Title: Status and plans for the ILC cryomodule design
1Status and plans for the ILC cryomodule design
- Tom Peterson, Fermilab
- TESLA Technology Collaboration Meeting
- Frascati, 6 December 2005
2TTF cryomodule is our reference
3TESLA-style module information . . .
- http//ilc.desy.de/e627/e634/e730/e745/index_eng.h
tml - Links to talks presented by Lutz Lilje, Axel
Matheisen, W.-D. Mueller, Bernd Petersen, Nick
Walker, and others at our December 6 - 7, 2004,
module meeting at DESY - http//lcdev.kek.jp/ILCWS/
- First ILC workshop, November 13 - 15, 2004 at
KEK - http//tesla-new.desy.de/content/index_eng.html
- DESY TESLA page with link to the TESLA Design
Report and other information including talks and
posters from the March 2004 ITRP visit
4Sources of Information
- Bernd Petersen, Lutz Lilje, Axel Matheisen, Nick
Walker, Hans Weise, and others (DESY) - Carlo Pagani (INFN)
- Terry Garvey (LAL-Orsay)
- Tom Nicol (Fermilab)
- Don Mitchell (Fermilab)
- John Weisend (SLAC)
- TESLA TDR (March 2001)
- And others!
5Some History of Changes in Design Features for
TTF Cryomodule
- Three generations of TTF cryomodule designs
- TTF-I was module 1
- TTF-II was modules 2 and 3
- TTF-III is modules 4 - 8
- TDR called for some significant changes from all
of the above such as a longer module with 12
cavities per module - Next -- TTF III is our baseline design
- X-FEL modules will differ in some details from
TTF type III - ILC modules will begin as a few type III
prototypes, which are essentially type III with
the quad at 2 K and supported like a cavity - Planning has begun for the next generation ILC
module design, type IV, based on the type III
design
6(No Transcript)
7Features of type III cryomodule
- Allows for fixed couplers
- Invar rod and roller bearings allow cavities to
remain axially fixed while the 300 mm tube
shrinks - Smaller cross section results in standard pipe
size for outer vessel - Axial position of last support changed to stiffen
structure near quadrupole
8Cryomodule III model -- helium vessels in the
vacuum vessel
CAD model based on DESY design imported and
modified by Don Mitchell, Fermilab
9Cryomodule III model -- helium vessels in the
vacuum vessel with input couplers and quadrupole
CAD model based on DESY design imported and
modified by Don Mitchell, Fermilab
10We have a general consensus regarding what needs
changing
- Based largely on TTF experience, but also Jlab
and others - Consensus collected by working groups at
meetings, including but not limited to - SLAC (14 - 16 Oct 2004)
- KEK (13 - 15 Nov 2004)
- DESY (6 - 8 Dec 2004)
- Snowmass (August 2005)
- SMTF collaboration meeting (5 - 7 Oct 2005)
11Type IV cryomodule will include the following
features from Type III
- 8 cavities per module
- Same cooling scheme and cryogenic system concept
- Same vacuum vessel diameter and 300 mm pipe
diameter - Nearly the same pipe locations and arrangement
- Same cavity centerline location relative to
vacuum vessel - Same support posts
- Same thermal shields concept, although coupler
port locations move - Same cavity support detail (300 mm header as
structural backbone with cavities held by roller
bearings and invar rods) - Same input coupler (at least in terms of mounting
and interface to vacuum vessel, cavity, and
thermal shields)
12Helium vessel supports
13Support posts
14Thermal shield installation
15(No Transcript)
16ILC cryogenic system overview
- Saturated He II cooled cavities _at_ 2 K
- Helium gas thermal shield _at_ 5 - 8 K
- Helium gas thermal shield _at_ 40 - 80 K
- Two-phase line (liquid helium supply and
concurrent vapor return) connects to each helium
vessel - Two-phase line connects to gas return once per
module - A small diameter warm-up/cool-down line connects
the bottoms of the He vessels (primarily for
warm-up) - Subcooled helium supply line connects to
two-phase line via JT valve once per string
(12 modules)
17TESLA cryogenic unit
18(No Transcript)
19Type IV cryomodule will differ from type III in
the following general areas
- Cavity iris-to-iris spacing reduced to 283 mm
- Reduces length from 12.20 to about 11.8 m, get
0.75 packing - Slow tuner modified to allow closer
cavity-to-cavity spacing (could mean switching to
blade tuner design, but choice still open) - Fast tuner -- new design
- Quad/corrector/BPM package under center post,
hung from 300 mm tube, not on rollers (diverging
from X-FEL) - Two major module types, one with quad and one
without
20More differences of Type IV cryomodule from type
III
- Interconnect features modified to accommodate
input coupler at end of cryostat - Quad current leads may be new and different, with
local impact on thermal shields and vacuum vessel
ports - Provisions for quad power lead connection at
center of module - Some pipe sizes will be increased for lower
pressure drops with high flow rates -- would like
to retain long cryogenic unit lengths up to limit
of 300 mm pipe and cryo plants. Present effort
includes re-analysis of heat loads, flow rates,
and cryogenic system thermal process.
