Kansai International Airport (Phase-I) Foundation Case Study - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Kansai International Airport (Phase-I) Foundation Case Study

Description:

CE 5333-Foundation Engineering. Spring 2005. Overview. Kansai International ... The ASCE named KIA the #2 civil engineering project of the 20th century, second ... – PowerPoint PPT presentation

Number of Views:2196
Avg rating:3.0/5.0
Slides: 24
Provided by: rajulte
Category:

less

Transcript and Presenter's Notes

Title: Kansai International Airport (Phase-I) Foundation Case Study


1
Kansai International Airport (Phase-I) Foundation
Case Study
  • By
  • Rajul Teredesai
  • CE 5333-Foundation Engineering
  • Spring 2005

2
Overview
Kansai International Airport (KIA)
3
Key Features
  • Located on a biggest man-made island in Osaka
    Bay, Japan
  • Constructed cost over 14 billion
  • The island of 4 X 1 km, constructed in around 18m
    of water, entirely from landfill
  • Project Started in 1986
  • Opened for flights in 1996
  • The ASCE named KIA the 2 civil engineering
    project of the 20th century, second only to the
    Panama Canal

4
Kansai Airport Aerial View
5
Construction of Airport
Stage Activity Time
I Subsurface Investigation 1 year
II Sea Wall Construction 2 years
III Landfilling 4 years
IV Terminal Construction 2 years
6
Bore Hole Locations
7
Subsurface of the Kansai Airport Foundation
8
Seawall Construction
  • Up to 40 ft. above sea level
  • Tripod blocks on seaward side for dissipation of
    wave energy

9
Seawall After Completion
Seawall Construction
10
Mechanism of Sand Drains
11
Advantage of Sand Drains
  • The weight of the piled sand forces the water in
    the clay to move outward along the sand piles.

12
Application of One Million Sand Drain at KIA
13
Reclamation
  • Three distinct grades of sand, gravel and rock
    from nearby mountains
  • Four years and 750 million cubic feet of fill
  • Transportation on
  • Ground Conveyor
  • Water Barges

14
KIA Terminal Building
  • Architect Renzo Piano

15
Settlement Predictions
  • Lack of experience with construction on deep
    deposit of diluvial clay
  • Expected settlement 19 to 25 ft
  • Actual settlement 27 ft (by the end of island
    construction in 1990)
  • It continued at the rate of 2 in/month

16
Settlement Calculations
  • Consolidation Settlement
  • Time Rate of Consolidation (Terzaghi 1925)

17
What Went Wrong in Predictions?
  • Un-conservative estimation of consolidation
    settlement
  • Wrong estimate of the time required for
    completion of consolidation settlement
  • Ineffectiveness of the sand drains in achieving
    the required success 100

18
Incomplete Consolidation
19
Underestimation of Excess Pore Water Pressure
Airport Started
Settlement Continued
20
Coping With The Problem of Continued Settlement
  • Basement of the terminal was lined with a quarter
    of a million tons of iron ore.
  • Result Island sank faster than the building it
    is trying to hold
  • Installation of hydraulic jacks under the colums
  • Result No differential settlement between the
    columns of entire building

21
Learning From Mistakes
  • Using data actual settlement data obtained from
    1st phase of project
  • Analysis of 400-m-deep boring exploration
  • State-of-the-art soil test methods
  • Expected Settlement 18 m
  • http//www.kald.co.jp/eindexframe.html

22
References
  • A report by Justin Phalen, UC-Davis, 2002
  • The official website of KIA http//www.kald.co.jp/
    eindexframe.html

23
Questions?
Write a Comment
User Comments (0)
About PowerShow.com