Title: PUBLIC%20HEARING%20ON
1- PUBLIC HEARING ON
- CONDITIONAL GRANTS AND CAPITAL EXPENDITURE
- 08 May 2006
2INTRODUCTION
- The Free State Department of Education has been
invited to Public Hearings and to address the
NCOP Select Committee on Finance on the
following - Data trends in conditional grants and capital
expenditure allocations - 2005/06 Transfers and actual expenditure
- Assessment on Departments monitoring capacity
- Indication of under spending/ overspending
- Capacity constraints and their impact
32001/02 05/06 CONDITIONAL GRANTS DATA TRENDS
SUMMARY
2001/02 R000 2002/03 R000 2003/04 R000 2004/05 R000 2005/06 R000 2006/07 R000
Total Amount Received 73,355 177,471 130,454 196,662 217,193 239,157
Total Spending 20,579 76,606 111,978 181,409 204,218 N/A
Balance 52,776 100,865 18,476 15,253 12,975
Spending 28 43 86 92 94
4CONDITIONAL GRANTS SPENDING TRENDS
52005/06 CONDITIONAL GRANTS RECEIVED
Conditional grant Appropriated R000 Roll-overs R000 Additional Funds R000 Total R000
HIV and AIDS 7,947 0,455 8,402
NSNP 53,817 2,951 11,747 68,515
Provincial Infrastructure grant 55,913 4,638 60,551
Own Infrastructure grant 73,360 6,365 79,725
Total 191,037 14,409 11,747 217,193
62005/06 SPENDING ON CONDITIONAL GRANTS
72005/06 CONDITIONAL GRANT SPENDING
8LEARNERS FED THROUGH Bread Menu NSNP DURING
2005/06
District No Learners No of schools
FEZILE DABI 17 941 197
LEJWELEPUTSWA 21 923 239
MOTHEO 26 317 168
THABO MOFUTSANYANA 126 244 488
XHARIEP 26 128 79
TOTAL 218 553 1171
92005/6 SCHOOLS FED COOKED MENU
District No Learners No of schools
FEZILE DABI 34 638 50
LEJWELEPUTSWA 45 294 61
MOTHEO 38 130 49
THABO MOFUTSANYANA 3 854 5
XHARIEP 16 127 44
GRAND TOTAL 134 043 209
10NSNP GRAND TOTAL 2005/06
Number of Learners Number of Schools
feeding of cooked meals 134 043 209
feeding of bread menu 218 553 1171
GRAND TOTAL 352 596 1380
11LEARNER SUPPORT PROGRAMMES
- Learner transport provided to 3 117 farm school
learners in Province. - 3 more Hostels (initial 8) in Edenburg for 55
learners, Villiers for 40 and Thaba Nchu for 100
learners
- Feed total 352 596 learners through NSNP
exceeding initial target of 287 000. - Provide hot meals to 21 schools in pilot
project, feeding over 134 043 learners
12HIV AND AIDS PROGRAMMES
- A total of 1,818 educators have been trained in
Basic Counseling Skills - A further 1,000 educators were trained from all
schools at GET and ECD level in Life Skills and
HIV and AIDS education - 1,000 educators were trained in awareness
programmes that include prevention, care and
support at school level - All School Management Teams were trained in the
management of the impact of HIV and AIDS,
programme extended to SGBs - ABET educators were trained in Life Skills and
HIV and AIDS education
13ADDITIONAL FUNDING R70,7 MILLION
14MINOR REPAIRS EPWP PROJECTS
- 252 schools completed, entails renovations at
R31,6 million where SMMEs were utilised - Further 355 schools allocated by end of February
2006 for similar project at R39,1 million - 22 farm schools refurbishment with unsafe
structures utilising mobile classrooms - Letsema projects completed at 90 schools to
repair broken windows, painting of ceilings and
walls etc.
15TRANSFER PAYMENTS TO SCHOOLS
- Funds transferred to schools for renovations were
executed through a selected process and training
was given before payments were made into their
banking accounts - Teams were set up in order to monitor and manage
individual school projects - Teams consist of the School Governing Bodies and
the principal plays a critical role. - District teams assisted schools in their
respective districts, lead by the Physical
Planners and at Head Office level, a Project
Manager was appointed to co-ordinate the above.
