Business Review Templates - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Business Review Templates

Description:

The template set is designed to cover business activities across all of the life ... Slide 8. Is a free text where the TL can report on their approach to ... – PowerPoint PPT presentation

Number of Views:4557
Avg rating:3.0/5.0
Slides: 24
Provided by: chr9151
Category:

less

Transcript and Presenter's Notes

Title: Business Review Templates


1
Business Review Templates
2
(No Transcript)
3
Guiding Principles
  • This set of templates should be used in
    conjunction with the Business Review Guidance
    document at ref xxxxxtbc
  • The template set is designed to cover business
    activities across all of the life cycle (CADMID).
    The selection of which templates are to be used
    is a decision for the IPTL / DG.
  • There should only be one business review of each
    team.

4
Template Information
  • This set of templates comprises 3 sections
  • General Slides applies to all reviews
  • Project related slides
  • Support related slides
  • The template sections differentiate between
    delivery of projects (including upgrades and
    UORs) and support (including supply of services)
    because our business does. A team engaged in both
    activities will review slides of data from all
    sections.

5
Section One
  • Whole IPT Summary Slide 7
  • IYM Summary RDEL, CDEL including CPF
  • Balance Sheet
  • Governance of Business Slide 8
  • Other Issues Slide 9
  • Benefits Tracking
  • Successes, Opportunities, Failings Threats
  • People Collocation

6
Summary Slide GuidanceSlide 7. This is
principally a financial summary of the whole
IPTs Business and should include all colours of
money that the IPT deals with, including the
operating cost. The Asset Deliveries are intended
to show an aggregate of all deliveries in the IPT
but this would not be required if all the
delivery information has already been presented
in a single large project above. Where IPTs
control significant stock movements, the Balance
sheet section would be an essential item.
However, it may be less useful for projects in an
early stage of the CADMID cycle for example.
Employ as required.Slide 8. Is a free text
slide where the TL can report on their approach
to assurance and any DESIB / IAB submissions and
record issues and opportunities for other group /
board attendances. Slide 9. Is a free text
contribution which should generally be by
exception and should be kept as short as
possible. The list of subjects may not be
relevant to all IPTs and other subjects may be
added.
7
Whole IPT Summary Report Mar 07
Money
Balance Sheet
Deliveries
Fixed Assets Current Assets Liabilities Net Assets
8
Governance of Business
  • Governance of the Project and Business
  • Information on the Assurance Plan
  • Approach to Initial Gate / Main Gate / Review
    Note (if appropriate)
  • Comments / information on wider review boards /
    groups
  • Participation in Industry groups etc

Input from IPTL and BM
9
Team, Stakeholders and wider Issues
  • Data to enable review of the following as
    appropriate
  • Benefits Tracking
  • Successes, Opportunities, Failings Threats
  • Staff issues, People Collocation etc
  • Meetings and Visits
  • Stakeholder engagement issues
  • Wider issues requiring the DG attention

Input from IPTL and BM
10
Section Two
  • Management of Projects (Upgrades UORs)
  • Position against the project plan slides 11 -
    13
  • EVM report slide 14
  • Risk report slide 15
  • Finance and Approvals slides 16 17
  • UOR data (if applicable) slide 18

11
Programme Baseline Level 0 Plan (Date) EXAMPLE
12
Programme Equipment Report
Key Target 1 PERFORMANCE
Key Target 2 TIME
ISD Anchor Milestone Tracking Chart
CMIS Input
Input from PMO
NARRATIVE
Key Target 3 COST
  • Performance
  • KUR23 - Shown as at risk as IC minus A delivers
    less than the planned capability at FOC ISD.
    Full capability is delivered in ship 3.
  • Time
  • Latest TRA shows significant increase in risk to
    ISD, due primarily to the inclusion of PRU
    related risks (Power Systems, S/W, PAAMS,
    Safety). The forecast 50 ISD is now November
    10. The implications of this analysis and the
    potential mitigation of Test Trials duration
    are still being quantified. Therefore, a
    revision to, or confirmation of, the December 09
    CMIS ISD is not expected before negotiations have
    matured i.e. by the end of the year. Anchor
    Milestone forecasts related to Power Systems have
    also been impacted by the consideration of PRU
    related risks.
  • Cost
  • Position against KT3


Input from RM, PMO and FC
Input from FC
13
Programme Support Report (If applicable)
PERFORMANCE
TIME
FoC Key Milestone Tracking Chart
CMIS Input
Input from PMO
NOTE Additional Support Milestones will be
considered for inclusion once a fully integrated
programme is developed
NARRATIVE
COST
IYMSTP 10 Year STP Profile
  • Performance
  • Support solution and upkeep cycle for 6 ships
    meets requirements of KUR9
  • Time
  • Support Solution work remains on track but a
    challenging timescale to meet BC submission to
    IAB scrutineers end Mar 07 and end Jun to IAB 4
    Committee.
  • Concerns with those materiel delivery dates at
    risk (IPLs and Tech Docs) being pursued through
    PCO.
  • Cost
  • This is the first year the IPT will incur
    expenditure against the DLO/STP. Budget (STP05)
    of 3.755m comprises 0.055m RDEL and 3.7m CDEL.
    Expenditure is for long lead items/spares. No
    variance between forecast and budget.

