PROJECT REPORT - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

PROJECT REPORT

Description:

The ROB comprises following different structure:- 1. Main railway ... required shall be less since the same required only nullify the tension. ... – PowerPoint PPT presentation

Number of Views:247
Avg rating:3.0/5.0
Slides: 36
Provided by: hos75
Category:

less

Transcript and Presenter's Notes

Title: PROJECT REPORT


1
PROJECT REPORT
  • DESIGN CONCEPTS OF BOW STRING GIRDER (40 M SPAN)
    OF ROAD OVERBRIDGE AND DESIGN OF SUB STRUCTURE
    FOR THE SAME.

2
PRESENTED BY
  • 1. R.M.MEENA
  • (XEN/C/JU/NWR)
  • 2. SIVA KUMAR (AXEN/Designs/MTP/MS/S.R.)
  • 3. L.N.LOKHARE
  • (AXEN/C/KTT/WCR)
  • 4. L.B.SINGH MAURYA
  • (Vice Principal/SRETC/TBM/S.R.)

3
INTEGRATED COURSE BATCH NO-514
  • PROJECT GUIDE
  • Sri.G. Bansal
  • COURSE DIRECTOR
  • Sri A.K.Rai

4
INTRODUCTION
  • On Indian Railway there are 16471 Nos of manned
    level crossings and 19284 Nos of unmanned level
    crossings as on date. These Level crossings are
    affecting the safe effective functioning of
    Railways. The Level crossings are the accident
    prone zones and causes delay of trains due to
    detention by road traffic at gate.

5
INTRODUCTION- cont
  • There are loss of valuable human life and
    Railways properties due to accidents taking place
    on this level crossings. Keeping safety point of
    view it become necessary to replace these level
    crossings by ROB/RUB..

6
INTRODUCTION- cont
  • Replacing the level crossings with ROB/RUB are
    being done by Railways in a phased manner based
    upon its TVU. Where ever possible ROB is
    preferable over RUB due to its less maintenance,
    effective usefulness, even though the initial
    cost of ROB is more.

7
SCOPE OF THE PROJECT
  • The ROB comprises following different structure-
  • 1. Main railway span (40 m)
  • 2. Approach spans having 20 m spans
  • 3. Abutment
  • 4. Reinforced earth retaining wall beyond
    abutment on the approaches where height is less
    than 4.0 m

8
SCOPE OF THE PROJECT - cont
  • As far as super structure is concerned only
    design concept of Bow string girder is
    emphasized. However for substructure complete
    design is made and enclosed.

9
ELEMENTS OF BOW STRING GIRDER
  • MAIN I- GIRDER
  • Main I- girder is purely a tension member because
    of its geometry. This member is proposed as a
    prestressed member .The amount the prestressing
    required shall be less since the same required
    only nullify the tension.

10
ARCH MEMBER
SUSPENDERS
MAIN I GIRDER
11
ARCH MEMBER
  • Arch member is always in compression and hence
    RCC is sufficient to take this load. A member
    size of 450x900 at supports and 450x600 at crown
    is normally sufficient to carry the compression
    for this 40 meter span.

12
SUSPENDERS
  • Since suspenders are pure tension members and it
    does not requires any flexural rigidity , these
    members can be provided as HTS strands firmly
    anchored between main I beams and arch members

13
CROSS GIRDER
  • Cross girder can be of RCC, which spans between
    main I -girders. The spacing of cross girders is
    kept as 4.15 meter the span is 8.0 meter. At
    the top of cross girder, a continuous slab of
    span of 4.15 meter and thickness of 230 mm is
    provided. Over the slab road-wearing surface as
    per IRC, specification is provided.

