Title: Project Tracking


1
Project Tracking
  • Unit objectives
  • How to track project actual data against original
    plan
  • Pick up KFulltime/MSProject IT
    2005/StudentData/Unit_05/Exploring and save on C
    drive

2
Creating a BASELINE Project
  • Baseline Once a project plan is approved, it is
    frozen as a baseline, so that you can report
    your actual time against it
  • Choose TOOLS, TRACKING
  • Save Baseline
  • Entire Project
  • OK

3
Ways to Enter Actuals
  • Task progress as a Percentage -100 is complete
  • Task actual start and finish dates
  • Task Actual work performed on a task

4
Task Progress as
  • EASY WAY
  • View, Tracking Gantt
  • View, Toolbars, Tracking
  • Look at the toolbars available to apply to a
    task.
  • Select a task, then do 50 complete.

5
Task Progress as
  • View, Tracking Gantt
  • Hilite task, then choose Tools, Tracking, Update
    Tasks
  • Task Preconstruction Get Approvals task
    change complete to 100
  • Change select architect task to 50 complete
  • Look at task Pre-Construction notice it takes
    its information from subtasks

6
Change Actual Start/Finish Days
  • Select task Draw Plans
  • Choose Tools, Tracking, Update Tasks or on
    Tracking toolbar, choose update tasks button
  • Planned start date is 2/21/06 and finish is
    3/13/06
  • Enter Actual start as 2/22/06
  • View, Tracking Gantt (notice slip in finish date
    and other tasks)

7
Enter Actual work performed
  • View, Task Usage
  • Scroll over, notice that there are yellow and
    white lines
  • On the right pane, right click beside a resource
    to select Actual Work this adds a line where
    you can update actuals
  • For Task Approvals, zero out times for the week
    of Feb 5th for Pat Leary notice time goes from
    80 to 40 hrs
  • Change to View, Tracking Gantt, notice Grey
    (planned time) and Blue (actual time) bars

8
Printing
  • View, Reports
  • Choose Assignments
  • Look at Who Does What When
  • Look at Assignment List
  • Close
  • Choose Current Activities
  • Tasks Starting Soon
  • Should Have Started Tasks
  • Close
  • Custom Build Your Own

9
Assignment Enter Actuals
  • Update your original project plan for the
    Research Assignment
  • Create baseline
  • Update all tasks to be 100 complete
  • Enter actual start and end dates
  • Enter actual time spent by resource.

10
Assignment Print
  • Print the following/add your names on top
  • Tracking Gantt chart
  • Reports
  • Overview, Project Summary
  • Workload, Task Usage

11
Assignment Enter Actuals
  • Tools, Tracking, Save Baseline.
  • Tools, Tracking, Update tasks
  • to be 100 complete
  • Enter actual start and end dates
  • View, Task Usage
  • Enter actual time spent by resource
  • Make sure there is a Project Summary Line on Your
    Project