MINIMIZED WASTAGES IN CONSTRUCTION PROJECT - PowerPoint PPT Presentation

1 / 53
About This Presentation
Title:

MINIMIZED WASTAGES IN CONSTRUCTION PROJECT

Description:

MINIMIZED WASTAGES IN CONSTRUCTION PROJECT – PowerPoint PPT presentation

Number of Views:707
Avg rating:3.0/5.0
Slides: 54
Provided by: Gue26
Category:

less

Transcript and Presenter's Notes

Title: MINIMIZED WASTAGES IN CONSTRUCTION PROJECT


1
MINIMIZED WASTAGES IN CONSTRUCTION PROJECT
  • PRESENTED BY
  • IR. SUYANTO HJ. OSMAN

2
BRICKS
3
CEMENT
4
WOOD
5
REBAR
6
SAND
7
INDISCRIMINATE DUMPING
8
INDISCRIMINATE DUMPING
9
INDISCRIMINATE DUMPING
10
WHAT IS WASTAGE
  • Something that
  • is wasted
  • waste or
  • waste materials.

11
What is construction waste?
Construction Waste
Waste generated by design
activities
Waste generated by construction activities
12
Construction Waste
Waste generated by design activities
  • Drylining cutting of plasterboard sheets and
    metal studs to fit wall heights and openings
  • Flooring cuttings of floor tiles to fit room
    layouts
  • Ceilings cuttings of ceiling tiles and fixings
    to fit room layouts
  • Insulation cutting of insulation boards to fit
    openings
  • Tiling cutting of floor and wall tiles to suit
    design and room shapes
  • Paving cutting of paving slabs to fit layout
  • Brickwork and blockwork cuttings of bricks and
    blocks to suit building dimensions and building
    services

13
Construction Waste
Waste generated by construction activities
  • Inaccurate or surplus ordering of materials that
    dont get used
  • Damage through transportation and handling
    errors
  • Damage through inadequate storage
  • Damage generated by poor co-ordination with
    other trades
  • Rework due to low quality of work
  • Inefficient use of materials
  • Temporary works materials (e.g. formwork,
    hoarding etc)

14
Construction Waste Facts(UK Statistics)
  • Recent research indicates that about 5-10 of
    building materials end up as waste on building
    sites.
  • 2.5 to 4 tons about 1.5 to 2.5 kg per square
    foot of waste is created during the
    construction of a typical home.
  • Most construction waste currently goes into
    landfills, increasing the burden on landfill
    loading and operation.
  • (In Malaysia, most construction waste goes into
    illegal dumping site)

15
Construction Waste Facts(UK statistics)
  • Consists mainly of

16
The process of buying materials
  • A waste allowance is generally included within
    the order to account for design waste and
    construction process waste.
  • Often generic and not project specific and as
    such run a risk of being inaccurate.
  • Leads to either the order of a surplus of
    materials or a materials shortfall.
  • Little evidence exists on the practice of
    reconciliation between materials ordered and
    materials used, therefore limiting the
    information available on contractors knowledge
    of their own efficiency levels.

17
Typical Malaysian Contractors Material Wastage
Allowance
18
The true cost of waste
Purchase Cost of the delivered materials wasted
Cost of waste storage, transport, treatment and
disposal
Loss of not selling waste for salvage or not
recycling

  • Cost of waste usually included in the project
    tender price.
  • Contractors often underestimate the real cost of
    waste.
  • Clients often end up paying for new materials
    that simply get thrown away.

19
WHY BOTHER?
  • An effective effort in minimizing
  • wastage in construction can
  • Make significant savings to the client,
    contractors and the environment
  • Divert a high percentage of all construction
    waste materials from the landfill and recycled
    into new products.

20
Conventional Construction Structure
21
Financial Benefits to clients and contractors
  • Clients end up paying for material wastage.
  • By reducing wastage, a reduced cost for the
    project can be achieved.
  • Cost saving may be shared by main contractors,
    sub contractors and clients

