Title: PETE 661 Drilling Engineering
1PETE 661Drilling Engineering
2Surge and Swab
- Three Different Forms of Surge and Swab
Pressures - Kick Detection on Trips
- Well Shut-in Procedures when a KICK is
Detected - A Blowout Case History
3Surge and Swab
- Read ADE Ch. 6
- Reference Advanced Well Control Manual, SPE
Textbook, 2003... - Homework 11 - due Nov. 25
- Homework 12 - due Dec. 02
- Project - due Dec 6
4Surge Swab
- The actual mechanics are complicated, but can be
sufficiently described by - Pressure to initiate movement in a thixotropic
mud - Steady-flow viscous drag between moving pipe
and a static borehole, - Dynamic pressures resulting from mud
acceleration or deceleration
5- Annulus Mud Velocity Profile during downward
movement of drillstring resulting in surge
pressure - Function of
- pipe speed
- system geometry
- flow regime
- whether the pipe is open or closed
6Inertial effects of pipe movement
Peak Velocity
Deceleration effects while breaking
Pipe at rest
Swab due to acceleration when P/U off of slips
7Example B-1
- The following conditions apply to a drilling
liner job on a deep well. - Present depth 16,000 ft
- Last casing setting depth 12,100 ft
- Last casing inner diameter 8.835 in
- Liner outer diameter 7.625 in
- Drillpipe outer diameter 5.0 in
- Liner length 4,300
ft - Mud density 15.8
lbm/gal - Average running speed one min. for
-
a 90 ft stand - Maximum acceleration 0.60 ft/s2
12,100
16,000
8Example B-1
- Assume the mud has developed an average gel
strength of 30 lbf/100 ft2 use the following
Fann multispeed viscometer data - q600 65 lbf/100 ft2
- q300 39 lbf/100 ft2
- q200 27 lbf/100 ft2
- q100 17 lbf/100 ft2
- q6 5 lbf/100 ft2
- q3 4 lbf/100 ft2
9Example B-1, solution
- When dealing with tapered string geometries
(liner strings, drilling assemblies, etc.), the
maximum surge or swab pressure is usually
experienced when the bottom of the string reaches
the depth of interest. - So, determine the surge pressure at 12,100 ft for
each of the three effects and calculate the
equivalent density based on the highest value.
10Example B-1
- Equation B-1 yields the pressure required to
break the gel strength -
d1
d2
11Example B-1
- We estimate the maximum string velocity using
Equation B-4 - Vp 1.5 (90/60)
- 2.25 ft/s
- 135 ft/min
12Example B-1
- From Equation B-2, the relative velocity opposite
the liner for Newtonian fluids is
13Example B-1
- The liner-casing clearance expressed as a ratio
is (7.625/8.835) or 0.863. Assuming power law
behavior, Schuhs extrapolated mud clinging
constant is about 0.48. Hence the effective
annular velocity from Equation B-5 is - Væ 394 (0.48)(135) 459 ft/min.
14Turbulent
Laminar
Mud Clinging Constant
Ratio of Pipe Diameter to Hole Diameter
15Example B-1
- To estimate annular friction losses, plot the
Fann viscometer data as shown in Figure B-2 and
the equivalent viscometer speed at 459 ft/min
using -
1666
Viscometer Reading, lbf/100ft2
611
Viscometer Speed, rpm
17Example B-1
- The viscometer shear stress q611 obtained from
Figure B-2 is about 66 lbf/100 ft2. The laminar
flow surge pressure for the liner is - where is the steady-flow surge pressure
and the subscript 1 designates the lowermost
string section.
18Example B-1
- Convert the effective annular velocity into a
flow rate - and determine the turbulent loss
19Example B-1
- The turbulent flow expression yields the highest
pressure loss so 897 psi is considered the
answer. Repeat the procedure for the drillpipe /
casing annulus. - K is 0.43 for the 0.566 diameter ratio so the
effective annular velocity is - Vae 64 (0.43)(135) 122 ft/min.
