Title: PROJECT MANAGEMENT Time Management*
1PROJECT MANAGEMENT Time Management
Dr. L. K. GaafarThe American University in Cairo
This Presentation is Based on information from
the PMBOK Guide 2000
2Critical Path Method (CPM)
- CPM is a project network analysis technique used
to predict total project duration - A critical path for a project is the series of
activities that determines the earliest time by
which the project can be completed - The critical path is the longest path through the
network diagram and has the least amount of float
3Finding the Critical Path
- Develop a network diagram
- Add the durations of all activities to the
project network diagram - Calculate the total duration of every possible
path from the beginning to the end of the project - The longest path is the critical path
- Activities on the critical path have zero float
4Simple Example
Consider the following project network diagram.
Assume all times are in days.
5Simple Example
Activity-on-arrow network
a. 2 paths on this network A-B-C-E, A-B-D-F. b.
Paths have lengths of 10, 16 c. The critical
path is A-B-D-F d. The shortest duration needed
to complete this project is 16 days
6Time Management
Key
ES
EF
7
9
9
10
Slack
Dur.
Act
6
2
C
6
1
E
LS
LF
13
15
15
16
0
2
2
7
Dummy
0
2
A
0
5
B
0
2
2
7
7
14
14
16
Activity-on-node network
0
7
D
0
2
F
16
7
14
14
7Cash Flow
8Cash Flow
9Determining the Critical Path for Project X
a. How many paths are on this network diagram?
b. How long is each path? c. Which is the
critical path? d. What is the shortest duration
needed to complete this project?
10Stochastic (non-deterministic) Activity
DurationsProject Evaluation and Review
Technique (PERT)
11Stochastic Times
Uniform
Triangular
Beta
12Important Distributions
13Stochastic Times The Central Limit Theorem
The sum of n mutually independent random
variables is well-approximated by a normal
distribution if n is large enough.
14PERT Finding the Critical Path (Stochastic Times)
- Develop a network diagram
- Calculate the mean duration and variance of each
activity - Calculate the total mean duration and the
variance of every possible path from the
beginning to the end of the project by summing
the mean duration and variances of all activities
on the path. - The path with the longest mean duration is the
critical path - If more than one path have the longest mean
duration, the critical path is the one with the
largest variance. - Calculate possible project durations using the
normal distribution
15Example I
Assuming that all activities are beta
distributed, what is the probability that the
project duration will exceed 19 weeks?
167
A 7, 2.8
B 4.5, 0.7
E 3.5, 0.25
14
17.5
C 5,0.1
D 7, 0
F8.7, 1.8
7
G 17.5, 1.36
177
A 7, 2.8
B 4.5, 0.7
E 3.5, 0.25
14
17.5
C 5,0.1
D 7, 0
F8.7, 1.8
7
G 17.5, 1.36
18Example II
Duration Duration Duration Duration
Activity IPA Distribution a m b
A --- Uniform 4 NA 8
B --- Triangular 3 4 5
C --- Beta 4 5 6
D C Beta 5 7 12
E A Triangular 3 3 6
F A, B Triangular 5 8 8
G E, D Uniform 9 NA 9
Construct an activity-on-arrow network for the
project above. Provide a 95 confidence interval
on the completion time of the project.
19Example II
Duration Duration Duration Duration
Activity IPA Distribution a m b
A --- Uniform 4 NA 8
B --- Triangular 3 4 5
C --- Beta 4 5 6
D C Beta 5 7 12
E A Triangular 3 3 6
F A, B Triangular 5 8 8
G E, D Uniform 9 NA 9
F
B
A
Start
Finish
E
G
C
D
20Example II
B (4, 0.17)
F (7, 0.5)
A (6, 1.33)
Start
Finish
C (5, 0.11)
E (4, 0.5)
G (9, 0.0)
D (7.5, 1.36)
21Time Management Crashing
Consider the following project network diagram.
Assume all times are in days.
22Time Management
C(2,1,50)
E(1,1,0)
A(2,2,0)
B(5,3,100)
F(2,1,250)
D(7,4,50)
23Duration/Cost Decision Support Curve
24Time Management
C(2,1,50)
E(1,1,0)
A(2,2,0)
B(3,3,100)
F(1,1,250)
D(4,4,50)
Shortest Possible duration with crashing is 10
days.Critical path is not changed.
25Example Problem
26Project Network
A 6
B 4
E 4
C 5
D 7
F 8
G 18
Shortest possible normal duration is 18 at a cost
of 757
27Time Management
0
6
6
10
A
B
1
6
4
4
13
17
1
7
10
14
1
4
E
18
14
0
5
6
13
Dummy
2
5
C
1
7
D
14
2
7
7
6
14
0
18
Dummy
4
8
F
0
18
G
18
10
18
0
28Crashing
A(4,4,10)
B(4,3,13)
E(2,2,21)
D(7,7,0)
F(8,6,12)
C(4,4,15)
G(13,13,18)
29Final Crashed Network
A(4,4,10)
B(4,3,13)
E(2,2,21)
D(7,7,0)
F(8,6,12)
C(4,4,15)
G(13,13,18)
The shortest crashed project duration is 13 days
at a minimum total cost of 924. Further crashing
of B or F is useless
30Using Critical Path Analysis to Make Schedule
Trade-offs
- Knowing the critical path helps you make schedule
trade-offs - Free slack or free float is the amount of time an
activity can be delayed without delaying the
early start of any immediately following
activities - Total slack or total float is the amount of time
an activity may be delayed from its early start
without delaying the planned project finish date
This part is from a presentation by Kathy
Schwalbe, schwalbe_at_augsburg.edu http//www.augsbur
g.edu/depts/infotech/
31Techniques for Shortening a Project Schedule
- Shortening durations of critical tasks by adding
more resources or changing their scope - Crashing tasks by obtaining the greatest amount
of schedule compression for the least incremental
cost - Fast tracking tasks by doing them in parallel or
overlapping them
This part is from a presentation by Kathy
Schwalbe, schwalbe_at_augsburg.edu http//www.augsbur
g.edu/depts/infotech/
32Shortening Project Schedules
Original schedule
Shortenedduration
Overlapped tasks
This part is from a presentation by Kathy
Schwalbe, schwalbe_at_augsburg.edu http//www.augsbur
g.edu/depts/infotech/
33(No Transcript)
34Activity Definition
Activity Sequencing
35Duration Estimation
Schedule Development
36Schedule Control