Transcript and Presenter's Notes

Title: LEVERAGING YOUR ASSETS AND CREATING PARTNERSHIPS FOR BUILDING FIBER


1
LEVERAGING YOUR ASSETS AND CREATING PARTNERSHIPS
FOR BUILDING FIBER
  • ITS ABOUT THE POLES STUPID
  • BROADBAND COMMUNITIES SUMMIT 2013
  • April 16, 2013
  • Sean Stokes
  • The Baller Herbst Law Group, P.C.
  • 2014 P Street, N.W.
  • Washington, D.C. 20036
  • (202) 833-0166
  • sstokes_at_Baller.com
  • www.Baller.com

2
The Big Picture
3
Federal Pole Attachment Regulations -- 47 U.S.C.
224
  • Regulate rates, terms and conditions of access
    for wired and wireless attachments to utility
    poles by telecommunications carriers and cable
    operators
  • Rules apply to poles, ducts, conduits and ROW
    owned by investor-owned (private) utilities
  • Rates Two formulas Cable only (not really)
    and Telecom. In 2011 the FCC revised Telecom
    formula to yield essentially same rate as Cable
    formula
  • Access Prescribed timelines for access to poles
  • Cost causer pays

4
Yup Yup Nope
5
What the Federal Attachment Rules Dont Do
  • Federal rules dont apply in 21 states that have
    reverse preempted the FCC and regulate at the
    state level.
  • Federal rules dont apply to municipal or
    cooperatively owned utilities -- 47 U.S.C.
    224(a)(1)
  • Federal rules dont provide attachment rights to
    stand-alone broadband or dark fiber services
  • Federal rules dont apply to utility fiber

6
  • If they want broadband so bad why dont the
    municipals just get out of the way and let us
    build?

7
OH
8
Public Power Utilities
  • View safety, security and reliability of their
    electric system as top priority
  • View poles and conduit as a community asset
  • Want to encourage broadband deployment
  • Want (and have an obligation) on behalf of their
    consumer owners to obtain cost recovery
  • Provide access to all types of service providers
    voice, video and data on similar terms and
    conditions

9
Leveraging Municipal Utility Assets
  • Bring the utility in to the planning process
    early
  • Dont assume that utility and municipality have
    identical interests
  • Dont confuse access to ROW with access to assets
  • Allow for in-kind consideration and where
    possible monetize the value of such services
  • Dont get tripped up by non-discrimination or
    level playing field clauses