Title: Introduction%20to%20Foamed%20Asphalt
1Introduction to Foamed Asphalt
2How is Foamed Asphalt Produced?
- Source material for foamed asphalt is ordinary
hot asphalt cement (AC-5 or PG 52-28). -
- Foam is produced using hot asphalt with a
temperature between 325 to 340 F and a
precisely defined amount of water (2.5 by weight
of asphalt). - When the water comes in contact with the hot
asphalt it evaporates explosively, causing the
asphalt to Foam. - The asphalt expands up to 15 of its original
volume. - When foamed, the asphalt has a very large surface
area making it ideal for mixing with aggregates.
3Expansion Chamber
- Cold water and air are injected simultaneously
into the hot asphalt. - The hot asphalt foams explosively and shoots down
into the mixing chamber.
4Mixing Chamber Diagram
Hot Asphalt
Water For Foam Generation
Compaction Water
5Foamed Asphalt Recycled Material
63 Asphalt Binder by Weight of Recycled Material
7Foamed Asphalt Work Done in Alaska
- Kenai Peninsula Paving Program 2001
- East Hill Road and West Hill Road, Homer
- Project Staff Bob Lundell, PE, Project Manager
- Gary Walklin, PE, Project Engineer
- Paul Dougherty, Grade Inspector
- Contractor Alaska Road Builders
- Eric Uppick with Wirtgen Group
-
-
8Project Location Homer, Alaska
9Mix Design
- Mix design was done by Wirtgen and Loudon
Partners - East Hill Road 2.5 0.3 Foamed Asphalt and
- 1 Portland cement by mass of material
- West Hill Road 3.0 0.3 Foamed Asphalt and
- 1 Portland cement by mass of material
- 1 Portland cement was added to increase the
percentage passing the No. 200 sieve, which is
critical for proper dispersion of the foamed
asphalt.
10Mix Design
- Fines are critical for proper dispersion of the
foamed asphalt.
11(No Transcript)
12(No Transcript)
13Wirtgen WR 2500
14Compaction Water
Hot Asphalt
15Initial Compaction
16Initial Compaction and Grading
17Final Grading and Compaction
18Final Compaction
19One Day After Foam Treatment
20Paving
21Final Driving Surface
22Advantages of Foamed Asphalt
- Allows the use of unsuitable base material (6 to
20 passing the No. 200 sieve). - Eliminates the need and expense of removing
unsuitable bases. - Can be opened to traffic immediately after
compaction. - Increased strength
Material Design Resilient Modulus (Ksi)
Foamed Asphalt Treated Base Crushed Asphalt Base Crushed Aggregate Base Coarse 110 80 40-50