Title: MRP, MRP II, and ERP
1 2Overview
- MRP, Material Requirements Planning
- Planning and scheduling technique used for batch
production of assembled items. - MRP II, Manufacturing Resource Planning
- ERP, Enterprise Resource Planning
- The extensive use of software to integrate record
keeping and information sharing throughout an
organization.
3Independent vs. Dependent Demand
- Independent demand Demand of finished goods.
- Dependent demand Demand for items that are
subassemblies or component parts to be used in
the production of finished goods. - The amount of dependent demand is the function of
the amount of independent demand.
4Material Requirement Planning (MRP)
- Material requirements planning (MRP)
Computer-based information system for ordering
and scheduling of dependent demand inventories. - What to order
- When to order
- How much to order
5(No Transcript)
6MPR Inputs Master Schedule
- Master Production Schedule
- which end items are to be produced,
- when they are needed, and
- in what quantities.
- Sources of quantities customer orders,
forecasts, orders from warehouses, and external
demand.
7MPR Inputs Master Schedule
Figure 14-4
8MRP Inputs Bill-of-Materials
- Bill of materials A listing of all of the raw
materials, parts, subassemblies, and assemblies
needed to produce one unit of a product. - Product structure tree Visual depiction of the
requirements in a bill of materials, where all
components are listed by levels.
9MRP Inputs Bill-of-Materials
10MRP Inputs Bill-of-Materials, Example
- Example Use the information presented in the
following figure to do the following - Determine the quantities of B, C, D, E, and F
needed to assemble one X. - Determine the quantities of these components that
will be required to assemble 10 Xs, taking into
account the quantities on hand (i.e., in
inventory) of various components.
Component On Hand
B 4
C 10
D 8
E 60
11MRP Inputs Bill-of-Materials, Example
12MRP Inputs Bill-of-Materials, Example
13MRP Inputs Bill-of-Materials, Example
14MRP Inputs Bill-of-Materials, Summary
- Many products have considerably more components.
- Timing is essential (i.e., when must the
components be ordered or made). - The amounts on hand must be netted out (i.e.,
subtracted from the apparent requirements) to
determine the true requirements. - Accurate records are a prerequisite.
- complex and time-consuming
15MRP Inputs Inventory Records
- Inventory records refer to standard information
on the status of each item by time period. - Gross requirements, scheduled receipts, and
expected amount on hand. - Supplier, lead time, and lot size.
- Changes due to stock receipts and withdrawals,
canceled orders, and similar events. - Like the bill of materials, inventory records
must be accurate.
16MRP Processing
- MRP processing takes the end item requirements
specified by the master schedule and "explodes"
them into time-phased requirements for
assemblies, parts, and raw materials using the
bill of materials offset by lead times. - The determination of the net requirements
(netting) is the core of MRP processing.
17MRP Processing
Figure 15-8
18MRP Processing Terminologies
- Gross requirements
- Schedule receipts
- Projected on hand
- Net requirements
- Planned-order receipts
- Planned-order releases
19MRP Processing Example
- A firm that produces wood shutters and bookcases
has received two orders for shutters one for 100
shutters and one for 150 shutters. - The 100-unit order is due for delivery at the
start of week 4 of the current schedule, and the
150-unit order is due for delivery at the start
of week 8. - There is a scheduled receipt of 70 wood sections
in (i.e., at the beginning of) week 1. - Each shutter consists of two frames and four
slatted wood sections. The wood sections are made
by the firm, and fabrication takes one week. The
frames are ordered, and lead time is two weeks.
Assembly of the shutters requires one week. - Determine the size and timing of planned-order
releases necessary to meet delivery requirements
under each of these conditions - Lot-for-lot ordering (i.e., order size equal to
net requirements). - Lot-size ordering with a lot size of 320 units
for frames and 70 units for wood sections.
20MRP Processing Example
21MRP Processing Example, Lot-for-Lot Ordering
22MRP Processing Example, Lot-Size Ordering
23MRP Processing Pegging
- Pegging is the process of identifying the parent
items that have generated a given set of material
requirements for an item.
24MRP Processing Pegging, Example
- For example, consider the two product structure
trees shown below. - Suppose that there is a beginning inventory of
110 units of D on hand, and all items have lead
times of one week. - A cancellation of 50 units of C will require the
pegging information in the following figure.
25MRP Processing Pegging, Example
26MRP Processing Regenerative vs. Net Change
- A regenerative system is updated periodically. It
is essentially a batch-type system. - Stable system.
- Long lead time.
- Less processing load.
- A net change system is continuously updated. Only
the changes are explored through the system,
level by level the entire plan would not be
regenerated. - Frequent change.
- Up-to-date information for planning and control
purposes.
27MRP Primary Outputs
- Planned orders - schedule indicating the amount
and timing of future orders. - Order releases - Authorization for the execution
of planned orders. - Changes to planned orders - revisions of due
dates or order quantities, or cancellations of
orders.
28MRP Secondary Outputs
- Performance-control reports
- missed deliveries and stockouts, and information
for accessing cost performance. - Planning reports
- purchase commitments and information for future
material requirements. - Exception reports
- late and overdue orders, excessive scrap rates,
reporting errors, and nonexistent parts.
29MRP Other Considerations
- Safety Stock / Safety Time Maintain smooth
operations. - Lot sizing Minimize the sum of ordering cost (or
setup cost) and holding cost. - Lot-for-lot ordering
- Economic order quantity
- Fixed-period ordering
- Part-period model
30MRP in Services
- MRP applications in services may involve material
goods that form a part of the product-service
package, or they may involve mainly service
components. - Examples Food catering and large-scale
renovations such as sports stadium or a major
hotel.
31MRP in Services
- Food catering service
- End item gt catered food
- Dependent demand gt ingredients for each recipe,
i.e. bill of materials - Hotel renovation
- Activities and materials exploded into
component parts
32Benefits of MRP
- Low levels of in-process inventories
- Ability to track material requirements
- Ability to evaluate capacity requirements
- Means of allocating production time
33Requirements of MRP
- Computer and necessary software
- Accurate and up-to-date
- Master schedules
- Bills of materials
- Inventory records
- Integrity of data
34MRP II
- Expanded MRP with and emphasis placed on
integration - Financial planning
- Marketing
- Engineering
- Purchasing
- Manufacturing
35MRP II
36ERP
- Enterprise resource planning (ERP) An expanded
effort to integrate standardized record-keeping
that will permit information sharing throughout
the organization