High Voltage Plant Asset Management - PowerPoint PPT Presentation

1 / 45
About This Presentation
Title:

High Voltage Plant Asset Management

Description:

Wide variation in understanding, ability and degree of self ... Misapplication of capital. 6/19/09. 7. CIGRE - General aging and failure model. 6/19/09 ... – PowerPoint PPT presentation

Number of Views:224
Avg rating:3.0/5.0
Slides: 46
Provided by: joet8
Category:

less

Transcript and Presenter's Notes

Title: High Voltage Plant Asset Management


1
High Voltage Plant Asset Management
  • Joe Tusek
  • Connell Wagner
  • tusekj_at_conwag.com

2
HV Asset Management Environment
  • Disaggregation
  • OEMs
  • Aging workforce
  • Staff churn
  • Production
  • 415V -gt 3.3kV -gt 11kV -gt 22-33kV -gt -----
  • Profit
  • OHS

3
High voltage equipment is complex
4
What is special about HV Assets?
  • New knowledge - not inferable from LV.
  • New service providers.
  • Special considerations in contracts.
  • Wide variation in understanding, ability and
    degree of self interest amongst practitioners.

5
Results of Poor Asset Management
  • Premature or late equipment refurbishment or
    replacement.
  • Under-testing or inappropriate testing -gt No
    useful CM data.
  • Over-testing - gt damage.
  • Unquantified risk (bounded by Worst Case
    Scenario).
  • Unsafe plant.
  • Damaged plant.
  • Misapplication of capital

6
CIGRE - General aging and failure model
7
Characteristics of HV plant failure
  • Motors
  • Apart from infant mortality, most electrical
    degradation tends to evolve slowly unless damage
    occurs -gt years.
  • Transformers
  • Most classes of failure can be picked up by DGA
    taken once every quarter for critical plant.
  • Cables
  • Very dependant on failure mechanism but typically
    within days or weeks.

8
HV Failures
  • There are a number of failure mechanisms that can
    lead to sudden unexpected failure.
  • Cost of preventing all failures is very high.
  • A good CM system will limit the likelihood of
    failure but will not guarantee freedom from
    failure.
  • On-line systems are good but many stories of
    after the fact identification of problems.
  • What can help?

9
Standards are a minimum
  • Committee system - representatives from OEMs,
    academics and recognised specialists.
  • Minimum agreed test levels and pass criteria.
  • Agreed compromise on quality, Standards only
    contain what OEMs can deliverable.
  • Adherence to Standards is a risk management tool.
  • Not perfect but substantially better than just
    using opinion.

10
Why Are Standards Not Followed
  • Ignorance
  • Bad advice
  • Expediency
  • Fear
  • Self interest
  • Good times can bring about practices that have a
    significant negative impact on the bottom line
    when times are tough.

11
Plant Life Cycle
  • Specification
  • Design
  • Construction
  • Factory Testing
  • Delivery
  • Installation
  • Commissioning
  • Acceptance
  • Operation
  • Maintenance
  • Refurbishment/Life Extension

12
Understanding HV System Degradation
  • Failure of HV systems is initiated through,
  • Electrical
  • Mechanical
  • Thermal
  • Environmental/Chemical

13
Electrical Degradation and Failure
  • Overstressing of insulating system by external
    stresses or failure of voltage grading systems.
  • Partial discharge due to insulating system
    being overstressing or contaminated.
  • Partial discharge due to delamination of
    composite insulating systems.
  • Tracking conducting paths often carbonised.

14
Partial Discharge
  • Is a breakdown of the insulation that does not
    bridge the primary insulation
  • Corona is a partial break down in gas.

15
Typical Partial Discharge Results
16
Electrical Degradation and Failure
  • Thermal instability of the dielectric in the
    insulating system.
  • Tracking across dielectric surfaces.
  • Short circuits between windings and winding
    components.
  • Damage to bearings from currents.

17
Mechanical sources of degradation
  • Short circuit currents and vibration
  • Age related loss of strength
  • Cycling, creep and fatigue
  • Bearings
  • Lubricating systems
  • Vibration or resonance

18
(No Transcript)
19
Thermal
  • Overheating of contacts/ connections/ joint
  • Thermal ageing of components
  • Failure of cooling systems
  • Ineffective maintenance of cooling system
    efficiencies
  • Ineffective maintenance of cooling medium
    condition (eg insulating oil in transformers)

20
Environmental
  • Oxidation
  • Hydrolysis
  • Corrosion
  • Contamination
  • external
  • gasses, particles, acidic or basic substances
  • lubrication, cooling or process.
  • internal
  • ageing products, acids and ozone.

