Title: FAA Update Airports Program
1FAA Update Airports Program
Association of California Airports
Arlene B. Draper
September 13, 2013
2FAA Update
- FY12 Program Highlights
- AIP Performance Metric
- Inactive Grants
- Are You Ready for FY14?
- Safety Initiatives
- Geo Balancing
3FY12 AIP Projects Funded (Western-Pacific
Region)
Total 470M
4AIP Funding for FY10/11/12
5AIP Performance Metric
- By September 30th, grant disbursement rate should
be as follow - FY12 grants - 60
- FY11 grants - 81
- FY10 grants - 91
- FY09 grants - 96
- FY08 and older grants, close them.
6OMB Target Balance Vs. Actual Regional Balance
Grant Year FY12 FY11 FY10 FY09
Target for July 43 Grant Balance 20 Grant Balance 10 Grant Balance 4 Grant Balance
AWP 64 Behind by 99M 20 6 Ahead 23M 2 Ahead by 6M
AAL 48 12 10 4
ACE 32 14 6 2
AEA 40 14 10 1
AGL 40 11 5 3
ANE 43 13 9 1
ANM 30 7 3 1
ASO 41 23 8 2
ASW 42 20 4 2
Note Data is as of September 10, 2013.
7Grant Payment Behind Schedule
8Note Data is as September 10, 2013.
Grants with No Payments
State gt 6 Months gt 9 Months gt 12 Months
Arizona 7 13 15
California 18 32 6
Nevada 3 3 5
Hawaii 1 5 1
Pacific Islands 1 1 0
Total 30 54 27
9Inactive Grants(No Payments gt 9 Months)
- FAA needs to explain to DOT reasons for keeping
inactive grants open. - Grant condition requires sponsors to complete
projects without undue delay. - Sponsors with inactive grants will be considered
as elevated risk. (required additional
documentation). - Grant inactivity is a factor in considering
future AIP grants with state apportionment and
discretionary funding. - FAA may pursue unilateral closeouts for inactive
grants.
10Important Dates for FY14
Events Due Dates
Environmental (FONSI, ROD, or CAT EX) December 2013
Application December 2013
Solicit Bids or Declare Carryover May 1
Grant Offers (approximate) June 15
Grant Execution (approximate) July 15
11Are You Ready for FY14?
- By 12/31/13 you have
- Planning complete
- Project on an approved ALP
- FAA environmental complete (FONSI, ROD, or
submission of extraordinary circumstance form) - Airspace review and approval complete
- Design complete and project ready for bid
12Airport Environmental
- Every AIP/PFC funding approval and Airport Layout
Plan approval requires environmental analysis
under the National Environmental Policy Act. - Action choices include
- A simple Categorical Exclusion with no further
action required - A Categorical Exclusion that requires a review of
possible extraordinary circumstances - An Environmental Assessment (EA)
- An Environmental Impact Statement (EIS)
- We also are the FAA focal point for
- Title 14, CFR, Part 150, Airport Noise
Compatibility Planning - Title 14, CFR, Part 161, Notice of Approval of
Airport Noise and Access Restrictions
13FY14 Environmental Deadline
- Environmental documents should be completed by
December 31, 2013 - Finding of No Significant Impact (FONSI) for
Environmental Assessment (EA) - Record of Decision (ROD) for Environmental Impact
Statement (EIS) - Submission of extraordinary circumstance form to
support categorical exclusions.
14Vehicle Pedestrian Deviations
- We have already exceeded last years rate of
Vehicle/Pedestrian Runway Incursions. Last year
we experience a significant reduction. We need
your increased focus on this as we close FY 13
and begin FY 14.
- Recommendations to Airport Operators
- Train and re-train your staff who drive on the
airport. - Train and re-train your tenants.
- Make sure your tenants provide proper escorts for
vehicles and pedestrians they give access.
(There should be consequences for not doing so.) - Conduct outreach/training for local Law
Enforcement and First Responders (Airports are a
different environment). - Ensure Perimeter Fencing, access controls, and
cautionary signage are maintained. - Change the Gate Code regularly. If you have
not done so recently, do it NOW!
15Airport Capital Improvement Plan (ACIP)
- All proposed ACIP work elements must be reflected
on an FAA Approved ALP. - Your ACIP can include all AIP eligible projects
for the 1-5 year planning time frame. - Your ACIP should be properly sequenced.
- Expectation for AIP funding should be realistic.
The ADO will only support justified projects.
163 Year Before Construction
- Scope the project
- Identify funding sources (AIP/PFC/State/Local)
- Identify NAVAIDS that might be affected
- Identify type of environmental review expected
(CatEX, EA, EIS). - Determine if ALP or Exhibit A needs updating
- Identify if Benefit Cost Analysis is appropriate
172 Year Before Construction
- Select consultant
- Initiate
- Environmental review (CatEX, EA)
- Update ALP, Exhibit A, BCA
- Refine work scope and cost estimate
- Coordinate
- NAVAIDS
- Instrument Approach Procedure
- Airspace, Air Traffic
181 Year Before Construction
- Solidify project scope
- Develop 90 plans and specification
- Update /revised cost estimates
- Finalize ALP update environmental review, BCA
- Review project schedule with FAA
- Be ready to accept grant the following year
(based on bids)
19National ADO Initiatives
- Geographic Balancing (Geo-balancing)
- National redistribution of resources to better
serve our customers - New Phoenix ADO to serve AZ and NV
- Phoenix office will initially report to LAX ADO
- LAX and SFO ADOs will exclusively serve
California -
- National SOPs under development to create
consistency among ADOs
20Phoenix Field Office
- Office opened on November 19, 2012
- Currently operating as Phoenix Field Office
- Current staff 1) Assistant Manager, 1) Program
Specialist, 2) Planners, and 2) Engineers, 1)
Environmental Protection Specialist, 1) Lead
Engineer - Phoenix ADO, when established, will also serve
Nevada.
21Summary
- Talk to us.
- Talk early.
- Plan ahead.
- Stay abreast of current regulation and guidance.
- Please talk to us before an issue becomes a
problem!
22Contact Information
- Mark McClardy, Division Manager
- Western-Pacific Region (310) 725-3600
- Mia Ratcliff, ManagerPlanning and Programming
Branch (310) 725-3610 - Brian Armstrong, Manager
- Safety and Standards Branch (310) 725-3620
- David Cushing, Manager
- Los Angeles Airports District Office (310)
725-3644 - Mike N Williams, Assistant Manager
- Phoenix Field Office (602) 379-3021
- Robin Hunt, Manager
- San Francisco Airports District Office (650)
827-7601 - Ron Simpson, Manager
- Honolulu Airports District Office (808) 541-1232
23Questions?