Overall route ugie to langeni - PowerPoint PPT Presentation

1 / 69
About This Presentation
Title:

Overall route ugie to langeni

Description:

Overall route ugie to langeni – PowerPoint PPT presentation

Number of Views:350
Avg rating:3.0/5.0
Slides: 70
Provided by: malcolm76
Category:
Tags: jine | langeni | overall | route | ugie

less

Transcript and Presenter's Notes

Title: Overall route ugie to langeni


1
DEPARTMENT OF ROADS AND TRANSPORT
UGIE TO LANGENI ROAD UPGRADING PROJECT
PTB5-03/04-2162
PHASE 2 NCEMBU PLATEAU TO LANGENI DEPARTMENT
TRANSPORT NATIONAL TECHNICAL STEERING
COMMITTEE SITE VISIT 12 NOVEMBER 2008
2
Locality Plan
3
A BRIEF BACKGROUND TO THE PROJECT
  • Initially community driven
  • Discussions with Local Authorities and Department
    Roads and Transport
  • Priority Project
  • Integrated 5 Year Transport Infrastructure Plan
  • Provincial Growth and Development Plan

4
PURPOSE OF THE ROUTE
  • Improving access to markets
  • Providing a more direct route
  • Increasing production at Sawmills due to
    increased
  • aforestation
  • Improving the quality of life of communities
  • Part of the Maclear Ugie-Mthatha corridor
  • Complementary to Kei-East London Rail upgrade
    project

5
FEASIBILITY STUDY/ ALTERNATIVE ROUTES
  • Routes to Langeni Sawmill/ new PG Bison Mill
    gt60 km longer
  • Alternative routes similar geology
  • Nov 2001 Jan 2003

6
Phase 2 - Ncembu Plateau to Langeni Sawmill
  • HHO Africa / Camdekon JV appointed 4 July 2003
    for Preliminary and Detail Design
  • Dept Roads and Public Works and Dept Transport
    wanted to go to tender November 2003, extended to
    February 2004
  • Fast track project Phase 1 and 2 required to be
    completed simultaneously Dec 2006 requirement
    of Dept Roads Public Works and Dept Transport
  • 1st Preliminary Design Drilling Investigation
    Contract completed December 2003
  • Survey completed January 2004

7
UGIE TO LANGENI AND R61
  • 3 Separate Phases for design and construction.
  • Phase 1 Ugie to Nyibeni Village 32,7 km
  • Phase 2 Nyibeni Village to Langeni Sawmill
    15,3 km
  • Phase 3 Langeni Sawmill to R61 (Tabase)
    17,3 km
  • 65,3 km

8
TYPICAL PLATEAU TERRAIN
Several wetlands and marshes
9
NCEMBU PLATEAU km 34-38
10
NYIBENI VILLAGE GABION RETAINING WALL AND
CASCADES/ OUTLET
11
TRIP DOWN THE MOUNTAIN PASS SECTION OF THE ROUTE
The following slides show the types of vegetation
encountered along the route as well as the
steepness of the escarpment section, from the
Plateau to the foothills
12
SV_42030_D
13
SV_42660_D
14
NCEMBU TO LANGENI
  • The Planning and design of 17,8km of new road
    through greenfields sections of plateau
    grasslands, a steep escarpment, indigenous
    forests and pine plantations.

15
NCEMBU TO LANGENI
  • This is a view of the route finally chosen to
    move from the plateau down the escarpment to the
    foothills below

16
SV_42900_D
17
SV_43320_D
Indigenous vegetation and steep crossfall
18
SV_43570_D
Indigenous and Commercial Forests km 43,1 to km
47,1 except firebreak
19
COMPLEX SECTION OF ROUTE FROM THE ESCARPMENT TO
LANGENI SAWMILL
V 1
Original alignment
V 2
B 2
Final Alignment
B 1
Indigenous and Commercial Forests km 43,1 km
47,1
20
SV 42 560
3o m cutting
Typical Rock Cutting Cross Section
21
LONGITUDINAL SECTION
  • As a result of ground constraints, and to reduce
    environmental impact, the proposed route will
    have steep slopes in certain sections

