FAA Update Airports Program - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

FAA Update Airports Program

Description:

Title: PowerPoint Presentation Author: MTONEY Mike N Williams Last modified by: Mary Created Date: 1/28/2005 8:32:53 PM Document presentation format – PowerPoint PPT presentation

Number of Views:212
Avg rating:3.0/5.0
Slides: 24
Provided by: MTONEYMik
Category:

less

Transcript and Presenter's Notes

Title: FAA Update Airports Program


1
FAA Update Airports Program
  • Western-Pacific Region

Association of California Airports
Arlene B. Draper
September 13, 2013
2
FAA Update
  • FY12 Program Highlights
  • AIP Performance Metric
  • Inactive Grants
  • Are You Ready for FY14?
  • Safety Initiatives
  • Geo Balancing

3
FY12 AIP Projects Funded (Western-Pacific
Region)
Total 470M
4
AIP Funding for FY10/11/12
5
AIP Performance Metric
  • By September 30th, grant disbursement rate should
    be as follow
  • FY12 grants - 60
  • FY11 grants - 81
  • FY10 grants - 91
  • FY09 grants - 96
  • FY08 and older grants, close them.

6
OMB Target Balance Vs. Actual Regional Balance
Grant Year FY12 FY11 FY10 FY09
Target for July 43 Grant Balance 20 Grant Balance 10 Grant Balance 4 Grant Balance
AWP 64 Behind by 99M 20 6 Ahead 23M 2 Ahead by 6M
AAL 48 12 10 4
   
ACE 32 14 6 2
   
AEA 40 14 10 1
   
AGL 40 11 5 3
   
ANE 43 13 9 1
   
ANM 30 7 3 1
   
ASO 41 23 8 2
   
ASW 42 20 4 2
Note Data is as of September 10, 2013.
7
Grant Payment Behind Schedule
8
Note Data is as September 10, 2013.
Grants with No Payments
State gt 6 Months gt 9 Months gt 12 Months
Arizona 7 13 15
California 18 32 6
Nevada 3 3 5
Hawaii 1 5 1
Pacific Islands 1 1 0
Total 30 54 27
9
Inactive Grants(No Payments gt 9 Months)
  • FAA needs to explain to DOT reasons for keeping
    inactive grants open.
  • Grant condition requires sponsors to complete
    projects without undue delay.
  • Sponsors with inactive grants will be considered
    as elevated risk. (required additional
    documentation).
  • Grant inactivity is a factor in considering
    future AIP grants with state apportionment and
    discretionary funding.
  • FAA may pursue unilateral closeouts for inactive
    grants.

10
Important Dates for FY14
Events Due Dates
Environmental (FONSI, ROD, or CAT EX) December 2013
Application December 2013
Solicit Bids or Declare Carryover May 1
Grant Offers (approximate) June 15
Grant Execution (approximate) July 15
11
Are You Ready for FY14?
  • By 12/31/13 you have
  • Planning complete
  • Project on an approved ALP
  • FAA environmental complete (FONSI, ROD, or
    submission of extraordinary circumstance form)
  • Airspace review and approval complete
  • Design complete and project ready for bid

12
Airport Environmental
  • Every AIP/PFC funding approval and Airport Layout
    Plan approval requires environmental analysis
    under the National Environmental Policy Act.
  • Action choices include
  • A simple Categorical Exclusion with no further
    action required
  • A Categorical Exclusion that requires a review of
    possible extraordinary circumstances
  • An Environmental Assessment (EA)
  • An Environmental Impact Statement (EIS)
  • We also are the FAA focal point for
  • Title 14, CFR, Part 150, Airport Noise
    Compatibility Planning
  • Title 14, CFR, Part 161, Notice of Approval of
    Airport Noise and Access Restrictions

13
FY14 Environmental Deadline
  • Environmental documents should be completed by
    December 31, 2013
  • Finding of No Significant Impact (FONSI) for
    Environmental Assessment (EA)
  • Record of Decision (ROD) for Environmental Impact
    Statement (EIS)
  • Submission of extraordinary circumstance form to
    support categorical exclusions.

