Title: ENERGY AUDIT AT R-INFRA DAHANU THERMAL POWER STATION (250 X 2 MW UNIT)
1 ENERGY AUDIT AT R-INFRA DAHANUTHERMAL POWER
STATION (250 X 2 MW UNIT)
- CENTRAL POWER RESEARCH INSTITUTE, BANGALORE-560080
2MERC CONTRACT TO CPRI
- INVESTIGATION INTO PERFORMANCE OF DTPS R-INF
- PERIOD 2 MONTHS FROM 22.01.2010
- TOR RATING OF THE UNITS
- PERMISSIBLILITY OF MW OVERLOADING OF THE UNIT
ABOVE THE MCR VALUE - DE-RATING/UP-RATING OF THE UNITS
- FACT FINDING OF UNIT CAPACITY HISTORY
- TESTS ON UNITS CONSTRAINTS
3DESIGN CAPACITY/ RATING OF DTPS
- INSTALLED DURING BSES PERIOD 1995
- TAKEN OVER BY R-INFRA IN 2003
- NO MAJOR CHANGE IN HARDWARE SINCE
- IDENTICAL TO OVER 25 250 MW UNITS INSTALLED ALL
OVER INDIA INCLUDING PARLI, PARAS TATA TROMBAY.
- SAME DESIGN REPLICATED IN ALL UNITS. THEY ARE OF
STAND 250 MW DESIGN OF BHEL - PG TEST, INSTALLATION MANUALS, NAME PLATES,
CAPACITY TESTS OF EQUIPMENT AND C I INDICATE
UNITS ARE OF 250 MW CAPACITY.
4Margins provided by OEM
- Continuous peak plant load duty (over and above
the 100 unit MCR rating) is denoted equipment
wise as follows - Boilers BMCR (boiler MCR) rating
- Turbines VWO (valve wide open) rating
- Generators MVA (apparent power) rating
- Generating transformers MVA (apparent power)
rating
5Margins over 250 MW
- DTPS units have operating margins of
- 8 steam flow in the boiler side (BMCR flow)
- 5 power output on the turbine side (VWO flow)
- 16 on the generator side (capability curve)
- 23 on the generator transformer side.
-
- These margins are provided in all 250 BHEL
supplied units including those at Paras Unit 3,
Parli Unit 6 and Tata Trombay Unit 8 as
elaborated in the text. MARGINS CAN BE FULLY USED
CONTINUOUSLY PROVIDED PARAMETERS ARE NOT
EXCEEDED. OEM HAS IMPOSED RESTRICTIONS ONLY ON
OPERATING PARAMETERS OF INDIVIDUAL EQUIPMENT AND
NOT ON MW MARGINS
6BOILER MARGINS
Sl. No. Unit particulars-boiler UNITS NCR BMCR MARGIN Design
1 Dahanu 250 MW Units 1 2 t/h 746.60 805 1.08 CE/BHEL
2 Paras 250 MW Unit 3 t/h 736.20 810 1.10 CE/BHEL
3 Parli 250 MW Unit 6 t/h 738.21 810 1.10 CE/BHEL
4 Tata Trombay Unit 8 t/h 736.20 810 1.10 CE/BHEL
5 Nasik 210 MW Unit 5 t/h 652 700 1.07 CE/BHEL
6 Chandrapur 210 MW Unit 3 t/h 652 700 1.07 CE/BHEL
7 Bhusawal 210 MW Unit 3 t/h 654 700 1.07 CE/BHEL
8 Koradi 210 MW Unit 7 t/h 652 700 1.07 CE/BHEL
9 Khaperkheda 210 MW Unit No 4 t/h 624.23 690 1.11 CE/BHEL
10 Chandrapur 500 MW Unit 7 t/h 1540 1670 1.08 CE/BHEL
INSTALLATIONS at SL. Nos.5-10 are old
7- Plant load (active power or MW) dependent and
plant load independent parameters - Majority of the quality parameters like
temperature, pressure (except for variable
pressure operation), voltage, etc., are designed
by the OEM to be nearly constant and first order
load independent for the load range of 60 UMCR
to through maximum load and changes are only
second order. - However, the quantity parameters like flow,
current, etc. are directly proportional to
active power (MW) or plant load or machine
loading. As energy efficiency increases these
quantities decrease in magnitude for a given
output.
8- OEM DEFINITION OF
- CONTINUOUS PEAK
- LIMITED TIME PEAK PARAMETERS
- Continuous peak parameter purposefully set for
achieving the maximum performance or output from
the machine. - Peak parameters for limited periods time limits
in s /min /h in one excursion as well as total
time in the lifetime of the equipment. Occurs
because of system operational transients or
constraints or faults or system mismatch.
