Trillo Apparel Company Revised Delivery Plan - PowerPoint PPT Presentation

1 / 8
About This Presentation
Title:

Trillo Apparel Company Revised Delivery Plan

Description:

The fact that the drywall and framing contractors are unable to start full crews on time is something that can be adjusted for in the schedule. – PowerPoint PPT presentation

Number of Views:317
Avg rating:3.0/5.0
Slides: 9
Provided by: Shanno142
Category:

less

Transcript and Presenter's Notes

Title: Trillo Apparel Company Revised Delivery Plan


1
Trillo Apparel Company Revised Delivery Plan
  • Presented by

2
1st issue
  • Building permits are necessary to start working
    on the actual building of the new space.
  • Delay in building permits
  • 2 weeks is now 3 weeks

3
2nd issue
  • Framing
  • Must be completed first before other building
    stages.
  • Contractor is only able to send half of the
    original crew due to delay.
  • Originally 15 days
  • Now 30 days
  • Drywall
  • Must be completed after other building stages are
    completed.
  • Contractor is only able to send half of the
    original crew due to delay.
  • Originally 15 days
  • Now 30 days

4
Option 1
5
Option 2
6
Proposed Solution
  • Option 2 will be utilized.
  • In order to stay at budget, and on time, changes
    will need to be made to when the different
    contractors are to come in to perform their work.

7
Conclusion
8
References
  • Kerzner, H. (2001). Strategic planning for
    project management using a project management
    maturity model. New York John Wiley.
  • Melton, T. (2008). Real project planning
    developing a project delivery strategy.
    Amsterdam Butterworth-Heinemann.