14
Vehicle Pedestrian Deviations
  • We have already exceeded last years rate of
    Vehicle/Pedestrian Runway Incursions. Last year
    we experience a significant reduction. We need
    your increased focus on this as we close FY 13
    and begin FY 14.
  • Recommendations to Airport Operators
  • Train and re-train your staff who drive on the
    airport.
  • Train and re-train your tenants.
  • Make sure your tenants provide proper escorts for
    vehicles and pedestrians they give access.
    (There should be consequences for not doing so.)
  • Conduct outreach/training for local Law
    Enforcement and First Responders (Airports are a
    different environment).
  • Ensure Perimeter Fencing, access controls, and
    cautionary signage are maintained.
  • Change the Gate Code regularly. If you have
    not done so recently, do it NOW!

15
Airport Capital Improvement Plan (ACIP)
  • All proposed ACIP work elements must be reflected
    on an FAA Approved ALP.
  • Your ACIP can include all AIP eligible projects
    for the 1-5 year planning time frame.
  • Your ACIP should be properly sequenced.
  • Expectation for AIP funding should be realistic.
    The ADO will only support justified projects.

16
3 Year Before Construction
  • Scope the project
  • Identify funding sources (AIP/PFC/State/Local)
  • Identify NAVAIDS that might be affected
  • Identify type of environmental review expected
    (CatEX, EA, EIS).
  • Determine if ALP or Exhibit A needs updating
  • Identify if Benefit Cost Analysis is appropriate

17
2 Year Before Construction
  • Select consultant
  • Initiate
  • Environmental review (CatEX, EA)
  • Update ALP, Exhibit A, BCA
  • Refine work scope and cost estimate
  • Coordinate
  • NAVAIDS
  • Instrument Approach Procedure
  • Airspace, Air Traffic

18
1 Year Before Construction
  • Solidify project scope
  • Develop 90 plans and specification
  • Update /revised cost estimates
  • Finalize ALP update environmental review, BCA
  • Review project schedule with FAA
  • Be ready to accept grant the following year
    (based on bids)

19
National ADO Initiatives
  • Geographic Balancing (Geo-balancing)
  • National redistribution of resources to better
    serve our customers
  • New Phoenix ADO to serve AZ and NV
  • Phoenix office will initially report to LAX ADO
  • LAX and SFO ADOs will exclusively serve
    California
  • National SOPs under development to create
    consistency among ADOs

20
Phoenix Field Office
  • Office opened on November 19, 2012
  • Currently operating as Phoenix Field Office
  • Current staff 1) Assistant Manager, 1) Program
    Specialist, 2) Planners, and 2) Engineers, 1)
    Environmental Protection Specialist, 1) Lead
    Engineer
  • Phoenix ADO, when established, will also serve
    Nevada.

21
Summary
  • Talk to us.
  • Talk early.
  • Plan ahead.
  • Stay abreast of current regulation and guidance.
  • Please talk to us before an issue becomes a
    problem!

22
Contact Information
  • Mark McClardy, Division Manager
  • Western-Pacific Region (310) 725-3600
  • Mia Ratcliff, ManagerPlanning and Programming
    Branch (310) 725-3610
  • Brian Armstrong, Manager
  • Safety and Standards Branch (310) 725-3620
  • David Cushing, Manager
  • Los Angeles Airports District Office (310)
    725-3644
  • Mike N Williams, Assistant Manager
  • Phoenix Field Office (602) 379-3021
  • Robin Hunt, Manager
  • San Francisco Airports District Office (650)
    827-7601
  • Ron Simpson, Manager
  • Honolulu Airports District Office (808) 541-1232

23
Questions?
Write a Comment
User Comments (0)
About PowerShow.com