9Sl. No. Particulars at 100 BMCR conditions Units Dahanu 250 MW Paras 250 MW Parli 250 MW Unit 6 Nasik 210 MW Unit 5 Chandrapur 210 MW Unit 3 Bhusawal 210 MW Unit 3 Koradi 210 MW Unit 7 Khaperkheda 210 MW Unit No 4 Chandrapur 500 MW Unit 7
1 Design coal GCV kcal/kg 3700 3400 3400 5000 4445 5100 5000 3500 3500
2 Annual average GCV kcal/kg 3966 3652 3608 3422 3170 3235 3642 3354 3170
3 Total heat to boiler Mcal/h 599.4 611.7 527.34 536 533.4 531.42 527.5 515.55 1215.9
4 Total fuel quantity t/h 162 179.9 155.1 107.2 120 104.2 105.5 147.3 347.4
5 Restriction on BMCR to GCV less No No No Yes No Yes Yes No No
10SIMULATED FROM ACTUAL DATA
11SIMULATED FROM ACTUAL DATA
12SIMULATED FROM ACTUAL DATA
13SIMULATED FROM ACTUAL DATA
14TURBINE MARGINS
Sl. No. Unit particulars-Steam turbine UNITS TMCR VWO MARGIN Design
1 Dahanu 250 MW Units 1 2 MW 250 262.82 1.05 Seimens
2 Paras 250 MW Unit 3 MW 250 264.78 1.06 Seimens
3 Parli 250 MW Unit 6 MW 250 264.78 1.06 Seimens
4 Tata Trombay Unit 8 MW 250 264.78 1.06 Seimens
5 Nasik 210 MW Unit 5 MW 210 213.30 1.02 Russian
6 Chandrapur 210 MW Unit 3 MW 210 215.80 1.03 Russian
7 Bhusawal 210 MW Unit 3 MW 210 215.00 1.02 Russian
8 Koradi 210 MW Unit 7 MW 210 215.80 1.03 Russian
9 Khaperkheda 210 MW Unit No 4 MW 210 221.70 1.06 Seimens
10 Chandrapur 500 MW Unit 7 MW 500 524.40 1.05 Siemens
15TURBINE MARGINS
Sl. No. Unit particulars - Steam turbine UNITS TMCR VWO MARGIN
1 Hitachi MW 210 222.00 1.06
2 Mitsubishi MW 210 222.00 1.06
3 Siemens MW 210 221.70 1.06
4 Russian MW 210 215.60 1.03
16VWO 800 t/h
SIMULATED FROM ACTUAL DATA
17VWO 800 t/h
SIMULATED FROM ACTUAL DATA
18TURBINES
- DTPS has be able to maintain good MW load ability
on the machine within the OEM margins and without
exceeding any OEM parameter limits by - Maintaining high turbine efficiency (turbine heat
rate deviates from design by only 4.4 kcal/kWh) - Strictly maintaining water quality parameters as
per OEM guidelines - Minimizing auxiliary stack, vent and gland
sealing steam requirements in the turbine.
19Sl. No. Unit particulars-Generator MVA rating MW at pf 0.85 MW at pf0.99 MARGIN pf0.85 to 0.99
1 Dahanu 250 MW Units 1 2 294.0 250 291.18 1.16
2 Paras 250 MW Unit 3 294.1 250 291.18 1.16
3 Parli 250 MW Unit 6 294.1 250 291.18 1.16
4 Tata Trombay Unit 8 294.1 250 291.18 1.16
5 Nasik 210 MW Unit 5 247.0 210 244.59 1.16
6 Chandrapur 210 MW Unit 3 247.0 210 244.59 1.16
7 Bhusawal 210 MW Unit 3 247.0 210 244.59 1.16
8 Koradi 210 MW Unit 7 247.0 210 244.59 1.16
9 Khaperkheda 210 MW Unit No 4 247.0 210 244.59 1.16
10 Chandrapur 500 MW Unit 7 588.0 500 582.35 1.16
20TESTS ON UNITS
- Maximum load- 265.5 MW 2292.7kcal/kWh
- 100 UMCR- 252 MW 2299.13 kcal/kWh
- F-GRADE LOAD- 2326.2 kcal/kWh
- MAXIMUM LOAD REACHED WAS 240 MW
- Design 2230.60 kcal/kWh
- Achieved 2293 kcal/kWh
- EVEN AT 268 MW NO PARAMETER HAS EXCEEDED OEM
LIMITS DTPS CONTROL SET POINTS ARE BELOW OEM
LIMITS
21Loadability
- Combining all the margins provided by the OEM,
R-Infra has been able to load the unit to 268 MW
against the design value of 250 MW. - Maintaining this load is not harming the life of
the unit as the DTPS has ensured that all
parameters are kept within OEM limits. - High loadability is made possible by high energy
efficiency or low unit heat rate which enables
the parameters not to exceed their limits. - OEM MANUALS DO NOT SPECIFIC ANY UPPER LIMITS ON
MW LOADING OR MW OVERLOADING ABOVE 100 UMCR
RATING, OEM MANUAL SPECIFIES CONTINUOUS AND
LIMITED TIME LIMITS ON OPERATING PARAMETERS OF B,
T,G,GT, ETC.