20Example B-1
- The equivalent viscometer speed is
-
- and q51 is 12.5 lbf/100ft2 from the logarithmic
plot. - Determine the laminar surge pressure across the
drillpipe annulus as -
-
21Example B-1
- Repeating the turbulent flow calculations
- and
22Example B-1
- The surge pressure across the drillpipe is 85 psi
and the total frictional pressure drop for the
tapered string is
23Example B-1
- Finally, equation B-6 yields the pressure
increase due to pipe acceleration.
24Example B-1
- And,
- Of the three effects, the steady-flow condition
is the most significant and the maximum
equivalent density seen at the last casing seat
is
252
Results in Mud lifted from annulus
And evacuation of the drillstring
3
and a drop in DP fluid level and a drop in BHP
4
Tight Clearance
5
1
26Example 5.3
- A trip operation commences at 5,010 ft with
- a 0.45-psi/ft gas sand at 5,000 ft
- a 13-3/8 in. 54.5-lbm/ft surface casing set at
2,000 ft - the hole diameter assumed to be 12.25 in.
27Example 5.3
- The drillstring consists of
- 4-1/2 in., 16.60 lbm/ft Grade E drillpipe and
- 600 ft.(182.9 m) of 7 x 3 in drill collars.
- Excess hole drag is indicated some distance off
bottom and the annulus soon becomes packed off. - Determine the pressure gradient at the gas sand
after pulling one more 90 ft stand of drillpipe
if the mud density is 9.2 lbm/gal
28Example 5.3, solution
- The mud in the space between the drillpipe and
openhole and steel volume are removed from the
hole by pulling one stand. The capacity factor
for a 4.5 x 12.25 inch annulus is 0.12611 bbl/ft.
The voided volume is - V (Cd Ca)
- V 90 (0.00644 0.12611)
- 11.9 bbl
29Example 5.3, solution
- The mud level change in the drillpipe is this
volume divided by the internal capacity factor - ?h 11.9/0.01422 836.8 ft.
- Which leads to the final wellbore pressure
gradient. -
Then what?
( gsand 0.45 psi/ft )
30Kick detection during trips-Example 5.4
- A national 10-P-130 triplex pump has a rated 3.7
gal/stroke output when furnished with 6.0 in.
liners. - How many strokes should this pump take to fill
the hole after pulling 10 stands of 5 in., 19.50
lbm/ft high - strength drillpipe? (Assume 95
volumetric efficiency.)
31Kick detection during trips-Solution
- The displacement factor for the drillpipe is
obtained from table 5.6 and the volume
corresponding to ten 90 stands is determined as - Vd (0.00813)(900) 7.3 bbl.
- Pump stroke counters that come with a PVT rental
package usually have a trip mode setting which
causes the counter to automatically stop the
stroke count when the flowline sensor detects
return flow. From Equation 5.9 the stroke counter
should read - when the hole fills.
32Kick detection during trips
To mud pit
Flowline
Fillup line
Annulus kept full by continuous circulation from
trip tank
Stack
Trip tank
Centrifugal pump
33Kick detection during trips
Wellhead Sonar
Water gun
Receiver Processor
Gas cut mud
Welbore Discontinuity
Hole Bottom
34Hard Shut-In while tripping DP
- Assure first that the choke manifold line is open
to preferred choke choke is in closed
position. - When a kick is verified, position upper tool
joint above the floor and set slips. - Stab and makeup a full-opening safety valve in
open position - Close safety valve.
- Shut the well in, using annular preventer open
remote-actuated valve to the choke manifold.
35Hard Shut-In while tripping DP
- Notify supervisory personnel.
- Install kelly.
- Open safety valve. Read record SIDPP.
- Read record SICP.
- Rotate drillstring through the closed annular
preventer if feasible. - Measure record the pit gain.
36Soft Shut-In while tripping DP
- Assure first that the choke manifold line is open
to preferred choke choke is in open position. - When a kick is verified, position upper tool
joint above the floor and set slips. - Stab and makeup a full-opening safety valve in
open position. - Close safety valve.