22
Financial Benefits to sub contractors
23
Environmental benefits
24
By setting waste reduction actions, you can
reduce the amount of waste that is generated by
your project. This is the first step in reducing
the amount of waste sent to landfill.
Once the amount of waste generated has been
reduced, actions can be set to recover MORE of
the wasted materials, sending LESS to landfill.
Many products contain recycled material. Recommend
ed minimum target 10 recycled content
Lets assume that 20 of the materials purchased
for this project will be wasted.
Lets now look at what happens to the waste that
has been generated.
There are often opportunities to reuse some waste
materials on-site.
This waste can then be included in the project
instead of being disposed of in skips.
Lets say that you are able to recover 50 of the
offsite.
Only 45 of the waste would be sent to landfill.
Materials Reused Onsite 0.5 tonne
Materials Reused Onsite 1 tonne
Recovered Offsite 5 tonnes
Recovered Offsite 7 tonnes
Recovered Offsite 10 tonnes
Materials Used In Project 80 tonnes
Materials Used In Project 90 tonnes
Recycled Materials 10 tonnes
Materials Purchased 100 tonnes
Waste Destinations Reused on site Recovered off
site Sent to landfill
Waste Destinations Reused on site5 Recovered
off site Sent to landfill
Waste Destinations Reused on site5 Recovered
off site50 Sent to landfill
Waste Destinations Reused on site5 Recovered
off site50 Sent to landfill45
Waste Destinations Reused on site5 Recovered
off site70 Sent to landfill25
Recycled Content 10
Wastage rate 20
Wastage rate 10
Sent to landfill 9 tonnes
Sent to landfill 4.5 tonnes
Sent to landfill 2.5 tonnes
Materials wasted 20 tonnes
Materials wasted 10 tonnes
Virgin Materials 90 tonnes
25
CAUSES OF CONSTRUCTION WASTAGE
  • 1. DESIGN
  • Design Changes.
  • Failure to use standard production item or
    standard size component
  • Lack of
  • design information/delayed instruction
  • Lack of dimension coordination.
  • No consideration on Value Management.

26
CAUSES OF Cont..CONSTRUCTION WASTAGE
  • 2. WASTAGE DURING CONSTRUCTION
  • Purchasing
  • Material Transportation and delivery
  • Storage problems
  • Practical waste
  • Handling and Fixing Waste
  • Faulty or poor workmanship
  • Vandalism and Theft

27
EXAMPLES OF CAUSES
Site Management and Practices
28
EXAMPLES OF CAUSES
Site Management and Practices
29
EXAMPLES OF CAUSES
Delivery of products
30
THE IMPORTANCE OF MINIMIZING WASTAGE IN
CONSTRUCTION
TIME
WASTAGE
QUALITY
COST
Wastage will have direct impact on Time, Cost and
Quality of a construction project
31
HOW TO EFFECTIVELY MINIMIZE WASTAGE
  • Attitude toward Minimizing wastage
  • Design to prevent waste
  • Use of prefabrication construction method instead
    of conventional method.
  • Material procurement and handling
  • Adapting a Site Waste Management Plan

32
Who should take action to reduce construction
waste?
  • A shared responsibility between all parties
  • The Client
  • The Designer
  • The Contractor
  • The Sub contractor and Supplier
  • The Workers
  • Contractors and sub contractors, cannot work in
    isolation.
  • Leadership is required from clients.

33
Design To Prevent Waste
  • Examples
  • Optimize designed dimensions to correspond to
    standard product dimensions.
  • Modify framing details to optimize lumber use and
    reduce waste and costs when ordering.
  • Order drywall in optimal dimensions to minimize
    cut-off waste. Drywall is available in different
    lengths, and designed dimensions should
    correspond to standard sizes.
  • Minimize the number of blueprints and
    reproductions necessary during the design and
    construction.
  • Evaluate if salvaging used products is possible.

34
COMPARISON WASTAGE LEVEL OF MAJOR MATERIAL USED
ON SITE BETWEEN CONVENTIONAL PREFAB CONSTRUCTION
Source Comparing material wastage level between
conventional in-situ and prefabrication
construction on 30 construction projects Hong
Kong Universities
35
Purchase To Prevent Waste
  • Avoid excessively packaged materials and
    supplies. Packaging should be adequate to prevent
    damage and waste.
  • Minimize waste of vinyl siding, flooring and
    countertop materials by ordering only the
    quantity needed in building specific lengths.
  • Evaluate estimating procedures to make sure that
    excess material is not delivered to the site.

36
The solution
  • Adopt a robust system that enables the
    production of accurate estimates of material
    requirements at the start of a project that links
    to real waste figures on completion.

37
A best practice approach to waste reduction
1
2
3
4
Planning
Implementation
Review
Improvement
Main contractor requests final waste information
from sub contractors
Share lessons learned Promote innovation Raise
awareness Demonstrate better financial and
environmental results
Clients sets targets for waste
Main contractors and sub-contractors review
waste and take action to minimise and manage waste
Main contractor prepares Site Waste Management
Plan
Sub contractors complete waste information
questionnaires
Sub contractor estimates waste
Quantitative Record
Qualitative Checklist
Quantitative Estimate
Qualitative Checklist
Main contractor coordinates data and feeds back
to client
38
A Site Waste Management Plan contains the
following key features
Q
Planning
Client sets targets for waste
  • waste targets as set by client,
  • an estimate of the waste to be generated on site,
  • actions to reduce waste, and
  • actions to avoid waste going to landfill

