Title: High Voltage Plant Asset Management
1High Voltage Plant Asset Management
- Joe Tusek
- Connell Wagner
- tusekj_at_conwag.com
2HV Asset Management Environment
- Disaggregation
- OEMs
- Aging workforce
- Staff churn
- Production
- 415V -gt 3.3kV -gt 11kV -gt 22-33kV -gt -----
- Profit
- OHS
3High voltage equipment is complex
4What is special about HV Assets?
- New knowledge - not inferable from LV.
- New service providers.
- Special considerations in contracts.
- Wide variation in understanding, ability and
degree of self interest amongst practitioners.
5Results of Poor Asset Management
- Premature or late equipment refurbishment or
replacement. - Under-testing or inappropriate testing -gt No
useful CM data. - Over-testing - gt damage.
- Unquantified risk (bounded by Worst Case
Scenario). - Unsafe plant.
- Damaged plant.
- Misapplication of capital
6CIGRE - General aging and failure model
7Characteristics of HV plant failure
- Motors
- Apart from infant mortality, most electrical
degradation tends to evolve slowly unless damage
occurs -gt years. - Transformers
- Most classes of failure can be picked up by DGA
taken once every quarter for critical plant. - Cables
- Very dependant on failure mechanism but typically
within days or weeks.
8HV Failures
- There are a number of failure mechanisms that can
lead to sudden unexpected failure. - Cost of preventing all failures is very high.
- A good CM system will limit the likelihood of
failure but will not guarantee freedom from
failure. - On-line systems are good but many stories of
after the fact identification of problems. - What can help?
9Standards are a minimum
- Committee system - representatives from OEMs,
academics and recognised specialists. - Minimum agreed test levels and pass criteria.
- Agreed compromise on quality, Standards only
contain what OEMs can deliverable. - Adherence to Standards is a risk management tool.
- Not perfect but substantially better than just
using opinion.
10Why Are Standards Not Followed
- Ignorance
- Bad advice
- Expediency
- Fear
- Self interest
- Good times can bring about practices that have a
significant negative impact on the bottom line
when times are tough.
11Plant Life Cycle
- Specification
- Design
- Construction
- Factory Testing
- Delivery
- Installation
- Commissioning
- Acceptance
- Operation
- Maintenance
- Refurbishment/Life Extension
12Understanding HV System Degradation
- Failure of HV systems is initiated through,
-
- Electrical
- Mechanical
- Thermal
- Environmental/Chemical
13Electrical Degradation and Failure
- Overstressing of insulating system by external
stresses or failure of voltage grading systems. - Partial discharge due to insulating system
being overstressing or contaminated. - Partial discharge due to delamination of
composite insulating systems. - Tracking conducting paths often carbonised.
14Partial Discharge
- Is a breakdown of the insulation that does not
bridge the primary insulation - Corona is a partial break down in gas.
15Typical Partial Discharge Results
16Electrical Degradation and Failure
- Thermal instability of the dielectric in the
insulating system. - Tracking across dielectric surfaces.
- Short circuits between windings and winding
components. - Damage to bearings from currents.
17Mechanical sources of degradation
- Short circuit currents and vibration
- Age related loss of strength
- Cycling, creep and fatigue
- Bearings
- Lubricating systems
- Vibration or resonance
18(No Transcript)
19Thermal
- Overheating of contacts/ connections/ joint
- Thermal ageing of components
- Failure of cooling systems
- Ineffective maintenance of cooling system
efficiencies - Ineffective maintenance of cooling medium
condition (eg insulating oil in transformers)
20Environmental
- Oxidation
- Hydrolysis
- Corrosion
- Contamination
- external
- gasses, particles, acidic or basic substances
- lubrication, cooling or process.
- internal
- ageing products, acids and ozone.
21Insulation Resistance (IR)/ Polarisation Index
(PI)
- Measure the DC resistance of insulation
- Very temperature and humidity dependant.
- Will show up contamination and moisture ingress.
- Polarisation Index is the ratio of the 10 minute
to the 1 minute IR, ?2.0 - Often is translated to fixed temperature, but
what is the starting temperature?