14
C LINE OF SPAN
L
C LINE OF BEARING
BOW STRING
L
CROSS GIRDER

4150
8m
41500
PLAN AT DECK LEVEL
15
LOADING
  • Live load
  • Load as per IRC-6
  • Combinations are
  • 1. Single lane 70R wheeled/track vehicle
  • 2. Two lane IRC class A, wheeled

16
ADVANTAGES OF BOW STRING OVER DECK TYPE GIRDERS
  • There is some considerable savings in depth of
    construction in case of bow string girder
    compared to typical deck type girder Due to
    reduced depth of construction, the over all
    length of ROB get reduced and overall economy
    achieved

17
7500
ROAD SURFACE
2500
DEPTH OF CONSTRUCTION2.50m
BOX GIRDER TYPE ROB
18
7500
BOW STRING GIRDER
ROAD SURFACE
2400
1000
DEPTH OF CONSTRUCTION1.0m
BOW STRING GIRDER TYPE ROB
19
DESIGN CONCEPT OF BOW STRING GIRDER
  • LIVE LOAD
  • Like our railway bridge rules, these IRC codes
    does not provide any EUDL,so for the above
    rolling loads maximum bending moment and shear
    force shall be worked out using STAAD-PRO 2003
    software. However a manual calculation is also
    shown. Due provision for impact is also
    considered as per the code.

20
DEAD LOAD
  • This comprise of dead load of all element of bow
    string span ,the carriage way wearing coat, foot
    path and other miscellaneous load such as cables,
    parapets, crash barriers have been considered

21
WIND LOAD
  • Wind load is arrived at as per IS 875
    part-III.the wind intensity multiplied by the
    projected area gives the wind load on the
    structure.

22
SUB STRUCTURE
  • The substructure consists of two numbers of
    1.80 meter dia column spaced at 8.0 meter apart.
    The depth of trestle beam is fixed as 1.25 meter
    for stiffness and other practical consideration
    such as requirement during construction and
    replacement of bearing.

23
8.0m
1.25m
6.525m
COLUMN 1.80m dia
1.80m
Rail level
PILE CAP
PILE 1.0m dia
ELEVATION OF SUBSTRUCTURE
4
24
LOADS AND OMENTS ON COLUMN
  • As we know the the column is critical at the
    pile cap level . Maximum moments will come at
    this level which are all explained through the
    following sketches. Algebraically adding all the
    moments the column section is designed

25
SESMIC LOAD
  • Lateral Seismic Coefficient0.04
  • Importance Factor 1.5 (for important bridges)
  • Foundation system factor 1.0 (for pile
    foundation)
  • Design for seismic force.04x1.5x1.0.06

26
SESMIC LOAD
  • Code followed IRC 78
  • Even though the seismic load does not affect the
    super structure, the impact on the substructure
    design is considerable.
  • Seismic Zone III

27
Adjoining span -20m
Bow string span- 40m
Lumped mass of super structure
Lever arm
Pile cap
1.DUE TO DEAD LOAD
Pile
28
Adjoining span -20m
Bow string span- 40m
Lumped mass of trestle beam
Lever arm
Pile cap
2.DUE TO DL OF SUB STRUCTURE
Pile
29
Adjoining span -20m
Bow string span- 40m
y
x

Lower load
Higher load

Un balanced moment higher load y-lower load
x
Pile cap
Pile
30
Adjoining span -20m
Bow string span- 40m
1.83 m

Lever arm
Pile cap
4. DUE TO LIVE LOAD
Pile
31
Foundation
  • The foundation system consists of four no of 1.0m
    dia pile spaced at 3.0m apart. The piles are
    proposed to be founded on hard strata, which is
    available at 25.0m depth. The piles are of bored
    cast in situ.

32
Foundation
  • Max. vertical Load in pile workout to be -
  • under seismic condition 264 tonnes
  • under normal loads 214
    tonnes
  • lateral load per pile 14
    tonnes

33
Foundation
  • Vertical load bearing capacity of pile 320 t
  • The above capacity of piles is based on soil
    capacity at site. The pile derives its capacity
    both from friction as well as end bearing.

34
FOUNDATION
  • Reinforcement design of pile
  • The length of fixity of pile below ground level
    Le is found based on lateral modulus of
    subgrade reaction of the pile
  • The moment on pile Horizontal load x Le
  • Based on the moment and the vertical load on the
    pile,the reinceforcement of the pile is designed

35
Pile cap
L12.5m
Le
5.318m
L22.5m
CALCULATION OF LENGTH OF FIXITY OF PILE
Write a Comment
User Comments (0)
About PowerShow.com