1
Project Activity andRisk Planning
2
What are Projects?
  • Group of Activities
  • Beginning, Middle, End
  • Well-Defined End Result

3
Examples of Projects
  • Construction
  • Research and
    Development
  • Design of New Product or Process
  • Spacecraft
  • Wedding
  • Can You Think of Projects?
  • Can You Think of Non-Projects?

4
Project Life Cycle
5
Project Planning Consists of
  • Purpose
  • Objectives
  • Overview
  • Contracts

6
Project Planning Consists of
  • Schedules (PERT/CPM)
  • Resources
  • Personnel
  • These Areas Can Be Handled Well with Microsoft
    Project and Other Software

7
Project Planning Consists of
  • Potential Problems and Risks
  • Risk Management Planning
  • Risk Identification
  • Qualitative Risk Analysis
  • (Risk Matrix)
  • Quantitative Risk Analysis
  • (Probabilities, Simulation)
  • Evaluation and Control (Feedback)

8
Initial Project PlanningDraw System Boundaries
  • A System Consists of the Following
  • Mission and Goals
  • - Objectives
  • - Performance
  • - Effectiveness
  • - Cost
  • Environment
  • Resources
  • Subsystems

9
In Project Planning Activities Must be Identified
  • Activities are Groups of Work Elements or Tasks
    with
  • Similar Technology Groups of Personnel
  • Single Duration of Time (Activity Completion is
    Event)
  • Definite Beginning End

10
List of Activities Can Be Developed with
  • Gozinto Chart
  • Bill of Materials
  • Work Breakdown Structure (WBS)

    Basically a Bill of Work Units

11
Work Breakdown Structure (WBS)
12
WBS Information
  • For Each Work Element (Activity) We Need
  • Work Statement (Input/Output)
  • Vendors, Contacts, Subcontractors
  • End Item Specifications
  • Cost Accounting Numbers Costs (ABC) (Assigns
    Activities to Cost Drivers to Costs E.g.
    Activity A to Labor Hours to Labor Costs)

13
WBS Information
  • For Each Work Element
  • (Activity) We Need
  • Resource Needs
  • Personnel (Linear Responsibility Chart or RACI
    Matrix)
  • Times (Scheduling, PERT/CPM, Gantt Charts)
  • Sequence Requirements

14
Activity AnalysisExample One
  • Activity Description Follows Days
  • A Define Problem --- 3
  • B Lease Computer --- 5
  • C Obtain Data A, B 4
  • D Determine Alternatives A, B 1
  • E Feasible Alternatives D 1
  • F Evaluation Modeling C, E 5
  • G Find Best Alternative F 1
  • H Implementation G 3

15
Activity AnalysisExample Two
  • Activity Description Follows Days
  • X --------------- --- 1
  • Y --------------- --- 2
  • Z --------------- --- 3
  • A --------------- X, Y 1
  • B --------------- X, Y, Z 2
  • Draw Activity-On-Node (AON or CPM) Diagram.
  • Draw Activity-On-Arrow (AOA or PERT) Diagram.

16
Activity AnalysisExample Three
  • Activity Description Follows
  • a Plan Survey ---
  • b Hire Personnel a
  • c Design Questionnaire a
  • d Train Personnel b,c
  • e Select Households c
  • f Print Questionnaire c
  • g Conduct Survey d,e,f
  • h Analyze Results g
  • Draw Activity-On-Node (AON or CPM) Diagram.
  • Draw Activity-On-Arrow (AOA or PERT) Diagram.

17
(No Transcript)