22Remaining life
- Units 1 2 have been commissioned in Jan and
March 1995 and have completed 15 years of service
and nearly 1,20,000 operating hours. - Acceleration of life expenditure takes place
due to parameter excursions into the
limited-time-overload-regime for long periods,
due to frequent cyclic loading, due to frequent
transients with high ramping rates. Scrutiny of
operation and parameters indicates that the DTPS
has avoided operation in these life limiting
regimes thereby preserving the longevity of their
assets. The cyclic operations are far lower than
their design values.
23We are here
Remaining Life (h, years)
? lt45 Good
? gt 45 poor
?45 Normal
Real time years
24Remaining life
- Considering a total engineering life of 35
years of service or 3,00,000 operating hours the
physical (actual) life expenditure of both units
is expected to be 40 . Except for generator,
where the life expenditure is 50 (remaining
life 50 or 14 years), the remaining life of
other components matches roughly with the
physical life expenditure. - This indicates that acceleration of life has not
taken place. The low degradation rate coupled
with the high loading on the plant also leads to
the conclusion that the equipment are healthy and
factors in the nature of non-repairable damage
are not present. UNHEALTHY EQUIPMENT CANNOT BE
LOADED AT ALL
25Degradation
- The CPRI test TG HR is showing a degradation
rate of 0.13 /year. The degradation is 2.0 of
the DHR
LOW LEVEL OF DEGRADATION INDICATES THAT THE
EQUIPMENT ARE HEALTHY AND NO NEGATIVE EFFECTS OF
MW LOADING BEYOND 100 UMCR
26Up-rating/de-rating
- The maximum load on Unit 1 was 268.7 MW and
on Unit 2 was 266.0 MW in 2009 in 2010.
Up-rating or de-rating of the unit has been
studied and it is concluded that the unit
capacity is 250 MW and the present maximum plant
loading of 268 MW is sustainable only because of
high boiler, turbine and generator efficiency
and external factors like coal quality being 600
kcal/kg higher and high power factor of 0.99. The
sustainability may not be long lasting. - The PG test by OEM is for 250 MW, these units are
identical to several 250 MW units, grid code 2005
stipulates a margin over the 100 UMCR rating.
Considering these facts it is concluded that the
up-rating of 250 MW to 260 or 265 MW may not be
sustainable in terms of availability as well as
loadability in the future.
27CONCLUSIONS
- SCRUTINY OF RECORDS INDICATES UNIT CAPACITY IS
250 MW IDENTIAL TO OTHER 250 MW UNITS SUPPLIED BY
BHEL. - OEM MARGINS IN BOILER, TURBINE, GENERATOR AND
GENERATOR TR HAVE BEEN FULLY MADE USE OF TO
ACHIEVE LOADABILITY OF 268 MW WELL WITHIN OEM
PARAMTER LIMITS. - OEM MARGINS CAN BE FULLY USED CONTINUOUSLY
PROVIDED PARAMETERS ARE NOT EXCEEDED. OEM HAS
IMPOSED RESTRICTIONS ONLY ON OPERATING PARAMETERS
OF INDIVIDUAL EQUIPMENT AND NOT ON MW MARGINS.
OEM PARAMTERS ARE NOT EXCEEDED BY DTPS. - TESTS INDICATE ANNUAL UHR OF
- 265.5 MW - 2293 kcal/kWh
- 100 UMCR- 252 MW 2299.13 kcal/kWh
- F-GRADE LOAD- 2326.2 kcal/kWh
- MAXIMUM LOAD REACHED WAS 240 MW
- Design 2230.60 kcal/kWh
- Achieved STATION DATA 2293 kcal/kWh
28CONCLUSIONS
- UPRATING OF THE UNIT HAS BEEN STUDIED. SINCE THE
UNIT IS OF 250 MW STANDARD DESIGN OF BHEL, THE
MARGINS ARE BEING UTILIZED BY ENERGY EFFICIENCY
IMPROVEMENTS, HIGHER GCV OF COAL AND HIGH POWER
FACTOR. THESE CIRCUMSTANCES MAY NOT BE
SUSTAINABLE ALL THROUGH THE LIFE OF THE UNIT. - GENERATORS AND GTS ARE QUITE HEALTHY AND NORMAL.
REMAINING LIFE IS ALSO GOOD. NO IMMEDIATE RISK
FOR 16-20 khours AS PER THE RLA REPORTS OF ABB
ERDA. CONSIDERING THE CRITICALITY OF LOAD
HANDLED BY DTPS AND CONSIDERING THAT THERE ARE NO
SPARES WITH OTHER MEMBERS OF MAHARASHTRA GRID FOR
250 MW THESE CAN BE CONSIDERED.
29