Title: Advanced Power Systems
1Advanced Power Systems
- ECE 0909.402-01, 0909.504-01
- Lecture 5 Electric Industry Today, Distributed
Generation - 21 February 2005
- Dr. Peter Mark Jansson PP PE
- Associate Professor Electrical and Computer
Engineering
2admin announcement
- course website is up.
- Postings Include
- Homework assignments
- Reading assignments
- Lectures
- Syllabus/Schedule (updated weekly)
3New homework
- HW 4 due next Monday
- now posted on web
- 4.1, 4.2, 4.3, 4.4, 4.5, 4.6, 4.7, 4.9, 4.10
4Aims of Todays Lecture
- Part One complete summary of ch. 3 concepts
- Electric industry today (NUGS, IPPs, QFs)
- Regulatory impacts (PUHCA, PURPA, FERC)
- Completion of ch. 4 concepts
- DG with Fossil Fuels
- HHV/LHV concepts
- Thermal and hydro technologies
5Aims of Todays Lecture (cont)
- 10 minute stretch break at 550
- 1st Quiz on Chapters 1-4
6US Industry structure - utilities
- Traditionally given a monopoly franchise
- In exchange, subject to regulation
- State and Federal
- Most are distribution only
- Many remain vertically integrated (G, T D)
- 3200 US electric utilities
- Four types
7US Industry structure - utilities
- Investor Owned (IOU)
- 5, generate gt 2/3 of power
- Federally Owned
- TVA, BPA, US Army Corps, sell power non-profit
- Other Publicly Owned
- Munis, state, 2/3 of this type, lt9
- Coops originally set up by REA
8US Industry structure nonutilities
- Nonutility Generators (NUGs)
- Prior to 1940 20 of power
- By mid-1970s a small fraction
- Late 1980s-1990s as regulators changed rules
- Some utilities had to sell off their assets
- Growth of NUGS in some states was significant
- By 2001 NUGs were delivering over 25
9LM 1
- Of the following sources of electric power
generated in the US, which one group provides
more than half? - A) Munis
- B) State Owned
- C) IOUs
- D) Federally Owned
- E) Cooperatives
10Regulatory impacts (PUHCA, PURPA, EPAct, FERC
Orders 888 2000)
- Public Utility Holding Company Act of 1935
- 1929 16 holding companies controlled 80 of US
utilities - Financial abuses in many large companies
- Stock Market Crash left many in bankruptcy
- PUHCA provided regulation and break-up of large
HCs - Public Utility Regulatory Policies Act of 1978
- 1973 oil crisis led to large rise in utility
retail rates - PURPA set up to encourage energy efficiency and
renewable energy technologies
11Regulatory impacts (PUHCA, PURPA, EPAct, FERC
Orders 888 2000)
- Energy Policy Act of 1992
- Created new entity EWG
- EPAct set up to begin opening up the grid to
allow competitive generators to compete for
customers hopefully to drive down costs and
prices - FERC Orders 888 2000
- 888 (1996) Requires IOUs to publish
nondiscriminatory tariffs that can be applied to
all generators/competitors - 2000 (1999) Calls for the creation of regional
transmission organizations RTOS to control
transmission system operation
12Industry today (NUGS, IPPs, QFs)
- NUG non-utility generator
- IPP non-PURPA-regulated NUGs
- QF meet PURPA requirements for efficiency or
renewable energy use (lt80 MWs in size at least
75 wind, solar, geothermal, hydro or MSW) max
50 utility owned
13California Meltdown
- Open market on wholesale in March 98
- First 2 years good prices (35/MWh)
- 40 of Californias generation sold
- August 2000 - 170/MWh (800/MWh)
- In 2000 customers paid 5x 1999 prices
- Due to low imports of hydro and adjacent power
- Market manipulation by Enron and 30 others
14Californias end of open markets
- Wholesale market stays high into 2001
- January 01 rolling blackouts (1500/MWh)
- By Feb customers had paid more than 99
- By May PGE declares bankruptcy
- CalPX market shutdown
- FERC intervenes with price caps (Sum 01)
15August 2003 Blackout
- MISO in charge of Ohio transmission system was a
key player in failure to control isolated
reactive power problem and loss of major
transmission service in Northern Ohio. - gt50 million people were out of service for
extended period while the grid was restarted - Largest widespread blackout in US history
- Nationally there is a major rethink of
deregulation
16LM 2
- Connect each event with its year
- A) Largest US Blackout 1978
- B) PURPA 2001
- C) California Meltdown 2003
- D) FERC Order 888 1992
- E) Public Utility Holding Co Act 1999
- F) FERC Order 2000 1996
- G) Energy Policy Act 1935
17Distributed Generation
- Economies of Scale Begin a Reversal
18Typical Power Generator Output
- Large Hydropower Installation 10 GW
- Nuclear 1,100 MW
- Coal 600 MW
- CC Gas Turbine 250 MW
- Simple Cycle CT 60 - 150 MW
- Molten Carbonate Fuel Cell - 4,000 kW
- Wind Turbines 10 1500 kW
- Fuel Cell (automotive) 60 kW
- Microturbine 30 kW
- Residential PEM Fuel Cell 5 kW
- Residential PV System 3-5 kW
19Typical End Use Consumption
- Laptop Personal Computer 20 Watts
- Desktop Personal Computer 100 Watts
- Residential Household (ave.) 1-2 kW
- Commercial Customer (ave.) 10 kW
- Supermarket 100 kW
- Office Building 500 1,000 kW
- Large Factory 1 MW
- Peak Use of Largest Buildings 100 MW
20What is Distributed Generation?