Main contractor prepares Site Waste Management
Plan
Sub contractor estimates waste
Quantitative Estimate
Qualitative Checklist
39
Best Practices
Implementation
  • Appoint a Site Waste Manager responsible to
  • ensure that appropriate storage conditions are
    available
  • keep a record of all materials brought to site
  • Site Waste Manager to ensure materials are
    supplied in an appropriate manner, and in the
    correct quantity
  • Site Waste Manager monitor costs/volumes of
    disposal
  • The Site Waste Manager to determine KPIs on this
    basis
  • Sub contractors appoint a Trade Waste Manager

Main contractors and sub-contractors review
waste and take action to minimise and manage waste
40
Reviewing data and providing feedback can have
real benefits, such as
Q
Review
Main contractor requests final waste information
from sub contractors
  • Assess effectiveness of the waste minimization
    and management strategy.
  • Learn what works and doesnt work in reducing
    waste
  • Identify exactly how efficient main contractors
    and sub contractors were on the project in turn
    enabling them to understand how wasteful they
    were
  • Main contractors can see which trades contributed
    what quantity of materials to the waste stream
    and why enabling them to prepare better waste
    estimates in the future
  • Capture any relevant data for future reference
    and use.

Sub contractors complete waste information
questionnaires
Quantitative Record
Qualitative Checklist
Main contractor coordinates data and feeds back
to client
41
Improvement
Share lessons learned Promote innovation Raise
awareness Demonstrate better financial and
environmental results
42
Appoint A Site Waste Manager
While all people involved should be encouraged
to contribute their ideas and suggestions on ways
to minimize waste, one person (or the
Environmental, Health and Safety Manager) should
act as the Site Waste Manager, responsible for
overseeing the management of construction wastes.
This person will be responsible for managing
waste reduction initiatives and coordinating the
activities of other employees.
43
Key role of a site waste manager .
  • Ensure that all relevant legislation and the
    contractors duty of care is complied with.
  • Initiate waste reduction, reuse and recycling.
  • Ensure all site personnel know their
    responsibilities for site waste management.
  • Co-ordinate waste management on site, gather data
    about waste on site, keep accurate records on
    waste movement on and off site.
  • Ensure that all waste storage areas and
    containers are properly labelled to show site
    workers where to deposit specific materials.
  • Be aware of the construction activities currently
    taking place on site and the activities planned
    in the short term.

44
Key role of a site waste manager
  • Conduct a survey of wastes likely to be generated
    on site and keep a record of them for planning
    ahead.
  • Whenever possible, ensure the re-use or recycling
    of material already on site before it is carted
    away or new materials are imported.
  • Obtain a list of potential buyers or collectors
    of materials to be re-used or recycled.
  • Encourage all site personnel to use their
    initiative in coming up with ideas of how to
    reduce, reuse and recycle wastes.
  • Inform designers so that waste can be reused and
    recycled on site or on another site.

45
Managing Subcontractors
  • Use a system of allowable waste percentages. In
    the early pre-work agreements the site manager
    decides how much waste is acceptable, and agrees
    a percentage with the subcontractor.
  • If they waste more than the agreed amount, they
    can be charged the extra costs.
  • This is a great incentive to reduce wastes by
    efficient use of
  • materials. The lower the allowable percentage,
    the more care people will take with materials.
  • Setting the right level is crucial.

46
Managing Subcontractors
  • Make subcontractors responsible for both
    purchasing the raw materials they need, and
    disposing of any waste material from their
    activities. This will give them a direct
    financial incentive to use materials efficiently
    with the minimum of wastage.
  • Make subcontractors aware of wastage and the
    costs involved in dealing with wastes.
  • Hold regular meetings to discuss wastage on site.

47
INCENTIVES
  • If contractors or sub-contractors can
    demonstrate a willingness to support and engage
    in waste reduction measures and demonstrate that
    these have an effect on their waste, then they be
    identified as preferred bidders.

48
Policy and legislation
  • Currently no regulatory obligation in Malaysia to
    reduce and manage waste to good practice
    standards.
  • Hope this presentation will increase the
    awareness for the need of public policy to
    achieve greater resource efficiency and reduce
    wastage in the construction industry.

49
Landfill Tax
The Landfill Tax in UK was introduced in 1996 to
encourage all organisations, including those in
the construction industry, to reduce the amount
of waste disposed to landfill.
50
Mandatory requirement for Site Waste Management
Plans (SWMPs)
It is expected that the use of SWMPs will become
a mandatory requirement for many construction
projects throughout the UK in the near future,
the current position being summarised below.
51
OFFENCES AND TO WHOM (UK)
52
CONCLUSION
  • Activities that minimize wastage, such as
    designing to standard sizes, reusing building
    materials, not only cut waste and recycling
    collection costs but also reduces materials'
    expenses.
  • Small changes to construction practices and extra
    attention to detail can add up to significant
    savings to the client, the contractor and the
    environment.
  • Everyone of us here has a role to play in
    bringing changes to our construction practice.
    Let us begin.

53
Thank You
Write a Comment
User Comments (0)
About PowerShow.com