Title: Prezentace aplikace PowerPoint
1Project Management
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
2Project Management
Activity 5
Activity 2
Activity 1
Activity 7
Activity 3
Activity 4
Activity 6
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
3Project Management
NETWORK graphical representation of the project
Activity ? Node
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
4Project Management
NETWORK graphical representation of the project
Activity ? Arc
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
5Project Management
Activity ADesign a car
Activity BMake a prototype
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
6Project Management
Activity A immediately PRECEDES activity B
Activity B immediately SUCCEEDS activity A
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
7Project Management
Activity A is the predecessor of Activity B and C
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
8Project Management
Activity E (Prototype test) follows Activity B
Activity D (Prototype presentation) follows
Activity B and C
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
9Project Management
Activity Requirements
- time
- money (cost)
- material
- machines
- people
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
10Project Management
Phases of Project Management
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
11Project Management
Methods
Deterministic time
Probabilistic time
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
12Project Management
CPM
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
13Project Management
CPM
- Finish time of the project
- Start and finish times of each activity
- A critical path consisting of critical activities
- Non-critical activities and their possible delay
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
14Project Management
CPM
Example - Music DM, Inc.
- Christmas compilation of Czech carols
1) Songs Selection
2) Mastering
3) Promotion Material Elaborating
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
15Project Management
CPM
Example - Music DM, Inc.
4) Customers Analysis
5) Promotion Material Production
6) Make CD Copies
7) Customers Selection
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
16Project Management
CPM
Example - Music DM, Inc.
8) Data to Printing House
9) Promotion Material to Printing House
10) Laser Print
11) Mailing
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
17Project Management
CPM
Example - Music DM, Inc.
Activity Description Duration Predecessors
A Songs Selection 15 None
B Mastering 8 A
C Promotion Material Elaborating 6 A
D Customers Analysis 7 A
E Promotion Material Production 4 C, D
F Promotion Material to PH 5 E
G Customers Selection 3 D
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry
18Project Management
CPM
Example - Music DM, Inc.
Activity Description Duration Predecessors
H Make CD Copies 12 B, D
I Data to PH 3 G
J Laser Print 9 F, I
K Mailing 8 H, J
- All the envelopes have to be delivered until
December 12
- Objective set the starting date of the project
_______________________________________________
____________________________ Quantitative
Methods of Management ? Jan Fábry