21(No Transcript)
22Cavity Interconnect
23Module predicted heat loads
24ILC cryogenic system much larger than TESLA 500
- 8 cryogenic plant locations
- Approximately 5 km spacing
- Each location with 2 cryogenic plants of about
the maximum size -- each plant equivalent to
about 24 kW at 4.5 K - Each plant about 6 MW wall plug power
- ILC cryogenics about 100 MW total
25Module pipe sizes increase
26(Increase diameter beyond X-FEL)
(Increase diameter beyond X-FEL)
(Review 2-phase pipe size and effect of slope)
27Some critical open design issues
- Quad/corrector/BPM package is a major unknown
right now and goes into the heart of the module - Tuner details, slow and fast, but especially fast
tuner - Vibrational analysis, which will be compared to
measurements for verification of the model for
future design work - Development of module and module component test
plans - Verification of cavity positional stability with
thermal cycles - Design of test instrumentation for the module
- Robustness for shipping, analysis of shipping
restraints and loads, shipping specifications - Active quad movers(?) A complication
28(No Transcript)
29(No Transcript)
30Blade tuner concept
31(No Transcript)
32Other open design issues
- Design for manufacturability, ease of assembly,
and cost reduction are always considerations - Part of the type IV design effort will also be a
consideration of other options - particularly with respect to quad location and
support - but also perhaps with respect to tuners and/or
other features - level of effort on these options will be dictated
by our manpower and schedule.
33Organization of effort
- An international effort
- Need division of tasks to make best use of our
resources - Minimize duplication of efforts
- Take advantage of ideas and expertise
- Pursue options with parallel efforts
- Each institution has limited resources
- Work has begun
- Fermilab has organized a group to do type IV
design, other labs have also expressed interest
and/or begun
34Type IV probable schedule
- Design module -- 12 - 24 months (2006 - 2007)
- Magnet/BPM package
- Tuners, etc.
- Integrate into module design
- Build and test -- 12 - 18 months (2007 - 2008)
- In addition to module, need module test stand and
test facility! - Total 2 to 3 1/2 years, depending on scope of
work and availability of resources.
35X-FEL Modules
- 100 modules will be industrially produced
- Brings us to the level of manufacturing
quantities - Some differences from ILC, but much of module
design and manufacturing is the same - Cavity supports, thermal shields, MLI, vacuum
vessel assembly, internal piping, etc. - X-FEL experience will be important and valuable
part of ILC module development - X-FEL module effort will stay ahead of ILC effort
- Remain in close contact and take advantage of
similar designs, experience, and industrial input
to design
36After Type IV--gt increasing quantities
- Experience with large quantities of SC magnets
follows an old engineering rule (factors of 10) - 1 prototype
- 10 pre-production prototypes
- 100 first production run (X-FEL!)
- Not throw-aways but slower production, still
making adjustments, relatively large fraction of
reject/rework - 1000 full production run
- There are design changes and manufacturing method
changes at each stage
37Industrialization, impact on design
- As we move to production of quantities of modules
in industry, the design will continue to change - Reduction of required labor
- Less costly materials
- Less costly manufacturing of components
- Design for more efficient assembly
38Type IV is not the (final) ILC design
- Test results of types III and IV will teach us a
lot - There will be some choices beyond type IV from
parallel development efforts - Industrialization will have a significant impact
on the design - Type IV is the next step in module design for ILC