Title: WEEKLY REVIEW
1VAE 193 Field PDI issues Countermeasures
Sl.No Defects Photos Counter Action Resp. Status Target Remarks
1. Connect drain ID has to be Increased for proper fitment Arul Drawing released sample has to be received 07.08.10
2. Arul/Sujay Drawing released sample has to be received 03.08.10
3. Screw drawing has been released 03.08.10
Drain pan not seated properly and fouling with
chiller tray
Temp Action Extra length wrapped with cable
tie Perm. Action Extra length has to be reduced
Bulb wire harness hanging
Metal reinforcement plate will be used for
proper fitment (same as 324 l)
Arul
RB Evap. Fitment loose
2VAE 193 Field PDI issues Countermeasures
Sl.No Defects Photos Counter Action Resp. Status Target Remarks
4 Evaporator seating RIB liner cut Increased the no. of air vent holes for better filling of puf added inspection check points to avoid the issue Murali/Raj kumar Done 26.07.10
5 Drain tray breakage grommet missing Presently started using regular drain tray with 2 mounting grommets. Mani/Raj kumar Done 22.07.10
6 Door locking problem Door lock plate width has been changed 11mm to 13mm for better locking (similar to 324L) Mani/Pawan Done 28.07.10
7. Top EPS missing Packing Operators Educated and instructed. Strapping operators will check before strapping Mani/Chandrashekar Done