ACARP - PowerPoint PPT Presentation

About This Presentation
Title:

ACARP

Description:

ACARP Australian Coal Association Research Program Australian Roadway Development Improvement Project OPERATORS WORKSHOPS September 2006 OBJECTIVE AND FORMAT ... – PowerPoint PPT presentation

Number of Views:697
Avg rating:3.0/5.0
Slides: 74
Provided by: gary251
Category:
Tags: acarp | cable | pulling | safety

less

Transcript and Presenter's Notes

Title: ACARP


1
ACARP
Australian Coal Association Research Program
  • Australian Roadway Development
  • Improvement Project
  • OPERATORS WORKSHOPS
  • September 2006

2
OBJECTIVE AND FORMAT
  • Provide a forum for roadway development operators
    to
  • Learn of emerging best practice and roadway
    development initiatives
  • Learn of developments in equipment and technology
  • Network with peers, and share their experience
    and learnings (and not just their successes)
  • Identify areas for targeted research

3
FORMAT
  • Four workshop subjects presented by best practice
    operators
  • Each workshop comprises a 20-25 presentation and
    a 20-25 minute open forum for discussion and
    sharing of experiences and learnings
  • Poster board presentations by OEMs and
    researchers
  • Plenary session to
  • Capture key findings
  • Identify opportunities to improve the workshop
    process
  • Identify other issues for future workshops
  • Identify areas for targeted research
  • Workshop report with copies of presentations to
    be provided to all participants

4
INTRODUCTION
  • Prerequisites for attendance
  • A passion for roadway development, and
  • A willingness to participate in discussions and
    share experiences

5
ACARP
Australian Coal Association Research Program
  • ROADWAY DEVELOPMENT
  • TASK GROUP
  • Guy Mitchell, BMA
  • Glen Lewis, Xstrata Coal
  • Bob Miller, Centennial Coal

6
2005 DEVELOPMENT CHALLENGE Why?
  • Marked increase in demand for export coal.
  • Significant increase in capital and production
    costs.
  • Substantial improvements in longwall production
    and productivity are continuing to be achieved.
  • Improvements in roadway development are generally
    failing to keep abreast of longwall improvements.
  • Higher capacity, new generation mines are being
    planned.
  • Older mines are still struggling to survive as it
    becomes more difficult to find solutions and
    successfully apply them.
  • Unlikely that both will be realised if current
    roadway development activities and trends are
    remain unchanged.

7
2005 DEVELOPMENT CHALLENGE
  • RDTG formed design a roadmap or strategy for
    targeted RD to improve roadway development.
  • Previous attempts as one off Company
    initiatives have failed
  • Poor problem scope, planning organisation
  • Lack of Mine involvement and commitment
  • Poor execution and patience
  • Absence of information sharing (competitive
    edge)
  • Industry wide problem where common sense suggest
    joint problem solving approach where we share
    successes and failures!
  • Initial members were Anglo, BHPB, BMA,
    Centennial, Rio Tinto, Thiess, and Xstrata.
  • References to July 2005 ACARP report identifying
    what incremental and step changes can and must be
    made in roadway technology and systems
  • Development of new generation longwall mines
  • Older mines to remain competitive

8
2005 DEVELOPMENT CHALLENGE
  • Report Recommendations
  • What operators/mine managers should do
  • What mine owners should do to address key
    constraints
  • What incremental/step change initiatives should
    be pursued by ACARP
  • Focus on Key Elements
  • Coal cutting and loading
  • Roadway support
  • Coal clearance
  • Logistics (services supplies)
  • Operators Workshop
  • Industry practitioners with broad range of
    conditions
  • Detailing sub elements of the development process
  • Providing insight into where their gains have
    been made
  • Process control/continuous improvement
  • Roof/rib support practices and equipment
  • Best practice maintenance
  • Panel advances
  • Opportunity for questions and discussions

9
ACARP
Australian Coal Association Research Program
  • REVIEW OF AUSTRALIAN ROADWAY DEVELOPMENT
    CURRENT STATUS
  • Gary Gibson, ACARP

10
2005 REVIEW
  • Identify where past wins have been achieved and
    the lessons learnt.
  • Identify incremental and step changes in roadway
    development technology and systems necessary to
  • Enable new generation, high capacity longwall
    mines to be developed
  • Provide productivity gains to enable existing
    mines to compete with the new generation mines.
  • Identify specific RD opportunities for new
    technologies, equipment and associated systems.
  • Build support and commitment for a targeted 7
    year RD program.

11
INDUSTRY REVIEW PROCESS
  • Reviews conducted with representatives from
  • All longwall mines
  • Bolting hardware suppliers Hilti, Jenmar, and
    One Steel
  • Corporate offices - Anglo, BHP Billiton, BMA,
    Centennial, and Xstrata
  • Geotechnical consultants - SCT, Seedsman, and
    Strata Engineering
  • Mining contractors - HWE, Roche, Thiess, UGM, and
    Walters
  • Mining equipment OEMs - DBT, Joy, and Sandvik
  • Other OEMs Alminco, Continental, Hydramatic,
    and PJ Berriman
  • RD organisations CET, Eikon CoalStream, GSS,
    and QCAT
  • Regulators and service providers DNRM, DPINR,
    and Coal Services
  • TBM OEM/developers IHI and Pacific Tunnelling
  • In all, some 160 persons participated.
  • Structured review process at mine sites, 1 on 1
    interviews elsewhere.

12
BEST PRACTICE MINES
  • A wide range of performance levels were reported
    across a wide variety of mining conditions and
    equipment.
  • Factors other than mining conditions, and
    equipment must be at play significant
    differences with similar equipment and similar
    mining conditions!