21
Insulation Resistance (IR)/ Polarisation Index
(PI)
  • Measure the DC resistance of insulation
  • Very temperature and humidity dependant.
  • Will show up contamination and moisture ingress.
  • Polarisation Index is the ratio of the 10 minute
    to the 1 minute IR, ?2.0
  • Often is translated to fixed temperature, but
    what is the starting temperature?

22
Insulation Resistance (IR)/ Polarisation Index
(PI)
  • DC tests generally result is stress distribution
    that is different from AC operation.
  • Depending on the voltage levels to be used, this
    may impact on interpreting or determine how and
    to what level the test is performed.
  • Generally discouraged and misinterpreted for XLPE
    cables, voltages of lt0.3Un for CM are not a
    problem.
  • VLF cable test relies on stress be representative
    at 0.1Hz.
  • VLF test is intended to fail defective cables.

23
Insulation Resistance
  • Typical IR Results at 10 minutes 20C
  • HV Transformer gt500 M ?
  • HV Motor gt1000 M?
  • HV Paper Lead Cable gt100 M?
  • HV XLPE Cable gt10,000 M?

24
DC Ramp Test
  • Voltage is raised slowly and current is plotted
    against voltage, i.e. resistance trajectory.
  • Generally applied to stators and indicates
    presence of damaged or weak ground wall
    insulation.
  • Less informative than PD test although much
    cheaper to perform and uses portable equipment.

25
Winding Resistance / Circuit Resistance
  • Measures complete circuit resistance
  • Applied to motors, switchgear, cables and
    transformers.
  • Generally 4 - terminal measurement.
  • Temperature correction required for comparison to
    measurements taken on other occasions.

26
Transformer - Circuit resistance results
27
Some other transformer tests
  • Applied Test
  • Induced Test
  • Ratio
  • Excitation current
  • Leakage impedance

28
Dielectric Dissipation Factor
  • DDF tests is sometimes referred to as Doble
    Tests.
  • Measure of the losses in the insulation,
  • electronic and ionic conductivity
  • dipole orientation
  • space charge and interfacial polarisation
  • partial discharge
  • corona

29
DDF in 3.3kV motors
30
DDF in 11kV motors
31
Partial Discharge in 11kV Motor
32
Dissolved Gas Analysis (DGA)
  • Measures gases in oil
  • Different gasses and combinations are indicative.
  • Provides historical as well as current
    information.
  • Cheap.

33
DGA detects
  • arcing
  • overheating
  • moisture
  • ageing
  • paper or metal involvement in degradation
  • need for oil reclamation

34
Furan Analysis / Degree of Polymerisation (DP)
  • DP is the average length of the molecular chain
    that makes up the paper
  • new 1200, end of life 200
  • Furans ? DP
  • Furan test is non-invasive, relatively cheap, but
    less accurate.
  • Typical large transformer can have over a few
    tons of paper and over 200kg of water trapped in
    the paper and pressboard insulation.
  • The insulating oil contains only a small fraction
    of the water in the insulating system.

35
Thermography
  • Simply one of the most cost effective risk
    control tools available to industry.

36
Ring Flux and ELCID
37
Ultrasonic or Acoustic Emission Detection
  • Primarily a locating test
  • Can detect
  • Corona
  • PDs
  • mechanical vibrations
  • leaks

38
Frequency Response Analysis
  • A transfer function or impedance function that
    represents the geometric and physical parameters
    of a transformer winding and its insulation.
  • Sensitive to winding deformation

39
Equivalent Paper Moisture
Dielectric Spectroscopy
paper moisture
Polarisation Depolarisation Current
Recovery Voltage Method
40
Transformer CM Options
41
On- line systems
  • Not as good as off-line tests in most cases.
  • Are good for managing the time towards final
    failure or end of economic life.
  • Best suited to critical plant items or those with
    known advanced active degradation.
  • May need expertise in interpretation.
  • Generally far less reliable than the plant being
    measured.
  • Relatively expensive as often need to installed
    in many locations.

42
Database Solutions
  • Pros
  • Very attractive
  • Benefit of large population
  • No requirement for internal expertise
  • Cons
  • Significant uniqueness in plant with components
    made globally.
  • Statistical notion of population is not helpful
    when you only a few plant items.
  • Suspend own judgement.
  • Decision making can be based on rest of the
    population and not on your plant or conditions.

43
Visual Inspection the ugly duckling of CM?
44
Minimum Electrical CM
  • HV Motor
  • Thermography HV Tests
  • MCSA and online measurements
  • Transformer
  • DGA Thermography
  • HV Test
  • Switchgear
  • Thermography insulation and circuit resistance
    HV tests
  • Timing checks

45
Where is help available?
  • Specialists service providers
  • OEMs
  • Consultants, in-house or external
  • Universities
  • Standards
  • Technical Organisations
Write a Comment
User Comments (0)
About PowerShow.com