Title: IEEE 1547 Interconnecting DR with Electric Power Systems
1IEEE 1547 - Interconnecting DR with Electric
Power Systems
- PUCO Technical Conference on Interconnection
- March 9, 2006 - Columbus, OH
- Jim Lemke Cinergy
- Member IEEE 1547 Working Group
2IEEE 1547 Series of Interconnection Standards
- Currently Approved
- IEEE Std 1547 (2003) Standard for Interconnecting
Distributed Resources with Electric Power Systems - IEEE Std 1547.1 (2005) Standard Conformance Test
Procedures for Equipment Interconnecting
Distributed Resources with Electric Power Systems - Work in progress
- P1547.2, P1547.3, P1547.4, P1547.5, P1547.6
3What is IEEE Std 1547 (2003)
- This standard provides interconnection technical
specifications and requirements, and test
specifications and requirements. - The stated specifications and requirements, both
technical and testing, are universally needed for
interconnection of DR, including synchronous
machines, induction machines, or power
inverters/converters, and will be sufficient for
most installations.
4IEEE 1547 Limitations
- lt 10MVA aggregate DR capacity
- Interconnection at typical primary or secondary
voltage levels - Primary voltage 2.4kV to 34.5kV
- Secondary voltage less than 600 volts
- Radial systems are the main emphasis
- Network systems
- P1547.6 Draft Recommended Practice for
Interconnecting Distributed Resources with
Electric Power Systems on Secondary Networks
5IEEE 1547 Requirements
- Interconnection technical specifications and
requirements (Section 4) - General requirements
- Response to Area EPS abnormal conditions
- Power quality
- Islanding
- Interconnection test specifications and
requirements (Section 5) - Design test
- Production tests
- Interconnection installation evaluation
- Commissioning tests
6Some IEEE 1547 Requirements Address DR Impacts
During Normal Area EPS Operation
Examples
- 4.1.1 Voltage Regulation
- 4.1.8 Interconnect integrity
- 4.3.2 Flicker
- 4.3.3 Harmonics
74.4.1 Voltage Regulation
- The DR shall not actively regulate the voltage
at the PCC. - The DR shall not cause the Area EPS service
voltage at other local EPSs to go outside the
requirements of ANSI C84.1-1995, Range A.
8Voltage Impact
Utility Substation
12.47 kV
Voltage Regulator
Other Loads
Voltage Profile
Upper Voltage Limit
126 V
ANSI C84.1 Range A
Lower Voltage Limit
114 V
9Voltage ImpactPeak Load Without DR
Utility Substation
12.47 kV
Voltage Regulator
Other Loads
Voltage Profile
Upper Voltage Limit
126 V
Substation Voltage Range
Lower Voltage Limit
114 V
10Voltage ImpactLight Load Without DR
Utility Substation
12.47 kV
Voltage Regulator
Other Loads
Voltage Profile
Upper Voltage Limit
126 V
Substation Voltage Range
Lower Voltage Limit
114 V
11Voltage Impact Light Load With DR
Utility Substation
12.47 kV
Voltage Regulator
DR
Other Loads
Voltage Profile
Upper Voltage Limit
126 V
Substation Voltage Range
Lower Voltage Limit
114 V
12Most IEEE 1547 Requirements Address DR Response
During Abnormal Area EPS Conditions
Examples
- 4.1.2 Integration with Area EPS Grounding
- 4.1.5 Inadvertent energization of the Area EPS
- 4.2.1 Area EPS faults
- 4.2.2 Area EPS reclosing coordination
- 4.2.3 Voltage
- 4.2.4 Frequency
- 4.4.1 Unintentional Islanding
13Unintentional Islanding
Substation Circuit Breakers
1
12.47 kV
69 kV
2
3
Substation
S
DR
Customer with DG
14Unintentional Islanding
Substation Circuit Breakers
1
12.47 kV
69 kV
2
If Circuit Breaker 2 opens, this circuit
including all its load along with the DG become
separated from the rest of the system in an
island
3
Substation
S
DR
Customer with DG
15Unintentional Islanding
Substation Circuit Breakers
1
12.47 kV
69 kV
2
3
Substation
S
Customer with DG
S
DR
Customer without DG
16Unintentional Islanding
Substation Circuit Breakers
1
12.47 kV
69 kV
2
3
If the fuse opens, the two customers on this
transformer along with the DG become separated
from the rest of the system in an island
Substation
S
Customer with DG
S
DR
Customer without DG
17Intentional Island
- P1547.4 Draft Guide for Design, Operation , and
Integration of Distributed Resource Island
Systems with Electric Power Systems
18Design Tests(IEEE 1547 Requirements That Can Be
Pre-certified)
- A determination that some requirements are met
can be done by type testing of interconnection
equipment, such as - Response to abnormal voltage frequency
- Interconnect Integrity
- Unintentional islanding (active techniques only)
- Harmonics
- IEEE 1547.1 Specifies the details of design tests
- Certification concept (example UL 1741)
- Does not imply that all IEEE 1547 requirements
are met and the device can be used anywhere
19Installation Review Study(IEEE 1547
Requirements That Cannot Be Pre-certified)
- A determination that other requirements are met
can only be done by an installation design
evaluation that includes Area EPS system
characteristics at the DR site. - Impact on Area EPS system voltage
- Grounding integration
- Isolation device
- Area EPS fault sensing
- Reclosing coordination
- Flicker
- Unintentional Islanding (passive techniques)
20Technical Issues Not Addressed by IEEE P1547
- Impact on Area EPS overcurrent protection scheme
- Penetration limits
- There is a lot we dont know about the effects of
significant DG penetration. - Redundancy
- Acceptable methods to meet requirements
- Dynamic character of distribution systems
- Loads change - increasing or decreasing
- Configuration changes frequently
21Additional P1547 Series Documents Under
Development
P1547.2 Draft Application Guide for IEEE 1547
Standard for Interconnecting Distributed
Resources with Electric Power Systems
P1547.3 Draft Guide for Monitoring, Information
Exchange, and Control of DR Interconnected with
Electric Power Systems
P1547.4 Draft Guide for Design, Operation , and
Integration of Distributed Resource Island
Systems with Electric Power Systems
P1547.5 Draft Technical Guidelines for
Interconnection of Electric Power Sources greater
than 10MVA to the Power Transmission Grid
P1547.6 Draft Recommended Practice for
Interconnecting Distributed Resources with
Electric Power Systems on Secondary Networks