13
BEST PRACTICE MINES
  • Key factors differentiating best practice mines
    and others
  • Driven culture, desire to succeed, focus on
    getting things right, accountability.
  • Understanding of roadway development as a
    process, and the application of short interval
    process control.
  • Degree of involvement of employees.
  • Focus on utilisation of personnel through
    provision of adequate fit for purpose
    equipment.
  • High levels of reliability and availability
    engineered into equipment, with focus on
    maintaining equipment fit for purpose.
  • Awareness of and aggressive application of new
    technology, equipment and systems to improve
    safety, productivity and costs .

14
HIGH PERFORMANCE MINES
  • High performers in poor conditions were typically
    achieving similar or better development rates
    than poor performers in good conditions.
  • Factors typically evident at high performing
    mines
  • Major focus on and prioritisation of roadway
    development.
  • Incentive schemes strongly linked to development
    performance.
  • Likely utilisation of 12CM/12/30/32 continuous
    miners in a balanced, sequential cutting and
    bolting process.
  • Ability to complete panel advances in 12 15
    hours.
  • Effective mine planning.

15
MAIN FINDINGS
  • Later generation mines with good conditions are
    likely to establish 15Mtpa mines without major
    developments in mining equipment and systems.

16
MAIN FINDINGS
  • Infrastructure limitations likely to constrain
    older mines from making major improvements in
    mine capacity.
  • Adverse conditions associated with depth (eg
    stress and gas) will pose additional productivity
    challenges to older mines, and to later
    generation mines as they mature.

17
MAIN FINDINGS
  • Technology developments are currently underway
    which will address some key process constraints
    in the short to medium term, providing potential
    to improve system capability across all mines.

18
CURRENT DEVELOPMENTS IN TECHNOLOGY
  • Five self drilling bolting (SDB) systems are
    currently in various stages of development, with
    a variety of civil sector SDB also available (but
    expensive).
  • Sandvik releasing an upgraded ABM25(S) designed
    for difficult mining conditions and 4.8m wide
    roadways. Likely to incorporate Aro
    semi-automated bolting system.
  • Joy mooted to be developing a new generation
    continuous miner for global roadway development
    market.
  • DBT established a global roadway development
    group.
  • Both IHI and Pacific Tunnelling have developed
    concepts and detailed engineering designs for
    TBMs, and project that they could be on site in
    18 24 months.

19
CURRENT DEVELOPMENTS IN TECHNOLOGY
  • Joy had 2 floor mounted 4FCT systems in operation
    in US mines, with 2 other systems then under
    manufacture for US mines.
  • Sandvik were due to shortly release a roof
    mounted continuous haulage system.
  • Continental anticipated releasing a roof mounted
    monorail based extensible and retractable
    development/longwall conveyor.
  • Cutting Edge Technologies had reportedly
    completed designs for an extensible conveyor
    system.
  • Eikon had completed design for a 250m3/hour coal
    slurry transportation system.
  • Finalisation of the ACBM was reportedly stalled
    by a failure to complete contracted development
    of an automated bolting system.

20
ROADWAY DEVELOPMENT CONSTRAINTS
  • Roof and rib bolting, and installation of roof
    and rib mesh
  • Cyclic nature of coal haulers, particularly
    beyond 70m from boot end
  • Advancement of conveyor and panel services,
    particularly with dual CM units
  • Routine installation of ventilation ducting
  • The logistics of supply, transport, distribution
    and handling - particularly at older mines.
  • Installation of long tendons as primary support
    becoming more widespread - installation equipment
    still fairly rudimentary
  • The physical demands of the work environment, the
    extent of manual handling, an ageing workforce
  • Coal cutting was not seen as a constraint at any
    mine, however the ability of machines to cut
    breakaways for cut throughs was considered to be
    a major failure of all machine configurations.

21
NEW MINING SYSTEM
  • The key attributes of a new roadway development
    mining system were identified as
  • Integrated, continuous cutting, bolting and coal
    clearance system continuous mining.
  • Automated bolting, with self drilling bolts.
  • Integrated materials supply and logistics with
    components stored in magazines or cassettes
    allowing minimal manual intervention.
  • Extensible (monorail mounted) face services (eg
    ventilation, power, water, compressed air, pump
    out).
  • Extensible, self advancing panel conveyor.
  • High capacity, automated installation of long
    tendon secondary supports.

22
INDUSTRY CONSTRAINTS
  • Real or perceived constraints to successful RDD
    of new technology and mining systems
  • Industrys ability and willingness to fund and
    sustain the RDD of new mining systems,
    particularly through tight economic conditions.
  • Few mines have sufficient development float to
    allow critical resources and mine real estate to
    be deployed to developing new technology.
  • Scarcity of managers, engineers, supervisors,
    operators and trades.
  • Limited size of Australian market, and OEMs
    propensity to develop new technology as global
    products, and for development to be done
    in-house.
  • Lead time from concept to successful
    demonstration is too long
  • loss of project champions (eg promotion or
    turnover) and
  • diminution of corporate energy and critical mass.
  • Overly restrictive legislation limiting the
    development and application of new technologies
    and the use of light weight materials.
  • Over zealous pursuit of absolute safety first by
    Inspectorate, with prosecutions in the event of
    less than absolute safety.

23
RECOMMENDATIONS
  • What mine operators and mine managers should do
    to improve development performance.
  • What mine owners should do to address key
    constraints.
  • What incremental change initiatives should be
    pursued by ACARP.
  • What step change initiatives should be pursued by
    ACARP.

24
MINE OPERATORS AND MINE MANGERS
  • Pursue industry best practice roadway
    development.
  • Fully embrace concepts of process control,
    continuous improvement, and involvement of all
    personnel in those pursuits.
  • Commit to conduct of a routine roadway
    development benchmarking process across the
    industry.
  • Commit and contribute to a regular best
    practice roadway development forum and enable
    development practitioners to share successes and
    failures, and learn of new practices,
    developments in RD, and emerging issues.
  • Through publication of Proceedings from the
    forums, support the development of a body of
    knowledge of best practice roadway development.
  • Give due recognition to development in the mines
    operation
  • Adequately resource development to enable it to
    be properly accountable for its performance.

