  • TELECOMMUNICATIONS PROJECTS

2
Over the past years, Nour Communications has
entered into various contracts in major
telecommunications projects with well-known
industry players such as Lucent Technologies,
Ericsson, Motorola, Nokia, Harris Farinon, and
the Saudi Telecommunications Company
(STC). The general overview of the scopes of
work of these contracts and their brief
descriptions are presented hereon. This
manifestation fortifies NOUR Communications
position as an experienced and dependable
contracting company in telecommunications
industry for both commercial and government
endeavors. This string of projects is brought
about by the cohesive teamwork of Nours
innovative management and skilled work force as
its most important resources.
3
  • COMPANIES THAT ENGAGED AND CONTRACTED
  • NOUR IN VARIOUS TELECOMMUNICATIONS
  • PROJECTS IN SAUDI ARABIA
  • Company Project
  • Lucent Technologies TEP 6 Project
  • L.M. Ericsson GSM E4, E5 and E6 Projects
  • NOKIA GSM E5 and E6 Projects
  • Saudi Telecom (STC) GSM E5 and CI Projects
  • Motorola PSD Project
  • Harris Farinon GID and PSD Projects

4
  • SOPHISTICATED TEST EQUIPMENTS
  • Nour Communications has always utilized the
    state-of-the-art tools and test equipments to
    ensure optimum system performance. From survey to
    integration, the wide range of equipments assists
    in improvement of work quality
  • Differential GPS Unit with accuracy of 3m
    horizontally and less than 1m vertically in
    resolution of coordinates and elevation.
  • SDH Analyzer Set for STM-1 systems.
  • c) 2 Mb/s BER Tester for E1 and T1 interface
    stability and performance assessment.

5
  • SOPHISTICATED TEST EQUIPMENTS continued
  • d) TEMS Pocket for GSM Base Station testing and
    detection of cross feeders.
  • e) Site Master for locating fault in feeders
    and VSWR testing.
  • MW Test Set (MTS) for checking of MW O/P power,
    received signal level and frequency measurement.
  • IFR for FM and VHF / UHF systems testing.
  • h) Set of Spectrum Analyzers and Oscilloscopes as
    well as set of tools enough for use of 20
    qualified installation teams for rapid deployment
    around the Kingdom.

6
  • A) Lucent Technologies International, Inc. / ATT
    Intl.
  • TEP6 Project From June 1996 to September 2000.
    Project managed by Lucent Technologies
    Norconsult was project consultant. Contracts
    for
  • 1. SITE SURVEY
  • Nour was the only survey contractor of Lucent on
    its Kingdom wide GSM 200K, 300K and 500K
    projects.
  • Total Number of Surveyed Sites in TEP6 1, 183
    Sites
  • Provided with Microwave line of sight (LOS) data
    between prospective GSM locations recorded any
    path obstructions and measured site elevation
    (AMSL) using Altimeter and Differential GPS.

7
  • Lucent Technologies continued (TEP6 Site Survey)
  • Ensured that site location was suitable, both
    demographic and geographic, for effective GSM
    propagation and coverage.
  • Using state-of-the-art GPS set, recorded the site
    geographical coordinates. Special software and
    compass to get site magnetic bearings and other
    required path data.
  • Using the Spectrum Analyzer set, ensured there
    was no possible interference or signal
    propagation to affect the designated GSM and MW
    frequency bands.
  • GSM survey was based on the mobile coverage RF
    and MW objectives taking up to 3 candidate
    locations per site.

8
  • Lucent Technologies continued (TEP6)
  • 2. SKILLED MANPOWER SUPPLY
  • Supplied Lucent with 21 Teams of Transmission
    Engineers for Testing Commissioning of GSM
    transmission network using different PDH and SDH
    equipment such as ATT Pcom, Harris MicroStar,
    and NERA STM 1 microwave radio sets.
  • Supplied Lucent with 33 Teams of Antenna
    Installers / Riggers, under Lucents disposal and
    direct supervision, to install GSM antennas and
    MW dishes of different sizes, including varied
    sizes of feeders, transmission cables, wave
    guides, jumpers, clamps, and related antenna
    accessories.

9
  • Lucent Technologies continued (TEP6)
  • 3. JUNCTION NETWORK
  • Transmission Contract (April 1998 Nov. 2000).
    Direct contract with Lucent Technologies.
  • Completed Sites 146 Sites
  • The Contract called for implementation of
  • Site survey of 146 MW sites Line-of-site (LOS)
    survey of
  • 64 MW hops.
  • Complete design and optimization of MW hops
    documentation of design and Method of Procedures
    (MOP) prior to site installation.

