Title: Converting Overhead to Underground
1Converting Overhead to Underground
- March 9, 2004
- APPA Conference
- San Antonio, Texas
Modesto C. Rodriguez, P.E. TD Engineer
III mcrodriguez_at_cps-satx.com (210)353-2533
2Objectives
- Overhead to Underground
- Conversion Program Background
- Conversion Program Guidelines
- Projects Completed / In Work
- Project Selection Process
- Projects Selected for 2003
3Objectives
- We have come a long way since 1993 What have we
learned? - Joint Trench Issues
- Easements Permits
- Trench Alignment
- Rivers to Cross? Bridge Attachments
4Objectives
- Factors That Increase Project Costs
- Summary
- Questions
5Overhead to Underground
- Definition Conversion of overhead electric
distribution lines to underground operation IAW
CPS standards, specifications, and accepted
engineering practices. - CPS utilizes dead front, loop feed, pad mounted
transformers with load break switches in primary
loop systems. - CPS converts the electric system up to the
customers meter loop. - Distribution Voltages Included 34.5KV L-L
13.2KV L-L.
6Overhead to Underground
- When feeder sectionalizing is necessary, or for
large multiple loads, CPS utilizes pad mounted,
SF6 gas insulated, switchgear in underground
primary loop systems.
7BITTERS RD. CONVERSION BEFORE
8BITTERS RD. CONVERSION
17,480 Ft Removal, Cost 2.182 Million
(124.82/FT)
9BITTERS RD. CONVERSION
17,480 Ft Removal, Cost 2.182 Million
(124.82/FT)
10BITTERS RD. CONVERSION
17,480 Ft Removal, Cost 2.182 Million
11ST. MARYS ST. CONVERSION BEFORE
29,875 FT Removal, Cost 1.82 Million
12ST. MARYS ST. CONVERSION
29,875 FT Removal, Cost 1.82 Million
13ST. MARYS ST. CONVERSION
29,875 FT Removal, Cost 1.82 Million
14Conversion Program Background
- On April 7, 1993, the CPS Board of Trustees
directed staff to review design practices with
the objective of modifying and incorporating
aesthetic consideration (converting OH to UG)
into its designs for electrical facilities. - As a result of this request, numerous studies
were conducted and results indicated it to be
Cost Prohibitive to place facilities underground. - Instead, in late 1993, CPS created a resolution
amending the Capital Budget to include a budget
to be known as the Overhead Conversion Fund.
15Conversion Fund Background
- The Funds are managed by the CPS General
Accounting Department. - Per resolution, the OCF budget is set at 1 of
the electric revenue billed during the previous
fiscal year to retail electric customers of CPS
residing within the City, the Municipalities, and
the Counties together with the balance of any
amount budgeted in previous years not spent. - Each of the 28 Municipalities and 8 Counties
served by CPS has an appropriate fund allocation.
16Conversion Fund Background
17Conversion Program Guidelines
- The OCF can be used for the following items
- Convert Overhead Electric to Underground
operation. - Overhead facility modifications, i.e.. Relocate
Overhead Electric. - Modifications also include, replacing existing
poles and cross-arms with aesthetic alternatives,
steel poles.
18Conversion ProjectsCompleted / In Work
- A total of 40 projects have been completed since
the inception of Overhead Conversion Fund. - 2 projects currently in construction.
- 2 projects are currently in design.
19Project Selection Process
- In 1997, COSA adopted a formal project selection
process. - Candidate Projects are gathered by COSAs Capital
Programs Division (CPD). - CPD submits candidate projects to CPS for cost
estimates. Total Cost UG Cost OH Removal -
OH Material Salvage Value - CPD evaluates and ranks projects.
- A Planning Commission reviews and selects
projects to be implemented. - CPD holds neighborhood association meetings to
show the impact to the neighborhood.
20Project Selection Process
- Projects with favorable neighborhood association
meetings remain on the list. - City Council reviews and approves projects via a
resolution authorizing the implementation of the
project. - CPS designs and plans the project utilizing CPS
standards, specifications and accepted
engineering practices. - Based on construction workload, CPS may hire a
contractor to complete the work.
21Projects Selected in 2003/2004
- 12 projects were selected.
- The estimated total cost for the 12 projects
20.72 Million - Status To date only 2 of the 12 project have
been released/ authorized by resolution. - The conversion process began with a bang!
However, currently, the other utilities are
refusing to participate in 10 of the 12 projects
for free.
22We have come a long way since the inception of
the program What have we learned?
23Joint Trench Issues
- During the design phase consideration should be
given to other utilities. - Other Utilities (CATV, Tele.) voluntarily elect
to participate in an overhead conversion job. - Establish a joint trench sharing agreement that
describes the methodology for determining each
utilitys share of the joint trench costs. - Collect the full charges as determined by the
agreement prior to commencing!
24Easements Permits
- Acquire Easements First!
- Quickly follow-up with easement documents when
given verbal permission to place lines
equipment by the property owner. - Mandatory for placement of padmount transformers.
Optional for services unless a service crosses
over the property to serve a neighbor. - Acquire permits or approvals as may be required
to gain access to easements or properties owned
by railroads, state highways and commissions as
early as possible. - Special permits may be required if the area is of
archeological significance.
25Trench Alignment
- Projects are usually selected in anticipation /
coordination with Civic Improvement Projects. - Select the most direct main trench alignment
maintaining a consistent location within the
street right of way keeping future CIPs in mind. - Know where all existing and proposed facilities
are located in effort to minimize conflicts with
storm lines, inlets, water mains and sewer lines.
Adjustments in elevation may be necessary. - Avoid late fees associated with delays by
managing the project closely while proactively
resolving conflicts as quickly as possible.
26Rivers to Cross? Bridge Attachments
Roosevelt / Grove St. Conversion
27Factors That Increase Project Costs
- Costs can vary greatly from project to project.
- Scope/Size of the project. Paved Vs. Unpaved
areas. - Soil Conditions Dirt Vs. Rock. Standard Vs.
Non-standard hours worked. - Extra depth charges in effort to avoid conflicts
with water mains, storm drains, storm drain
inlets, fire hydrants and roadway elevation
changes. - Spare ducts to accommodate future circuit
redundancy.
28Factors That Increase Project Costs
- Boring/Trenchless requirements under high traffic
roadways, newly reconstructed streets, and
railroads where open cuts are prohibited. - Replacing OH switches and maintaining existing OH
configurations utilizing padmount switchgear is
costly. - Submersible switchgear in Vaults.
- Dig ins.
29Summary
- Overhead Conversion Fund is alive and well.
- Mission accomplished.
- Future
30Questions?