25
MINE OWNERS
  • Develop and commit to a long term investment
    strategy to support and sustain the research,
    development and demonstration of new mining
    systems and technology.
  • Develop and commit to a long term strategy to
    develop the industrys skills base and overcome
    the scarcity of experienced mining professionals,
    engineers, supervisors, operators and trades
    personnel.
  • Challenge the restrictive legislative framework
    being imposed on the industry, and the regulators
    resort to prosecution in the event of less than
    absolute safety.
  • Fund, support and sustain
  • routine roadway development benchmarking studies
  • conduct of regular best practice roadway
    development forums, and
  • development of a best practice body of
    knowledge.
  • Challenge mine operators and mine managers if
    they fail to pursue industry best practice
    roadway development practices.

26
ACARP
Australian Coal Association Research Program
  • ROADWAY DEVELOPMENT
  • IMPROVEMENT STRATEGIES
  • Guy Mitchell, BMA
  • Glen Lewis, Xstrata Coal
  • Bob Miller, Centennial Coal

27
BRAINSTORM TIME
  • A quick exercise
  • Your thoughts ideas
  • Your opinions
  • Whats good?
  • Whats bad?

28
WORKSHOP RESPONSES - MACKAY
  • GOOD
  • Clean separation of development from longwall
    equal focus individual business units
  • Involvement of operators and others in all facets
    of the development process and activities
  • Companies using data to identify opportunities
  • Ownership of process and involvement is high at
    high-performing mines
  • Focus on workforce and community
  • Parallel-pathing of activities

29
WORKSHOP RESPONSES - MACKAY
  • BAD
  • Lack of commitment by all stakeholders
  • Right people lack control
  • Industry becoming closed to new inexperienced
    people
  • Operators dont have enough input into
    standardising processes
  • Non-standardisation of processes
  • Coal haulage continued use of shuttle cars
  • Old technology used too long
  • Failure of develop continuous haulage systems
  • Unrealistic budgets
  • Lack of investment in process
  • People not able to be accountable
  • People lack of work ethic
  • Unrealistic expectations of machinery and
    peoples performance
  • Fear of failure development behind budgets -
    reluctance to try new things
  • Fear of prosecution
  • Rosters affect effective communication
  • Lack of knowledge and management focus
  • Shift duration - operators become unproductive
    later in shift

30
WORKSHOP RESPONSES - POKOLBIN
  • SUCCESSES OF LAST 5 YEARS
  • Hydraulic bolters in lieu of hand held bolters
  • Focus on process, and integration of systems
  • Set standards, with all shifts doing the same
    thing
  • Achievements in primary and secondary support
    systems and products (installation systems
    require further RD)
  • Machine monitoring improvements, almost to
    longwall standards
  • Use of fit for purpose materials and equipment
    handling attachments - spent on ancillary
    equipment to improve materials handling and
    logistics systems
  • Attitude of personnel harnessing power of
    people pride in their job maintenance of
    standards
  • Senior management credibility doing what they
    said they would do
  • Involvement of people in process
  • Change in leadership model and supervisors role
    leader rather than lamp holder
  • Age of workforce focus on ergonomics
  • Increased focus on safety and development of
    safety systems approach
  • Services handling systems monorails
  • Increased KW installed in development equipment
  • Radio control of machines success?
    reliability? exposure of people to pinch points?

31
WORKSHOP RESPONSES - PENRITH
  • RD SUCCESSES OF LAST 5 YEARS
  • Geological and geotechnical developments for roof
    support determination
  • Application of monorail systems
  • Development of roof and rib support hardware by
    OEMs and suppliers
  • Technology developments from ACBM project
  • How do we wrap emerging technologies together as
    an integrated, cost effective system?
  • RD ISSUES FROM THE PAST 5 YEARS
  • RD on the run (roof and rib support) lack of
    industry support
  • Reactive application of geotechnical design to
    support systems
  • Failure to adopt other industry supply systems
  • Lack of predictability of geotechnical conditions
  • Pioneering development of equipment
  • Further improvements in monorail systems required
  • ACBM getting OEMs and operators to take it
    forward

32
ACARP - INCREMENTAL CHANGE
  • Demonstrate a high capacity, integrated mining
    system that incorporates then available, best
    practice technology.
  • Pursue and expedite commercialisation of
    alternative self drilling bolt technologies and
    automated bolting systems, including potential
    retrofitting of automated bolting systems to
    existing CMs.
  • Facilitate and expedite completion of the ACBM
    and associated technologies.
  • Develop alternate skin reinforcement and
    confinement measures to eliminate use and
    handling of steel mesh.
  • Facilitate development of an extensible, self
    advancing panel conveyor.
  • Develop a high capacity, automated long tendon
    installation system for both primary and
    secondary support applications.

33
ACARP - INCREMENTAL CHANGE
  • Develop a mine economics modelling system that
    enables mines to properly evaluate the full cost
    of alternate development systems.
  • Pursue other complementary technology
    developments including
  • automation and robotics
  • machine guidance systems
  • light weight materials
  • face pumping systems
  • roadway construction and consolidation
  • gas drainage
  • Improve level of awareness and understanding of
    technologies being applied in other industry
    sectors
  • Metalliferous and tunnelling
  • Coal industry assessment by a technologist

34
ACARP - INCREMENTAL CHANGE
  • Improve level of awareness and understanding of
    roadway development technologies and systems
    being utilised in mines overseas.
  • Desk top review
  • Technology mission if warranted.
  • Develop software that will facilitate and enhance
    the adoption of the systems approach/ process
    control.