16ACTUAL SPENDING ON CAPEX AS 31 MARCH 2006
Description 2005/06 Allocation R000 Spending as at 31 March 2006 R000 Spending
Capital transfers 213,683 210,583 99
Buildings and fixed structures 56,799 39,998 70
Machinery and equipment 27,708 23,116 83
Total 298,190 273,697 92
17TRANSFER OF FUNDS FROM EDUCATION TO PWRT
- Funds for capital projects implemented by Public
Works were transferred as per the agreements
between the two departments - A total amount of R106,942 million was made
available to Education and subsequently
transferred to the Department of Public Works to
speed up capital projects - As at 31 March 2006 an amount of R95,634,845 was
spent - This amount includes R8,956,713which is for
retentions and guarantees to contractors. - An amount of R10,827,271 was brought forward to
the current financial year, being funds already
committed
18SERVICE LEVEL AGREEMENT
- The existing Service Level Agreement makes
provision for the Department of Public Works to
execute all Capital projects, whilst the
Department of Education is responsible for the
implementation of Minor Capital Projects
(renovations) and day-to-day maintenance - The Department of Education remains responsible
for funds transferred to the Department of Public
Works - Meetings between the two departments take place
on monthly. These meetings are attended by Senior
Managers from both departments - The Service level Agreement is in the process of
revision to make provision that the Department of
Public Works will also take responsibility for
the implementation of the latter
19PROGRESS ON CAPITAL PROJECTS IN 2005/06
- Completed 6 new schools
- Tawana
- JJ Kubheka
- Disasterpark
- SS Paki
- Louriepark ( completed April 2006)
- Tumisang (Completed April 2006)
- And good progress on others
- JC Motumi (Kutlwanong)
- Kgotso- Uxolo(Reitz)
- Commenced with construction of 2 new schools
- Dr. Mgoma- January 2006 (Welkom)
- EE Monesa January 2006
- (Senekal)
- Commenced with construction of Additional
facilities at - Mmabana P/S- Jan 2006
- AND finalised
- PPP feasibility study completed for construction
of 13 new schools to eliminate platooning schools
by 2008/09
20OVER / UNDER SPENDING
- It is important to note that according to MINMEC
figures, only 74 was spent on Capex. This figure
was disputed in that meeting and the correct
figure is 90 of our budget - The main reason for not spending all the funds is
due to the heavy rains in the Province since
January 2006 - The Department of Public Works promised that the
outstanding amount will be spent by June on the
projects affected by rain
21OVER / UNDER SPENDING AND CAPACITY CONSTRAINTS
- The only areas of under expenditure are located
in the implementation of small capital projects,
day-to-day maintenance and the Letsema Project
due to capacity constraints of implementers of
projects . - Improved planning projects were approved prior
to the commencement of the 2006/07 financial year
to ensure more efficiency in 2006/07 - Improving staffing levels by appointing
additional technical staff to monitor progress on
site
22MONITORING CAPACITY AND PLANNING
- Capital and Expenditure trends throughout the
Department are now monitored by a dedicated
Directorate one Management Accountant is
dedicated to this assignment . - Monthly reconciliation on BAS Expenditure reports
are done to track expenditure against each
project - Monthly in-house monitoring meetings are now held
to provide early warning to all Managers. - The relevant Directorate must now report at the
Quarterly Review meetings of its remedial
measures on under/over expenditure. - Regular monitoring meetings with Department of
Public Works, Roads and Transport are held to
monitor progress on major capital works. - The full implementation of the Infrastructure
Development Programme will also assist to ensure
projects are effectively executed. (IDIP) - National Treasury is also assisting with the
Technical Assistant to support both Education and
Department of Public Works, Roads and transport - The Planning of Projects is also improved to
ensure the projects start on time and are
timeously completed. - Business Plans for the 2006/07 have been
submitted on time to PWRT for the current
financial year according to the Division of
Revenue Act.
23INFRASTRUCTURE ACTION PLAN 2006/07
24INFRASTRUCTURE ACTION PLAN 2006/07 (CONTINUED)
252006/07 INFRASTRUCTURE DELIVERY IMPROVEMENT
PROGRAMME
- Align the Budget Process Strategic Planning
Process - and
- the multi-year Infrastructure Plans
- Regular Monitoring of infrastructure projects
- Keeping accurate expenditure and commitment
register for the Capital Budget Transferred to
PWRT - Regular Management meetings with PWRT
26THANK YOU