Input from RM, PMO and FC
Input from FC
14
Earned Value Management
PERFORMANCE STATUS...Key Things to Track
EVM Schedule/Cost Variance
Typical Earned Value graph showingSchedule and
Cost Variances
  • Planned Value (PV) indicated by the Blue line is
    the agreed plan and represents what the project
    should achieve.
  • Earned Value (EV) represented by the green line
    shows what has actually been achieved or Earned.
    In this example the EV curve is diverging from
    the PV curve indicating that at the given time,
    the project has achieved less than planned.
  • Actual Cost (AC) represented by the red curve
    shows the actual cost of the EV. In this example
    the AC has exceeded the costs of the PV.
  • Cost Variance (CV) expresses the cost difference
    between the EV and the AC.
  • Remember it is the difference between EV and AC
    that gives the variance. Comparisons of AC
    against PV is misleading.
  • Schedule Variance (SV) expresses the schedule
    difference between the EV and PV.

5,000
PV
AC
cv

sv
EV
TIME
5 months
schedule variance EV - PV negative
number cost variance EV - AC negative
number
behind schedule, over cost
Use Data for Decision Making
QUESTIONS
  • To realise the benefit of EVM it is essential
    that you have confidence in the data, that you
    take heed of the information it gives you and
    that you act appropriately on that information.
  • If the graph used in this tutorial was an actual
    output on your project. What questions would
    arise and what actions might you take?
  • - How critical is my schedule? E.g. could
    adjustments be made?
  • - Can additional resources be applied? e.g to
    work overtime
  • - Can any tasks be completed concurrently?
  • - Are there technical innovations which could
    speed up the process?
  • - Can the requirement be reduced? E.g. remove
    gold plating.
  • - Would a schedule risk assessment expose the
    impact to project?
  • - Could any tasks be re-scheduled? E.g. Time
    phasing
  • - Could less costly facilities be employed?
  • - Are there tasks which can be deleted?
  • Comment - This list is not intended to be
    exhaustive..

Five Basic Performance Data Questions Answers
15
Programme Risk Report
KEY RISKS EQUIPMENT
CONTINGENCY
EP Risk Budget Exposure
NOTE Increased exposure reflects proposed Stage
2 Trials over-budget risk
Input from PMO
KEY RISKS SUPPORT
CONTINGENCY
STP Risk Budget Exposure Will show an analysis
of 10, 50, 90 exposure against STP Risk
Budget, when STP Risk data is sufficiently
mature STP Affordability An IAB Information
Note, to be issued through CDP mid Oct, concludes
that affordability against existing budget levels
in average annualised cost terms can be achieved
for a class of 8 ships or less. More work will
be necessary to achieve a more acceptable
RDEL/CDEL balance during the development of the
support solution although the full scale of the
issue cannot be resolved without external Project
assistance.
16
Programme Financial Report
EQUIPMENT PLAN FORECAST AGAINST APPROVAL
NARRATIVE
  • EP07 is for 8 ships based on the PRU BTP risk
    adjusted cost of ????m (????m near cash) with
    cost growth compared to EP05 of ???m (near
    cash).
  • Commitment Against Approval
  • ASSET DELIVERIES - No planned asset deliveries
    during FY06/07
  • First Asset deliveries planned during FY07/08
    (PAAMS Missiles Training equipment)

Input from FC
IN_YEAR MANAGEMENT
NARRATIVE
Equipment Plan Forecast 558m (control total
616m). No from AP5 forecast. Risk
Analysis Op Costs Forecast ?????m compared to
Budget of ????m, variance of ????m. No change
from AP5 forecast.
17
MPR/Approvals Forecast Summary
  • MPR/NAO
  • Draft MPR06 Audit report received from NAO.
    Shows in-year cost growth of ???M (to ????M)
    and delay of 7 months (to Dec 09). Re-statement
    of MPR05 figures (adding a further cost growth of
    ??M) not shown against MPR06. Also shows 3 KURs
    at risk due to potential reduction in capability
    on FOC at ISD. Proposed text amendment to
    reflect accurately the progressive demonstration
    of capability.
  • The cost growth reported in MPR06 enabled the DPA
    to achieve Key Target 3 and the PSA target for
    2005/06. There may be sensitivity in reporting
    all the 2006/07 potential cost growth, within
    CMIS, so soon after the NAO agreeing the MPR06
    figure in June 2006. The proposed course of
    action is to update CMIS once negotiations with
    Industry have reached a mature and stable
    position, planned for 1st Qtr 2007.
  • PCT SUMMARY

Input from BM/FC
18
UOR Summary Data
KEY DATA
19
Section Three
  • Support and Service Delivery
  • Performance against CSA or JBA slide 20
  • Availability / Operating Hours Slide 21
  • Customer Wait time / Safety Risks Slide 22
  • Supply Chain Issues Slide 23

20
Performance against User CSA / JBA / OSP outputs
11Month of data assessed eg, APR 07
  • State overall FFP and comment on individual
    metrics if showing AMBER or RED
  • Comment factors contributing to metrics that have
    previously been AMBER or RED but are now YELLOW
    or GREEN
  • Example-
  • FFP - YELLOW
  • FE_at_R - RED - commentary
  • ABORTS - AMBER - commentary



21
Performance against User CSA / JBA / OSP outputs
2Month of data assessed eg, APR 07
Availability / Operating hours chart etc to be
inserted here if applicable

22
CUSTOMER WAIT TIME (As appropriate)
SAFETY RISKS
23
Supply Chain Performance Month of data
assessed eg, APR 07
Insert details of any known demand failure trends
or supply chain issues with details by
exception only If EVM is being operated for
support details should be included here
Write a Comment
User Comments (0)
About PowerShow.com