35
ACARP - STEP CHANGE
  • (We recognise the problem but cant conceptualise
    the solution)
  • Develop a vision to demonstrate a high capacity,
    integrated mining system by end 2008.
  • Specification capable of sustained, continuous
    production at a level of 10MPOH, gt20 hours day
    (10/20).
  • Develop a strategy for development and
    demonstration of the high capacity, integrated
    mining system.
  • Develop a specification for the high capacity,
    integrated mining system
  • Commission the design of a number of alternative
    systems
  • TBM concept could provide an integrated,
    continuous cutting, bolting and coal clearance
    system at a number of mines.
  • TBM provide good immediate ground support in
    difficult ground conditions.
  • Construction industry approach simultaneous and
    parallel pathing of work activities

36
ACARP - STEP CHANGE
  • Evaluate and select a design that best meets the
    industry specification and requirements, and
  • Commission an OEM (or OEMs) to develop the
    technology and manufacture the integrated system.
  • Establish a collaborative agreement to conduct
    demonstrations at appropriate mine site (eg
    highwall), either
  • by a project team internally funded by the mine
    owner, or
  • by an externally funded mining contractor
    (ACARP).
  • Project manage the technology and equipment
    development process through to the conclusion of
    the field trials and demonstrations through to
    end 2008.

37
WHAT HAS BEEN DONE TO DATE
  • Report accepted by ACARP and key recommendations
    supported including
  • Benchmarking studies on 6 monthly basis
  • Regional Operators Workshops on 6 monthly basis,
    culminating in Operators Conference early 2008
  • Review of civil and tunnelling sectors
  • Alternate skin reinforcement and web-based
    operators network/MIS invited to make second
    round submissions
  • Support for field trials of SDB project
  • High capacity mining systems workshop scheduled
    November 2006 (coupled with L15 project?)
  • Commitment to pursue opportunities identified in
    workshop processes

38
ACARP
Australian Coal Association Research Program
  • KEY FINDINGS JULY 2006 BENCHMARKING STUDY
  • Gary Gibson, ACARP

39
JULY 2006 BENCHMAKING STUDY
  • Contributions received from
  • Mandalong
  • Metropolitan
  • Broadmeadow (BMA)
  • Tahmoor
  • Angus Place
  • Beltana
  • Austar
  • North Goonyella
  • Broadmeadow (HWE)
  • Springvale
  • Appin
  • Glennies Creek and Kestrel reportedly well
    advanced
  • Findings now to be separately reported to
    respondents and workshop participants, with
    close-off of responses 8 September 2006.

40
ACARP
Australian Coal Association Research Program
  • PROCESS CONTROL AND CONTINUOUS IMPROVEMENT
  • David Gibson and Matt Bonnard, Beltana

41
PROCESS CONTROL WORKSHOP - MACKAY
  • How do you involve people in the selection the
    equipment?
  • Form task groups to involve people from
    conception to completion. Benchmark other sites
    and consider all OEMs. Beltana to supply
    guidelines for equipment performance and
    expectations. People that will be using the
    equipment pick the best of what is available and
    engineer in changes to suit our requirements
  • How much time per week you as Development
    Coordinator spending doing work for your process
    and not the rest of the mine?
  • Approx 70 attributable to the process
  • How do you get people to own the process?
  • Firstly, development operates as a business unit,
    and recruits its own personnel, with personnel be
    selected for what they are good at (majority of
    personnel were recruited from South Bulga and
    were each well known for their various strengths
    and capabilities)
  • We feed them with information and shift briefings
    are attended daily by each crew at the start of
    shift
  • We listen to suggestions and act where
    appropriate, and involve them in the selection of
    their equipment
  • We adopt sustainable manning levels
  • Can you outline the incentive scheme?
  • Two major components, 50 each for development
    metres and longwall tonnes
  • We conduct fortnightly audits of panel standards
    including roadway alignment and horizon control,
    safety equipment, etc
  • Safety performance is also factored into
    incentive scheme
  • What are the top 5 delays, and do you have any
    magic wands?
  • No magic wands top 5 delays section advance,
    travelling to section, flitting, stone dusting,
    supplying the miner

42
PROCESS CONTROL WORKSHOP - MACKAY
  • What material handling issues have been
    identified with the new CM?
  • Bolts handled by QDS pod system. Biggest issues
    are handling 1.7m mesh module and vent tubes.
    Mesh is stowed in the rib behind the miner and
    fetched as required, vent tubes are brought in
    when bolting and handled/installed from the miner
    platforms.
  • Are you going to transfer the learnings to the
    new Blakefield mine?
  • Yes, the process will be picked up and taken to
    Blakefield South although there will be a need
    for a much larger work force
  • Face cycle?
  • Approx 3.2 3.5 days including 8 hour
    maintenance shift and 18-20 hours for section
    advance
  • Impact of say 30 increase in support density?
  • Reduce development rate by 0.5MPOH (from 5MPOH)
  • Shift roster?
  • Seven day, four panel roster, 8 week rotation
  • Rotate shifts each 2 weeks, that is, 2 weeks on
    night shift, 2 weeks on afternoon shift, 2 weeks
    on dayshift, two weekends, 1 week off
  • Undermanagers work same roster but the
    development process management team works normal
    5 days
  • Do you intend to utilise dual CM unit at
    Blakefield?
  • Yes. The model has us running two twin miner
    panels at Blakefield
  • Back bye maintenance?
  • We are responsible for everything inbye of our
    portal. Done when we are cutting at the start of
    our cut sequence when there are no parallel tasks
    to do and also during our weekend maintenance
    windows.

43
PROCESS CONTROL WORKSHOP - POKOLBIN
  • You mentioned panel auditing, what auditing do
    you do?
  • Fortnightly audits of panel standards are
    conducted as part of the mines incentive scheme
  • Typically audit alignment and width of roadways
    and compliance with other panel standards
  • Have you sought or do you have an exemption for
    stonedusting?
  • Yes, application currently being evaluated by
    Department
  • What have you found to be the optimum break away
    angle?
  • Have found 70 degrees to be optimum as it doesnt
    add too much additional development over life of
    panel
  • Used to drive belt road and cut out a wedge for
    break away, now cut a 5.5m cut out in the cut
    through as the belt road is advanced. That
    enables CM to get a full head of coal when it
    commences cut through
  • Who starts the panel advance?
  • Whoever holes the cut through, no other fast
    rules, rotating shifts are employed
  • Now considering cutting B heading again while
    belt road is being cleaned up
  • What is the budget this year and how are you
    going against it?
  • Budget 17.446km roadway development for single
    unit
  • 11.18km completed YTD, and we are 186m ahead of
    budget YTD
  • What are the major impediments to further
    improvement?
  • Continued use of shuttle cars, need to utilise
    continuous haulage systems (going overseas next
    week to benchmark their performance)
  • Panel advances are biggest delay, typically 20
    hours to complete and over life of panel that is
    significant given that we are currently
    completing two panel advances per week
  • Face services an issue, but not convinced
    regarding monorail systems at this stage
  • What fundamental changes do you expect as you go
    into deeper areas of mine?

