A 12/31/2015
Redondo 496 MW PSA wkshps 5/2015 CEC Decision 2016 12/31/2020
Alamitos 640 MW 400MW AFC supplement expected 2015 Unknown 12/31/2020
Huntington Beach 644 MW 200MW Amendment to CEC Decision expected 9/2015 Unknown 12/31/2020
Carlsbad 632 MW CEC Decision 7/2015 Const. start TBD 12/31/2017
Wellhead 98 MW AFC expected 2015 after PPA approved Unknown N/A
Pio Pico 300 MW Const. started 2/2015 Operation 9/2016 N/A