10
  • Lucent Technologies continued (TEP6 Junction
    Network)
  • Indoor installation on 146 sites using NERA SDH
    STM1 MW Radio with Frequency Diversity 16 hops
    with Space Diversity.
  • Outdoor Installation on 146 sites different
    sizes of cross-polarized MW dishes and wave
    guides.
  • Hop alignment, equipment testing and
    commissioning prior to site integration into the
    long-haul MW network.

11
  • B) L.M. Ericsson
  • GSM E4 From March 2000 to December 2001.
    Direct contract to Ericsson project managed by
    Ericsson project consultant was Norconsult.
    Contracts for implementation of
  • 1. SITE SURVEY / RADIO SITE INVESTIGATION
  • Total Number of Surveyed Sites 755 Sites
  • Site Search/Acquisition Survey. Survey of up to
    3 candidate locations of a prospective new GSM
    Cell Site giving emphasis on RF and LOS
    considerations.
  • Change-out Site Survey. To determine the
    required transmission installation and Civil
    Works for a change out of GSM radio equipment,
    according to on-site Ericsson instructions,
    prioritizing the re-use of existing equipment for
    transmission, DC power and battery back up.

12
  • L.M. Ericsson continued (GSM E4 Site Survey)
  • Radio Site Investigation.
  • Documentation of both existing and planned radio
    facilities based on RSI checklist, floor plan,
    cable tray, and site lay out drawings, and
    detailed photographs of site and equipments.
  • Transmission Survey.
  • Comprehensive transmission equipment survey
    conducted on MSC and existing Microwave Sites
    that were serving as Node Sites in the GSM mobile
    communications network.

13
  • L.M. Ericsson continued (GSM E4)
  • 2. RADIO INSTALLATION RBS and Transmission.
  • Total Number of Completed Sites 241 Sites
  • Contract entailed the following scope of work
  • Change out of Lucent BTS 2000 equipment with
    Ericsson RBS 2202 cabinets with TRX radio units
    and associated elements.
  • Replacements and cut over of GSM antennas to
    effectively provide cellular communications in
    the 900 and 1800 MHz bands.
  • Replacements of LDF series feeders, jumpers,
    cable clamps, and other related antenna
    accessories.

14
  • L.M. Ericsson continued (GSM E4 Radio
    Installation)
  • Installation of Transmission Microwave Equipment
    cabinet including cablings.
  • Installation of Mini-Link TMR 9202 both indoor
    and outdoor units.
  • Installation of microwave antenna dish and
    coaxial cable RG-8.
  • Alignment of MW hop and 24-hour BER burn test to
    ensure optimum signal gain.
  • Installation of batteries and rectifier units
    (Battery Back Up).
  • Cable connections and terminations both outside
    and inside shelter.

15
  • L.M. Ericsson continued (GSM E4)
  • 3. SITE CIVIL WORK CONSTRUCTION.
  • Total Number of Completed Sites 243 Sites
  • MSC / Indoor Room Site survey for civil
    engineering site design construction and
    installation of raised floor system, FM200 gas
    flooding system, coded security access system,
    cable tray system, other civil, electrical and
    mechanical works including HVAC fire alarm and
    detection control, and lighting fixtures
    structural steel materials and electrical
    conduits.
  • New Green Field Site Surveys for site
    acquisition and civil engineering complete site
    design excavation backfill supply and
    installation of equipment and generator shelters
    self-support steel tower erection and painting
    supply and install gantry between tower and
    shelter chain link fence ship and install power
    generator other civil, electrical and mechanical
    works like HVAC, lightings, etc.

16
  • L.M. Ericsson continued (GSM E4 Civil Work )
  • New Roof Top Site Site survey for civil
    engineering site design civil construction and
    installation of equipment shelter (3m x 3m) with
    foundation, cable tray system, antenna support,
    structural steel works including mast, electrical
    circuits and lighting fixtures and site cleaning
    and preparation.
  • Change Out / TRU Expansion Site Detailed site
    surveys site design existing building analysis
    dismantling of Lucent BTS equipment installation
    of new antenna mounts, shelter erection with
    foundation and other civil and electromechanical
    requirements.