44
PROCESS CONTROL WORKSHOP - PENRITH
  • To get good scores you need equipment
    reliability. How do you achieve it?
  • Firstly, you need good equipment supported by a
    good maintenance program, with 100 compliance
    with that program
  • We use a 4-5 day window between panel change outs
    to give equipment a major work over
  • Utilise two maintenance windows, 2 x 12 hour
    shifts of a weekend and one 8 hour dayshift mid
    week. Major maintenance jobs done on weekends
  • How do you develop crew ownership of the
    development process?
  • Firstly, development operates as a business unit,
    and recruits its own personnel, with personnel be
    selected for what they are good at (majority of
    personnel were recruited from South Bulga and
    were each well known for their various strengths
    and capabilities)
  • We feed them with information and shift briefings
    are attended daily by all crews at start of their
    shift
  • We listen to suggestions and act where
    appropriate, and involve them in the selection of
    their equipment
  • We adopt sustainable manning levels
  • Who tracks the development cycle process time?
  • Crew supervisors report on a prepared shift
    report and are required to log performance in 15
    minute rests
  • Development Maintenance Coordinator uses the
    mines PULSE system to record data
  • Performance is tracked on a daily basis on a
    whiteboard in the crew muster area, weekly
    performance is tracked, reported and trended by
    the planner. Graphs displayed in muster area
    updated weekly.
  • Are crew supervisors deputies, and how do you
    achieve sustainability if in fact they are
    deputies?
  • Yes, crew supervisors are deputies and we
    typically have at least two deputies in a crew,
    sometimes 3. They step-up from operator to Crew
    Supervisor as required
  • The step-up deputies/crew supervisors are paid at
    a rate higher than operators but slightly less
    than the nominated Crew Supervisor
  • You noted that at 170m depth rib support density
    increases. Do you experience a change in
    development rates with increased rib bolting?
  • Yes, we see a de-rating of development rates of
    some 15 with the increase in rib support and
    seam water make
  • The 170m depth of cover is nominal and the change
    in rib support is driven by conditions. We
    commenced increased rib support at 130m depth of
    cover in the current gateroad

45
PROCESS CONTROL WORKSHOP - PENRITH
  • What do the 12 man development crews comprise?
  • Each crew comprises a crew supervisor plus an 11
    man crew, with the crew comprising a maintenance
    supervisor, 2 fitters, 2 electricians and 6
    operators one of which is a step up crew
    supervisor (deputy)
  • You noted that development crews comprised 12
    personnel including the crew maintenance
    supervisor, how many people are used when cutting
    and loading?
  • We typically cut out for 10-12m at a time and
    then bolt the 10-12m increments in one campaign
  • We require that 5 people be on the CM when
    bolting up, and this will include whoever is
    available including SC drivers and trades
    personnel
  • What does the weekend maintenance crew consist
    of?
  • 1 crew supervisor, 1 operator, 2 fitters and 1
    electrician, plus supplementary contractor if
    required
  • What sort of incentive scheme do you have?
  • Two major components, 50 each for development
    metres and longwall tonnes
  • We conduct fortnightly audits of panel standards
    including roadway alignment and horizon control,
    safety equipment, etc
  • Safety performance is also factored into
    incentive scheme
  • Do you have a system for controlling the
    development process?
  • Dont do it down to the minute, but crew
    supervisors report in 15 minute increments on
    report forms which are customised for each shift
    in accordance with work scheduled for shift
  • Debrief crew supervisors and crews at end of each
    shift
  • Do you maintain during belt moves?
  • No, not with the single CM unit. Maintenance is
    completed during the three scheduled maintenance
    windows
  • What rosters do you work?
  • Seven day, four panel roster, 8 week rotation
  • Rotate shifts each 2 weeks, that is, 2 weeks on
    night shift, 2 weeks on afternoon shift, 2 weeks
    on dayshift, two weekends, 1 week off

46
ACARP
Australian Coal Association Research Program
  • ROOF AND RIB SUPPORT PRACTICES AND EQUIPMENT
  • John Vincze, Springvale

47
ROOF RIB SUPPORT WORKSHOP - MACKAY
  • With self drilling bolts is it important to
    pre-tension the bolt?
  • Yes, we believe it is important to tension the
    bolts as we go. At this stage we havent trialled
    any SDB but we will as soon as they are ready.
  • How does galvanising the long tendons
    (spin-bolts) affect the metallurgy of the
    tendon/bolt?
  • Dont know, thats a question for a metallurgist.
    Again we havent used them yet however we are
    considering them for use in the Mains where we
    have a high water content from adjacent old
    workings.
  • What benefit do you get out of the galvanised
    mesh as compared to the standard mesh?
  • Marked difference, they last a fair bit longer.
    It is more expensive and we only use it for
    reconstruction work in a light duty rib support
    role, and it is very easy to handle. Must note
    that we put a fair bit of support into it, with
    bolt spacing at 1 metre in accordance with the
    mines standard support rules. Also the large
    pizza plates give it a fair bit of support and
    provide good coverage over the mesh.
  • With all the primary and secondary roof support
    materials, belt structure and other materials
    being used has there been any increase in manual
    handling injuries?
  • Yes, but we try to minimise it. The PET delivers
    the pods to the panel and they are put onto the
    miner with a pod handler, and the operator only
    has to touch the 7 bolts when he goes to install
    them, and he drags the 8m bolts off the monorail.
  • Trusses installed by contractors and they are
    delivered underground and unrolled on the job.
  • Main injuries at the mine are strains, to the
    back, shoulder and arms, and we do notice that as
    the workforce ages they are more susceptible to
    these injuries.
  • I noticed on one of the photographs that the
    miner appeared to have a slide arrangement to put
    the mesh onto the CM. Can you give us some more
    details of that?
  • Yes, we have a slide arrangement for when we put
    the mesh onto the CM, it minimises the incidence
    of the mesh catching on the CM.