22
SV 43 000
Reinforced Earth Retaining Wall 1
23
ENVIRONMENTAL CONDITIONS
  • Extensive input and requirements from DWAF/
    DEAET/ Langeni in scoping and EIA stages
  • Botanical Inventory of road footprint through all
    indigenous forests.
  • Restricted access to indigenous forests during
    investigation stages.
  • Full time ECO
  • Indigenous tree harvesting requirements
  • ROD 21/06/2004
  • DWAF Indigenous Forestry Licence

24
Typical area recovered plants
km 42 to km 43,5
  • 2 ha Protea Grassland
  • 3 ha Indigenous Forests

25
Nursery
  • 3000 bulbs and ferns
  • 4000 indigenous tree saplings
  • 40 000 Scilla Natalensis (Natal Lily)
    transplanted

26
Indigenous Timber Harvesting
km 43,2
  • 1000 m3 harvested and auctioned

27
RAINFALL SUMMARY
28
RAINFALL SUMMARY
Typical Example Worked 54,5 days of potential
125, or 44 of available working time
Similar period October 2007 March 2008
29
Weather
30
Haul Road Complete
August 2005
31
Excessive Rain Haul Road Apr06
km 42,8
32
DOLERITE CUTTINGS
Weathered Vertical and Horizontal Columnar
Jointing
33
VIEW KM 42,4 TO 42,8 WITH CATTLE TRACK
34
CUT IN DOLERITIC TALUS
  • 3 - 15 metre deep doleritic talus
  • Instability of cut slopes
  • Reinforced Earth retaining wall
  • Low shear strength of soil matrix
  • Tie back anchors into underlying bedrock

km 42,5 km 43,3
35
REINFORCED EARTH WALL 1 TERRANAILING
36
CAVITIES IN-SITU MATERIAL/ TALUS
37
TERRANAILING
38
TERRANAILING/ GUNITE PROTECTION/ CONCRETE PLINTHS
Wall 1 km 42,7
39
CONNECTING TERRATREL, PARAWEB TERRANAILING
40
WALL 1B CUT STABILISATION
km 42,6 42,8
41
WALL 1A 1B GUNITING / TERRANAILING
42
STORMWATER DIVERSION BERM
Degraded Wetland above cuttings km 42,6 42,8
43
REINFORCED EARTH WALL 1
44
VIADUCT 1 CROSS SECTION
45
GENERAL ACCESS VIA BOARDWALK
46
VIADUCT 1
Blondin Cableway/ Leap frogged Crane Comparison
47
VIADUCT 1 SPAN 7 BEAMS
48
VIADUCT 1 SPANS 7 6, BEAM YARDS, LAUNCHING
GIRDER
49
VIADUCT 1 SPAN 6, 5 4 / INDIGENOUS FOREST /
BOARDWALK ACCESS
50
VIADUCT 2
Original Viaduct 2 with Caissons
51
VIADUCT 2
Modified Viaduct 2
52
VIADUCT 2 UGIE ABUTMENT, LANGENI EXCAVATION
53
SLIP AT KM 44,6
54
KM 44,6 CUTTING STABILISATION 90 COMPLETE
55
WALL 4
56
TYPICAL OUTLET STRUCTURE
57
REINFORCED EARTH WALL 8 HIGHEST (18M)
58
CONSTRUCTION SEQUENCE
59
CONSTRUCTION SEQUENCE
60
CONSTRUCTION SEQUENCE
61
PAVING TEAM CONCRETE ROAD
Typical team - preparation 15
persons - paving 20 persons Anticipated
person days to concrete pavement completion
- 20 000 person days
CONCRETE VOLUMES 14 000m3 concrete road 37
500m3 structures, side drains
62
AERIAL VIEW OF TEAM
63
COMPLETED SECTIONS CONCRETE ROAD
64
NEW MILL AT UGIE
65
MOUNTAIN PASS
66
VIADUCT 1 TO PHASE 3
67
CONTRACT PROCUREMENT
  • Contractor LM3 Joint Venture Rumdel,
    LikThemba, Mametse, Themcon, Makhuba Misela
    Construction
  • Works Value R293 563 014-19

Project Participation Goals
Cumulative labour 277 000 person days (538
persons from local communities To end contract
estimate 300 000 person days Training R750
000.00 including Eco-tourism (16 persons)
68
CATTLE TRACK AND FOOTPATH ONLY PREVIOUS ACCESS
69
THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com