17
  • L.M. Ericsson
  • GSM E5 From August 2001 up to present.
    Direct contract to STC Project supervised by
    Ericsson project consultant is Norconsult
    Telematics. Contracts for implementation of
  • 1. SITE SURVEY
  • Total Number of Surveyed GSME5 Sites 530 Sites
  • Site Search/Acquisition Survey. Survey of up to
    3 candidate locations of a prospective new GSM
    Cell Site giving emphasis on RF and LOS
    considerations.

18
  • L.M. Ericsson continued ( GSM E5 Survey)
  • Change-out Site Survey.
  • To determine the required transmission
    installation and Civil Works for a change out of
    GSM radio equipment, according to on-site
    Ericsson instructions, prioritizing the re-use of
    existing equipment for transmission, DC power and
    battery back up.
  • Site Survey for Civil Engineering.
  • Detailed survey of existing sites for equipment
    upgrade building or tower analysis (comparative
    study) for loading capacity survey includes
    electromechanical considerations of increased
    load capacity due to planned additional equipment.

19
  • L.M. Ericsson continued (GSM E5)
  • 2. SITE CIVIL WORK CONSTRUCTION.
  • Total Number of Completed Sites 286 Sites
  • MSC / Indoor Room Site survey for civil
    engineering civil design FDED preparation
    construction and installation of raised floor
    system, FM200 gas flooding system, coded security
    access system, cable tray trunk system, other
    civil, electrical and mechanical works including
    HVAC fire alarm and detection control, and
    lighting fixtures structural steel materials and
    electrical conduits.
  • New Green Field Site Surveys for site
    acquisition and civil engineering civil design
    FDED preparation excavation backfill supply
    and installation of equipment and generator
    shelters self-support steel tower erection and
    painting supply and install gantry between tower
    and shelter chain link fence install power
    generator other civil, and electromechanical
    works like HVAC, lightings, etc.

20
  • L.M. Ericsson continued (GSM E5 Civil Work )
  • New Roof Top Site Site survey for civil
    engineering civil design FDED preparation civil
    construction and installation of equipment
    shelter (3m x 3m) with foundation, cable tray
    system, antenna support, structural steel works
    including mast, electrical circuits and lighting
    fixtures and site cleaning and preparation.
  • Change Out / TRU Expansion Site Site survey for
    civil engineering civil design FDED preparation
    existing building analysis dismantling of Lucent
    BTS equipment installation of new antenna mounts
    and cable ladder, shelter erection with
    foundation and other civil and electromechanical
    requirements.

21
  • L.M. Ericsson continued (GSM E5)
  • 3. SUPPLY OF COMPLETE EQUIPMENT SHELTER.
  • Total Number of Shelters Delivered 187
    Shelters
  • Inside shelter installation of required
    equipments and accessories meeting the approved
    standards set by STC for GSM environment.
  • Completed shelters are being shipped from Nour
    Warehouse to the assigned GSM Cell Site.
  • Inside shelter installation includes the
    following
  • HVAC units, MDB panel, Halon / Fire Alarm Panel
    set, Security Access Control Panel set, battery
    rack and rectifier units, Tower Obstruction Light
    Control (TOLCO), cable and trunk ladder, door
    closer, required cablings, and inside / outside
    lighting fixtures.

22
  • L.M. Ericsson continued (GSM E5)
  • 4. SUPPLY OF CONTAINERIZED DUAL DIESEL
  • GENERATOR
  • Total Number of GSM Sites Installed with D.
    Generators 89 Sites
  • Nour is the sole agent in Saudi Arabia of
    Germanys SAB containerized dual generator. To
    date, 100 sets have been sold and 89 sets
    installed on GSM Sites not serviced by commercial
    power. Deutz is engine make of the 3-phase,
    32.5KVA, 26 KW generator.
  • As STC approved power generator for GSM sites, it
    is installed together with accessories within a
    30-foot box container providing a noise level of
    65dB at 10 meter distance.
  • Accessories provided with the generators control
    panel, starter batteries, FM200 fire
    extinguishing system, 220V and 24VDC lights,
    ventilation, fuel day tank and buried fuel bulk
    tank.