48
ROOF RIB SUPPORT WORKSHOP - MACKAY
  • You mentioned light weight tensioners, can you
    give us more detail?
  • They are lighter than previous ones used, but I
    am not certain how heavy they actually are. It
    certainly is an issue working at 3m height when
    lifting the tensioner overhead. We do get
    injuries, and we dont have a solution yet. We
    would certainly like to hear of one if there are
    any solutions.
  • Do you post grout the 8m spin bolts?
  • Yes, they are post-grouted with a thixotropic
    mixture which is the consistency of toothpaste.
    Also post grout the tendons and trusses but we
    use a strata binder grout for that, with the
    strata binder penetrating the strata as well.
  • What else is suspended off the monorail system?
  • 8m bolts, plastic (grout) tubing, maximum fifteen
    20 litre drums of oil, maximum 20 bags of
    stonedust (20kg each), fitters and electricians
    tool boxes, first aid equipment
  • What is the make up of the production crews and
    what are they responsible for?
  • Similar to what was at Beltana with dual
    continuous miners in gateroads and 6 miners on
    each CM, with 1 fitter, 1 electrician and 1
    deputy in the panel.
  • Deputy manages the crews annual leave roster,
    with one tradesmen and 3 miners allowed off at
    any one time. Sick leave does impact upon numbers
    although we have good support from outbye crew.
  • The three production crews cut coal, do belt
    extension and pipe extensions, with the dayshift
    outbye crew doing roadworks right up to the crib
    room, and doing the transformer moves, and
    transporting belt structure and supplies.
  • 110m belt move is budgeted for 3 shifts,
    averages 17 hours with a best result of 11 hours.
    The belt move includes the belt and 6 air and
    water pipes, with a 4 fire main between the
    travel road and belt road every second pillar

49
ROOF RIB SUPPORT WORKSHOP - POKOLBIN
  • What is the standard panel manning and what are
    the crews responsible for?
  • A deputy, 12 operators, 1 fitter and 1
    electrician
  • Dual CM unit in gateroads
  • Headings at 48m centres, cut throughs at 140m
    centres
  • Crew responsible for supplying panel, roadworks,
    pipework, belt structure
  • Best panel advance 11 hours, budget 3 shifts but
    typically achieve 18 hours
  • 1200mm longwall conveyor installed in development
  • Transformer move every fourth pillar
  • You mentioned you hade problems with Megabolts
    and they were no longer used, can you expand upon
    that?
  • Had problems tensioning Megabolts off the CM,
    very heavy tensioning equipment
  • We found that Megabolts were not flexible enough
    in our operating environment
  • Also found them to be difficult to install and
    post-grout

50
ROOF RIB SUPPORT WORKSHOP - PENRITH
  • Water was reported to be a major issue at
    Springvale, can you outline what you use to
    manage the mines water make?
  • Have a number of Air 2000 pumps, 3.7KW and 37KW
    mono pumps
  • Typically have fish tanks every 3-4 pillars along
    the longwall gateroads
  • Water is pumped out to surface via a series of
    boreholes and in some instances we utilise a FBT
    (frigging big tanks) to transport water from the
    mine
  • We have also drilled a 1.2km long borehole in
    advance of the longwall bleeder roadways to
    pre-drain the installation face area of future
    longwalls
  • It was noted that you are awaiting the
    development of SDB. Hilti now have a self
    drilling bolt available now, why not utilise it ?
  • The Hilti SDB system does allow the bolt to be
    pre-tensioned
  • While Hilti have a SDB roof bolt, we have a
    greater need for a SDB rib bolt
  • What type of rib mesh do you use along the
    longwall block side of gateroads?
  • Steel rib mesh is now used although we were
    previously using Tensar mesh

51
ACARP
Australian Coal Association Research Program
  • DEVELOPMENT AND OPTIMISATION OF CONTINUOUS MINERS
  • (Best Practice Maintenance and Engineering)
  • Alan Bruce, Crinum

52
CONTINUOUS MINER WORKSHOP - MACKAY
  • How much roof and rib support is installed at
    Crinum?
  • In good roof conditions there are 6 x 2100mm roof
    bolts installed per metre, with 2 x 1200mm steel
    rib bolts on the chain pillar side and 3 x
    cutables on the block side. When roof conditions
    deteriorate there are 8 x 2100mm bolts installed
    per metre.
  • Platforms on the ABM25(S), why do they raise and
    lower?
  • Our ergonomist recommended that operators only
    move their head through a 15 degree arc in order
    to minimise pinching of discs in the neck, and
    also required operators to be at a suitable
    height relative to the drills rigs
  • The preferred operating height was above the
    preferred maintenance height, and to lift the
    machine components up 200mm to be above the work
    platform would have increased the overall machine
    height
  • Then decided to install a moveable platform which
    was raised for operation and lowered for
    maintenance, thereby putting the operators at the
    correct height and avoiding increasing the
    machine height
  • Where are the control for raising and lowering
    the platforms?
  • There is another valve bank situated beside the
    rib bolter controls to operate the platforms and
    the mesh handler.
  • How far back from the face are the roof bolts
    installed?
  • The roof bolts will be installed at 2.6m from the
    face.
  • The Joy Sumps Shearer addressed many of the
    ergonomic issues raised in your presentation, is
    there any benefit in revisiting that machine as a
    work platform?
  • The Sumps Shearer is no longer being considered
    for development by Joy, but I definitely believe
    it had potential.
  • What sort of improvement do you expect from the
    new ABM25(S)?
  • The ABM25(S) is expected to give a 12 increase
    in development productivity
  • What other improvement initiatives are being
    considered with introduction of the ABM25(S)?
  • There are three different projects currently
    being undertaken. One is the ventilation-monorail
    system and its interface with the miner, the
    second is the supply cassette system, and the
    handling, carting and loading of supplies onto
    the miner, the third is the electrical
    requirements to run the machine, ie cable sizing
    and handling.