22Insulation Resistance (IR)/ Polarisation Index
(PI)
- DC tests generally result is stress distribution
that is different from AC operation. - Depending on the voltage levels to be used, this
may impact on interpreting or determine how and
to what level the test is performed. - Generally discouraged and misinterpreted for XLPE
cables, voltages of lt0.3Un for CM are not a
problem. - VLF cable test relies on stress be representative
at 0.1Hz. - VLF test is intended to fail defective cables.
23Insulation Resistance
- Typical IR Results at 10 minutes 20C
- HV Transformer gt500 M ?
- HV Motor gt1000 M?
- HV Paper Lead Cable gt100 M?
- HV XLPE Cable gt10,000 M?
24DC Ramp Test
- Voltage is raised slowly and current is plotted
against voltage, i.e. resistance trajectory. - Generally applied to stators and indicates
presence of damaged or weak ground wall
insulation. - Less informative than PD test although much
cheaper to perform and uses portable equipment.
25Winding Resistance / Circuit Resistance
- Measures complete circuit resistance
- Applied to motors, switchgear, cables and
transformers. - Generally 4 - terminal measurement.
- Temperature correction required for comparison to
measurements taken on other occasions.
26Transformer - Circuit resistance results
27Some other transformer tests
- Applied Test
- Induced Test
- Ratio
- Excitation current
- Leakage impedance
28Dielectric Dissipation Factor
- DDF tests is sometimes referred to as Doble
Tests.
- Measure of the losses in the insulation,
- electronic and ionic conductivity
- dipole orientation
- space charge and interfacial polarisation
- partial discharge
- corona
29DDF in 3.3kV motors
30DDF in 11kV motors
31Partial Discharge in 11kV Motor
32Dissolved Gas Analysis (DGA)
- Measures gases in oil
- Different gasses and combinations are indicative.
- Provides historical as well as current
information. - Cheap.
33DGA detects
- arcing
- overheating
- moisture
- ageing
- paper or metal involvement in degradation
- need for oil reclamation
34Furan Analysis / Degree of Polymerisation (DP)
- DP is the average length of the molecular chain
that makes up the paper - new 1200, end of life 200
- Furans ? DP
- Furan test is non-invasive, relatively cheap, but
less accurate. - Typical large transformer can have over a few
tons of paper and over 200kg of water trapped in
the paper and pressboard insulation. - The insulating oil contains only a small fraction
of the water in the insulating system.
35Thermography
- Simply one of the most cost effective risk
control tools available to industry. -
36Ring Flux and ELCID
37Ultrasonic or Acoustic Emission Detection
- Primarily a locating test
- Can detect
- Corona
- PDs
- mechanical vibrations
- leaks
38Frequency Response Analysis
- A transfer function or impedance function that
represents the geometric and physical parameters
of a transformer winding and its insulation. - Sensitive to winding deformation
39Equivalent Paper Moisture
Dielectric Spectroscopy
paper moisture
Polarisation Depolarisation Current
Recovery Voltage Method
40Transformer CM Options
41On- line systems
- Not as good as off-line tests in most cases.
- Are good for managing the time towards final
failure or end of economic life. - Best suited to critical plant items or those with
known advanced active degradation. - May need expertise in interpretation.
- Generally far less reliable than the plant being
measured. - Relatively expensive as often need to installed
in many locations.
42Database Solutions
- Pros
- Very attractive
- Benefit of large population
- No requirement for internal expertise
- Cons
- Significant uniqueness in plant with components
made globally. - Statistical notion of population is not helpful
when you only a few plant items. - Suspend own judgement.
- Decision making can be based on rest of the
population and not on your plant or conditions.
43Visual Inspection the ugly duckling of CM?
44Minimum Electrical CM
- HV Motor
- Thermography HV Tests
- MCSA and online measurements
- Transformer
- DGA Thermography
- HV Test
- Switchgear
- Thermography insulation and circuit resistance
HV tests - Timing checks
45Where is help available?
- Specialists service providers
- OEMs
- Consultants, in-house or external
- Universities
- Standards
- Technical Organisations