23
  • C) NOKIA
  • GSM E5 Project From September 2001 up to
    present. Direct contract to Nokia project
    managed by Nokia project consultant is
    Norconsult Telematics. Contract for
    implementation of
  • GSM AND TRANSMISSION RADIO INSTALLATION
  • Total Number of Completed GSME5 Sites 204
    Sites
  • Implementation planning based on site specific
    and network configurations radio site
    investigation survey.
  • Change out of Lucent BTS equipment with new Nokia
    Macro UltraSite or Micro MetroSite GSM 900/1800
    MHz radio including antennas, feeders and
    jumpers and battery back up unit.

24
  • NOKIA continued (GSME5 Radio Installation)
  • Installation, testing and commissioning of
    transmission radio Nokia FlexiHopper or
    MetroHopper, and associated MW antenna.
  • Testing, commissioning and integration of all
    installed equipments.
  • GSM E6 Project Project has just started
    January 2003 calling for approximately 130 sites
    allocated to Nour for complete radio
    installation.
  • Contract entails the same scope of work as that
    of GSME5 Project.

25
  • D) Saudi Telecommunications Company (STC)
  • GSM RV / CI Project (Ph I Ph II) From
    July 2001 up to present. Direct contract to STC
    Norconsult Telematics is project consultant.
  • SITE CONSTRUCTION (Civil Work and Telecom)
  • Total Number of Completed CI GSM Sites 73
    Sites
  • Contract is for Nour to construct and deliver to
    STC brand new GSM Cell sites, located along roads
    and villages in the Western Region, on a turn-key
    basis. Complete site construction requires both
    telecom and civil works scope of work as briefly
    described below
  • Civil Work Implementation
  • Site acquisition survey of up to 3 candidates per
    site
  • Civil engineering survey and site design (FDED)
    documentation.

26
  • Saudi Telecom (STC) continued (CI Project)
  • Site acquisition survey of up to 3 candidates per
    site.
  • Civil engineering survey and site design (FDED)
    documentation.
  • Site preparation, excavation and backfill,
    foundation preparation.
  • Erection of steel tower and equipment shelter.
  • Supply, delivery and installation of Dual
    Generators and fuel tanks.
  • Complete civil and electromechanical works such
    as gantry and cable tray system, antenna mounts,
    HVAC system, cable trenches, chain link fence,
    lighting fixtures, tower painting, concreting,
    and other works.

27
  • Saudi Telecom (STC) continued (CI Project)
  • Telecommunications Implementation
  • Complete BTS 2000 equipment installation
    including RF accessories like TRX radio units,
    DDF, GSM 900 MHz antennas and feeders, internal
    and external cablings reconditioning of indoor
    BTS units.
  • Installation of MW transmission equipment using
    Harris MicroStar M7 or ATT Pcom radio units
    installation of MW antenna dishes up to 2.4m
    diameter and IF cable RG-8 hop alignment and BER
    burn test to ensure link stability.
  • Installation of battery back up DC supply,
    batteries and rectifier units.
  • Testing and commissioning of all installed
    equipments.
  • Power up and Integration of site into the GSM
    network.

28
  • E) Motorola / NASCO
  • Public Security Directorate (PSD) Transmission
    Project
  • From October 1998 to December 1999. Direct
    contract with Motorola and NASCO.
  • Total Number of Completed Sites 21 Sites
  • Contract called for Installation of transmission
    equipment on
  • 21 PSD Sites located in Makkah, Jeddah and Taif.
  • MW radio used was Alcatel PDH T1 American
    Standard
  • Installation of PSD Monitoring System.
  • Transmission documentation of the 21 completed
    sites.

29
  • F) Harris Farinon
  • GID Transmission Project
  • Direct contract with Harris Farinon for
    implementation of
  • Transmission network installation using SDH 4T1
    QuadraLink MW radio in the Western Region
  • Installation of Omniplex Multiplexer for PTT Line
    Combining on Hand Held and Mobile Radios
  • Installation of complete Network Management
    System for the whole West District over RS-232
    modems in Taif and Jeddah.
  • PSD Transmission Project
  • Direct contract with Harris Farinon for
    implementation of
  • Setting up of Transmission Network and its
    Network Management System five (5) sites in
    Riyadh and three (3) sites in Madinah.

30
SITE SURVEY RADIO SITE INVESTIGATION
31
CIVIL WORK SITE IMPLEMENTATION
32
RADIO INSTALLATION ERICSSON RBS TRANSMISSION
RADIO
33
RADIO INSTALLATION STC BTS NOKIA RBS
AND TRANSMISSION RADIO
34
DUAL DIESEL GENERATORS INSTALLED ON GSM SITES