53
CONTINUOUS MINER WORKSHOP - POKOLBIN
  • You stated that the work platform raised and
    lowered some 200mm for maintenance, can you
    explain that some more?
  • Our ergonomist recommended that operators only
    move their head through a 15 degree arc in order
    to minimise pinching of discs in the neck, and
    also required operators to be at a suitable
    height relative to the drills rigs
  • The preferred operating height was above the
    preferred maintenance height, and to lift the
    machine components up 200mm to be above the work
    platform would have increased the overall machine
    height
  • Then decided to install a moveable platform which
    was raised for operation and lowered for
    maintenance, thereby putting the operators at the
    correct height and avoiding increasing the
    machine height
  • What level of productivity improvement is
    expected with the ABM25(s) at Crinum?
  • The ABM25(S) is expected to give a 12 increase
    in development productivity
  • What was the increase in cost for the ABM25(S)
    relative to a new CM?
  • I understand that VA spent some 6-7M to complete
    the development
  • It cost BMA 0.5M more than an off the shelf
    machine
  • Did it surprise you that you had to be so
    proactive with OEMs?
  • I know what OEMs are like, they dont like making
    changes
  • You have highlighted a number of changes to the
    on-board ventilation system. Do you consider that
    the on-board systems are worthwhile as compared
    to a conventional ducting system?
  • Dont know, we have always had the on-board
    system
  • Are any other changes to the roadway development
    system at Crinum being considered?
  • Yes, always working to improve the system
  • Looking at how to make the supply system work
    better, including QDS attachments, etc
  • A participant noted that Crinum had developed and
    fitted a simple device to the MBE that allowed
    belt structure stands to be inserted with minimal
    manual effort

54
CONTINUOUS MINER WORKSHOP - PENRITH
  • How well does the ABM25(S) break away and
    complete cut throughs?
  • Same as the 12CM32, hasnt been identified as an
    issue at this stage
  • With the electronic roof bolting controls is
    there any ability to monitor bolt torque and
    tension?
  • Yes, there is an ability to monitor all CM
    functions and to record data on the surface
  • In regard to the specific drilling energy
    function we monitor and record data for the two
    outside roof bolts
  • Why have you fitted hydraulic traction drives on
    the CM?
  • To create room on the machine, that is two motors
    that are not required
  • Development and fitment of self drilling bolting
    systems are likely to require on board chemical
    injection storage and pumps and the space created
    by fitting the hydraulic traction units will
    allow retrofitting of SDB systems
  • What factors were identified by OEMs when they
    did not submit tenders for development of the new
    Crinum CM?
  • No analysis of why OEMs didnt submit tenders was
    completed
  • Is Crinum a wet or dry pit?
  • Dry now, although it was very wet initially
  • Have you done any comparison of the availability
    of the electronically controlled roof bolting
    rigs?
  • Still working on the comparison although it
    should be noted that we didnt have to send a
    fitter into the panel for the first 6 weeks that
    the bolters were being used (Note Crinum
    standard panel manning does not include trades
    personnel)
  • You seem to have had a fair budget available to
    undertake all the necessary modifications?
  • Small changes were taken at a time, with
    continual improvements being made over time

55
CONTINUOUS MINER WORKSHOP - PENRITH
  • You reported that you have just had your best
    year of development at Crinum, what performance
    rates were achieved, MPOH and metres overall?
  • Typically achieving 3.5 3.75MPOH
  • Dont have an exact overall figure but it was the
    most metres achieved in any one year and we only
    operated the 3 CMs on a part time basis, rather
    than on a full time basis as in previous years
  • Now that you have both upgraded 12CM32s and an
    ABM25(s) available, do you have any preference on
    how they will be deployed to mains and gateroad
    drivage?
  • No preference however should note that we are
    moving to a highwall operation at Crinum East and
    there will be no mains development
  • You noted that you changed from gear pumps to
    Rexroth pumps, were there any other changes
    necessary to accommodate that change?
  • No, nothing different
  • What did it cost for development of the ABM25(S)?
  • BMA committed 300,000 up front to commence the
    development process and I understand that VA
    spent some 6-7M to complete the development
  • The machine as delivered will cost 4.8M
  • What level of productivity improvement is
    expected with the ABM25(s) and what other
    improvements are contemplated in roadway
    development at Crinum?
  • The ABM25(S) is expected to give a 12 increase
    in development productivity
  • Other improvements include introduction of
    monorail mounted ventilation systems and
    improvements to handling and installation of roof
    mesh and support materials

56
ACARP
Australian Coal Association Research Program
  • PANEL ADVANCES
  • Jim Richardson, United

57
PANEL ADVANCES WORKSHOP - MACKAY
  • What improvements to the development services
    time?
  • Panel advance could be sped up by utilisation of
    Development monorail system.
  • Potential to get time down to 4.5 hours.
  • Is there a specific development maintenance
    window, and does maintenance get done during
    development time?
  • Maintenance for the belt road equipment is linked
    to a full shift (usually Thursday ) each week
    when Stop Belt maintenance is carried out.
  • The travel road equipment is carried out when
    services are being advanced after the travel road
    miner has mined to 130m chainage.
  • Why does the mine work a five day roster, why not
    seven day roster?
  • 5 days are enough to maintain longwall
    continuity.
  • Rosters are simple.
  • Management are not burnt out.
  • We are not paying penalty rates.
  • Do you utilise detailed procedures to ensure that
    the belt extension process is consistently
    repeated?
  • We have procedures detailed within the panel
    folder however we tend to achieve repeatability
    by utilising the same people to do the same job
    each time, so there is not a need to constantly
    refer to these procedures.
  • With the introduction of the contractor based
    weekend production crews we have progressively
    involved them in the process to the point that
    this weekend they will complete their first solo
    panel advance.