- Small-scale power generation
- Typically less than 50 MW
- Located in the distribution system of a utility
- Often customer (not utility) owned
- May include use of waste heat
21Cogeneration and CHP
- Capturing and using waste heat while generating
electricity - CHP combined heat and power
22HHV and LHV
- Often during combustion of a fuel, latent heat is
generated. If we include the latent heat in our
calculations (i.e., if our furnace or system is
able to capture that heat and make it useful) we
want to use the higher heating value of our fuel. - HHV high(er) heating value, gross heat of
combustion - LHV low(er) heating value, net heat of combustion
23HHV and LHV tables
- GAS HHV LHV (in Btu/lb) RATIO
- Methane 23,875 21,495 90
- Propane 21,669 19,937 92
- Natural Gas 22,500 20,273 90
- Gasoline 19,637 18,434 94
- No. 4 oil 18,890 17,804 94
24Power plant efficiency
- ? output power / input fuel energy
- Large Centralized power stations
- ? is typically based upon HHV of fuel
- Distributed Generation power stations
- ? is often based upon LHV of fuel
- To convert
25LHV / HHV example
- A small micro-power plant has a fuel input of
12,500 Btu (LHV) per kWh of electricity it
generates. Find its LHV and HHV efficiencies if
we assume it runs on gasoline - Gasoline LHV/HHV 0.9378
- Efficiency 3412 Btu/kWh / Heat Rate
- ? LHV 3412 / 12,500 27.3
- ? HHV ? LHV x LHV/HHV 27.3 x 0.9378
25.6
26LM 3 - You try it
- A micro-power plant has a fuel input of 14,500
Btu (HHV) per kWh of electricity it generates.
Find its LHV and HHV efficiencies if we assume it
runs on methane - Methane LHV/HHV 0.9003
- Efficiency 3412 Btu/kWh / Heat Rate
27Microturbines
- Very small gas turbines (NG or waste gas)
- Typically 500 W to 300 kW
- Typical Microturbine Components
- Compressor
- Turbine
- P-M generator
- Combustion chamber
- Heat exchanger (recuperator)
Often all on one shaft
28Leading Manufacturers
- Capstone Turbine Corporation
- One moving part common shaft 96,000 rpm
- C30 - 30 kW unit
- ? LHV 26, Heat Rate 13,100 Btu/kWh
- C60 - 60 kW unit
- ? LHV 28, Heat Rate 12,200 Btu/kWh
- Elliot Microturbines
- TA100R - 105 kW unit
- ? LHV 29, Heat Rate 11,770 Btu/kWh
- 172 kW thermal potential for hot water ? TTE gt
75
29Elliot Microturbine Application
- The Elliot TA 100A produces its full output of
105 kW when burning 1.24 x 106 Btu/hr of natural
gas. Its waste heat is used to supplement an
existing boiler by raising its temperature from
120 -140 oF. It operates for 8000 hours/year. - A) If 47 of the fuel is transferred to boiler
what should flow rate be? - B) If boiler is 75 efficient and NG is 6 per
MMBtu how much money will microturbine save in
displaced fuel? - C) If electric costs 8 / kWh what is annual
savings? - D) If OM is 1,500 per year what are net
savings? - E) If microturbine costs 220,000 what is Initial
RR and SPB?
30LM 4
- A) If we can not use the waste heat is it
economical to install a microturbine in this
application? - (assume you require lt 10 yr Simple Payback)
- B) What if your electric costs are 11 / kWh?
- C) What is lowest price electricity can be to
still meet your 10 yr simple payback requirement?
31Reciprocating IC Engines
- Very small piston-driven, 4 stroke ICEs
- Typically 500 W to 6,500 kW
- Typical Operation
- Intake, Compression, Power, Exhaust
- Spark ignited (Otto cycle)
- Compression ignition (Diesel cycle)
- Multi-fuel gasoline, natural gas, kerosene,
propane, fuel oil, alcohol, waste gas
32Advanced Reciprocating Engines
- Current design is cheapest of all DGs
- Efficiencies are good
- Today electrical ? 37-40
- Turbocharged Thermal fuel ? horsepower
- Otto cycle ? LHV 41, ? HHV 38
- Diesel cycle ? LHV 46, ? HHV 44
- ARES Targets ? ELECTRIC 50, ? CHP 80
- HRSG can increase overall ? CHP 85
33Stirling Engines
- Energy is supplied from outside the system
- External combustion, can run on any heat source
- Invented in Scotland and patented in 1816
- Used quite extensively until early 1900s
- Eliminated from market by efficient technologies
- Current efficiencies relatively low lt 30
- Size ranges from 1 25 kW
- No explosions, relatively quiet devices
- Good match with solar dishes
- Four states of Transition in Stirling Cycle
34New homework
- HW 4 due next Monday
- now posted on web
- 4.1, 4.2, 4.3, 4.4, 4.5, 4.6, 4.7, 4.9, 4.10