- Close the annular preventer open
remote-actuated valve to the choke manifold.
37Soft Shut-In while tripping DP
- Shut well in by closing choke.
- Notify supervisory personnel.
- Install kelly.
- Open safety valve. Read record SIDPP.
- Read record SICP.
- Rotate drillstring through closed annular
preventer if feasible. - Measure record the pit gain.
38Shut-In while tripping DP--more than one stand
in hole
- First assure that the choke manifold line is open
to preferred choke choke is in open position. - When a kick is verified, position upper
connection above the floor and set slips. - Pickup last drillpipe or combination stand make
up into collar. - Run stand into hole, position tool joint set
slips. - Stab makeup a full-opening safety valve in open
position. - Close safety valve.
39Shut-In while tripping DP--more than one stand
in the hole
- Close pipe rams open remote-actuated valve to
choke manifold. - Shut well in by closing the choke.
- Notify supervisory personnel.
- Install kelly.
- Open safety valve. Read record SIDPP.
- Read record SICP.
- Rotate drillstring through closed annular
preventer if feasible. - Measure record pit gain.
40Shut-In tripping DC
41Example 5.5
- Two 9 x 3 in. drill collars left to be pulled
when flow is detected. The bore is shut-in with a
FOSV and the annular preventer is closed. - At what shut-in pressure will the string be
ejected from the hole if friction between the
packing element and collar is 1,000 lbf and the
mud density is 9.4 lbm/gal - Assume the casing pressure gauge is 20 ft below
the closed value.
42Example 5.5, solution
- Problem solution lies in setting equal to
zero in equation 5.11 and solving for
43Example 5.5
- Note the denominator term is equivalent to
cross-sectional area of pipe OD, Ao. Solving for
Ao and the other cross-sectional areas.
44Example 5.5
- The unit weight of the collar section can be
determined by multiplying the steel volume over
one foot by the steel specific weight of 0.2833
lbf/cu in - W1(56.548 sq in)(12 in/ft)(0.2833 lbf/cu in)192
lbf/ft - Assume a 180 ft stand length, substitute terms
and solve for
45Shut-in when out of hole
- Choke line open with blind ram closed--
- When a kick is verified, close the choke.
- Close manifold gate valve immediately upstream
from the closed choke. - Notify supervisory personnel.
- Read record SICP.
- Measure record pit gain.
46Shut-in when out of hole
- Choke line closed with blind ram open (Hard Shut
in) - When a kick is verified, close the blind ram.
- Close manifold gate valve immediately upstream
from the closed choke. - Notify supervisory personnel,
- Read record SICP.
- Measure record pit gain.
47Shut-in when out of hole
- Choke line open with blind ram open or soft
shut-in-- - When a kick is verified, close blind ram.
- Close choke.
- Close manifold gate valve immediately upstream
from the closed choke. - Notify supervisory personnel.
- Read record SICP.
- Measure record pit gain.
48Blowout Case History
49Blowout Case History
- Significant events pertaining to a blowout from a
shallow oil well. - Set 18-5/8 in conductor casing at 415 ft (100 ft
BML). Installed diverter equipment. - Had a good oil show in the samples from 520 ft.
- Lost full returns at 650 ft. Attempts to regain
circulation were futile. Resumed dry drilling
with hole standing full but not circulating. - Topped an oil reservoir at 900 ft continued to
drill to 960 ft. Began trip out of the hole.
50Blowout Case History
- Significant events pertaining to a blowout from a
shallow oil well. -
- Well began to flow at some point in the trip. The
flow was not detected until oil began to impinge
on rotary table. - Poorly maintained FOSV could not be installed. No
backup was available. - Panic ensued causing misuse of diverter. Off-duty
personnel were not alerted. - Crews failed to don breathing equipment in
presence of flowing hydrogen sulfide. - Failed to recognize that rig equipment was
inadequate to control blowout that abandonment
was in order.