58
PANEL ADVANCES WORKSHOP - POKOLBIN
  • Can you go through the road clean up and cut
    through holing process?
  • The travel road CM is advanced to 132m to
    complete overdrive before being pulled back to
    clean up travel road from outbye cut through to
    face
  • Following clean up of travel road vent ducting is
    recovered and the extension of services is
    commenced
  • Belt road CM completes 20m overdrive in belt road
    before commencing cut through
  • When belt road CM holes it takes about 2 hours to
    complete bolt up, during which time a loader is
    used to doze up belt road into overdrive
  • Belt road CM then trammed into belt road and an
    LHD cleans up the cut through into belt road
    overdrive, before CM trammed to face and loads
    out stowage at face into shuttle car
  • Does the conduct of the panel advance on day
    shift and out of cycle require specialisation
    of day shift crew?
  • Yes, that is one of the keys to our success, with
    the day shift crew developing their
    specialisation and repeating it each 4 days, with
    the same people doing the same thing each time
  • What type of LTU drives are installed?
  • Eddy current winches which tension the belt to
    7KN
  • What is the name of the day shift supervisor?

59
PANEL ADVANCES WORKSHOP - PENRITH
  • When do surveyors install the grade line and do
    the belt bolt mark-up?
  • On the stop belt shift (typically Thursdays)
    although may have to do it during the panel
    advance if there is no belt stop shift between
    panel advances
  • When are belt hanging bolts installed?
  • On the stop belt shift (typically Thursdays)
    although may have to do it during the panel
    advance if there is no belt stop shift between
    panel advances
  • Why not pre-hang the belt hanging chains rather
    than hang them at the start of the belt move?
  • One fell down hit operator, and there have also
    been reports of then falling down and catching
    equipment
  • Doesnt add too much time
  • We use fully encapsulated 2100mm belt hanging
    bolts which are part of our roadway support
    system
  • Participant reported that they pre-hung the
    chains and marked the grade line on the chains to
    expedite levelling of the conveyor structure
  • How long are the longwall blocks, and do you have
    any problems pulling the belt out of the LTU over
    that distance?
  • 3.2km long
  • Problems are experienced at times due to soft
    floor conditions in inbye section of panel,
    however the utilise a second LHD to assist
  • Do you have any issues involving contractors in
    panel advances given the strong union culture at
    the mine?
  • Union role at mine not an issue, they have a
    position of Board and employees are kept fully
    informed on costs and profitability
  • Employees recognise that contractors are there to
    assist them and to make the mine viable
  • Contractors used on panel advances are drawn from
    other contract works being undertaken at the mine
    at the time (eg secondary support, ventilation)
    and are not specifically employed for panel
    advances

60
PANEL ADVANCES WORKSHOP - PENRITH
  • When do you put the belt into the LTU?
  • On the stop belt shift, approximately 2 hours
    to install
  • How do you doze up the belt road?
  • Use an LHD bucket to push up the floor material
    rather than use it as a conventional loader
    bucket. Then load it out with CM and shuttle cars
  • How do you install the belt structure when
    pulling the boot end back with the LHD?
  • We crowd the boot end back into the bucket and
    that separates the top and bottom belt and allows
    the idlers to be inserted between the belt
  • Do you use the weekends when there is no
    production scheduled to complete preparation
    works for panel advance?
  • Previously we used weekends to catch up on the
    belt hanging bolts, stone dusting and major
    component changes on the equipment, and
    maintenance of the travel road unit
  • Now are working a 7 day week with mine employees
    on a 4X9.5 hour roster 4 days per week, with
    Walters working other 3 days to catch up on a
    development shortfall created by extended
    equipment overhauls, geology and EA negotiations
  • Contractors trained to do belt advances and they
    are completed as they fall
  • being utilised on 3X12
  • What is the pillar cycle time?
  • Typically 4 days in middle 20 pillars of gateroad
    development, extending out to 5 days at start and
    finish of panel due to mining conditions
  • Do you use a second DCB?
  • Yes, use a second DCB to leapfrog belt road DCB
    each pillar, with travel road CM powered directly
    off transformer which is moved every 2 pillars as
    part of panel advance

61
PANEL ADVANCES WORKSHOP - PENRITH
  • Do you have any views regarding roof and floor
    mounted structure?
  • 1200mm belt operates at 5.2m/s and needs to be
    high standard, and we utilise roof mounted
    structure to provide a high standard longwall
    ready conveyor
  • Minimal works are undertaken on completion of
    gateroad development to get conveyor longwall
    ready
  • What improvements could be made to panel advances
    at United?
  • Considering use of monorail services management
    system in both headings to take the extension and
    relocation of panel services off the critical
    path
  • Expect panel advances could then be completed in
    4.5 hours
  • Do you use a breaker feeder?
  • No, we load directly onto a grizzly style boot
    end
  • The overall system is currently in balance and do
    not require a breaker feeder for surge capacity
  • Do you mine any rock at all?
  • Yes, seam thins at inbye end of longwall blocks
    and we take up to 400mm of roof stone
  • Not a problem for conveyor system
  • Which miner completes the cut through?
  • Belt road CM completes the cut through
  • The travel road CM pulls up at 132m after
    completing overdrive and is then pulled back to
    clean up travel road from outbye cut through to
    face (while belt road CM completes hole through),
    before recovering vent ducting and commencing
    extension of services

Write a Comment
User Comments (0)
About PowerShow.com