Title: Demands of Contracting Environment
1Demands of Contracting Environment
2What is an Engineering Contractor (EC)?
- Traditional Approach Build only
- Hiring a company who has a team of experienced
engineers (Chemical/Mechanical/Civil/Electrical
etc can vary with the field of work involved)
to build large engineering set ups i.e.,
Production plants for chemical and mechanical
products mechanical part production system - Emerging Approach Build, Own and Operate
- Hiring a company who has a team plus resources to
fund the whole set up of Build Own and Operate
3Typical EC Projects in Pakistan
- PARCO
- Motorway
- Gwader Port
- Airport
- Fatima Fertilizer
- Power Plants
- Motor car assembly units
4Emerging Approach
5Key ECs Strengths
- Holds library of equipment design and cost
- May have carried out many similar projects
- Holds equipment procurement data base
- Strong project management and control systems in
place - Capacity and capability to deliver the services
6What an Engineering Contractor (EC) does?
- Play a key role in the life-cycle of large
multi-million dollar projects/facilities. - This is normally achieved in following stages
- Development
- Implementation
7ECs Evolution in Oil Sector
- 60s - A few oil companies ran their EPC
themselves - 70s emerged international ECs
- 80s oil price crisis led to huge redundancies
leading to contracting out all detailed
engineering work - Now ECs have become an indispensable part of
the development and implementation of new
processing facilities in oil, gas and
petrochemical sectors. - Many ECs holds licence for certain process
technologies
8Future of an EC
- World marketed energy consumption to grow by 40
- same as per last 20 years means processing
capacity to be doubled in the last decade - Oil Sector is already seeing an overheated
contracting market for large Engineering and
Construction Projects
9Large EC ProjectKey Elements
- Building large ECP is technically complex best
illustrated by the high level of availability - Have high demands on the quality of the technical
development and implementation - BUT
- The risks are high !
10The Institutional Partners
- The owner of the facility
- Contractors (EC)
- Authorities
- Customers and feedstock suppliers
11The Project Life CycleDevelopment
- Most critical part of project life cycle when
location and main functionality parameters are
defined ie project feasibility, alignment with
clients business strategy and selection of
preferred options - Detail of functionality, CAPEX, schedule and
organisation are developed in stages - Confirm compliance with clients integrity
management and personal safety standards,
environmental legislation and HSE framework - Normally 1-3 of the total installed costs
12Development Stage Demands
- Define clear project objective
- System control
- Traceability of all design work i.e. data sheets,
PIDs - Legislation directives ie SIL, HSE, EA
- Hazard and Risks ie HAZOP/HAZAN
- Whole life cycle analysis and process
optimisation ie enhance process efficiency by
minimising raw material, water, steam and energy
- Doubled man-hours charged as the Bag is becoming
heavier.
13Team Triangle
Sales
Engineering
Proposal
14The project Life CycleImplementation
- Detailed engineering, procurement, construction
- Following implementation a distinct reference
point in the project life cycle is the start-up
of the facility when the responsibility is
transferred to operating company.
15Typical ECs Task Force
Project Manager
Engineering Manager
Lead Piping Engineer
Lead Process Engineer
Lead EI Engineer
Lead Civil Engineer
Lead Mechanical Engineer
16Engineers Level of Input
Chemical/Process
Civil/Structure
Mechanical/Piping
EI
Input Level
Execute - Detailed Engineering Construction
Commissioning and Operation
FEED
17Contractual Arrangementskey attributes
- A systemic organisational framework for
institutional cooperation is required - Projects inherently require the ability to adapt
to changes and uncertainly - this is important
as to the long time nature of projects - This area is weak in Pakistan and requires built
in provisions cater contractual flexibility for
long duration projects like PSDP, facility
development.
18Key Institutional Attributes
- Generally, in the world, ECs common observations
are - EC Projects require competence to cope with risks
and turbulence. - They become manageable through the design of
strategic systems. - The infusion of governability.
- The transformation of institutions.
- The design of financial arrangements, and the
building of ownercontractor relationships.
19Typical Owner-Contractor Agreements Map
20Generic Options for Contractor Selection
21Key Drivers of a Contract Business Deal
22Additional Hierarchical Contract Components
- Conditions of effectiveness of contracts
- Acceptance
- Insurance
- Force Majeure
- Premature termination
- Taxes
- Applicable law
- Dispute arbitration and resolution
23Case Studies
- Technical Specification
- Quality of cost estimates
- Payment Terms
- Schedule
24Technical Specification
- Key Attributes The quality of the
specifications includes adequacy and
completeness (executable descriptions, not
political statements), consistency between the
technical and commercial part of annexes, and the
clarity of scope, deadlines and the clients
deliverables. The concreteness of the
specifications documentation will heavily
determine future change orders or claims, as it
defines what is a changed requirement.
- Example When building the worlds biggest
sulfuric acid plant in Mount Isa, Australia - no
clear profile was available of the variation of
the SOx concentration in the off-gas of the four
different smelters, information that was key to
determine and control the specifications of the
sulfuric acid plant. When the Sox profiles became
available, specifications had already been
defined for the acid plant construction
contractor. Thus, some equipment had to be
changed, causing many significant engineering
change orders for which the contractor charged
high fees. This significantly increased the cost
and the delivery time of the plant.
25Quality of Cost estimates
- Key Attributes Ideally, the price and the
quality of the underlying cost estimates should
be perfectly consistent with the technical
specifications, including an adequate cost
contingency. The client should avoid to always go
for the lowest bid.
- Example The joint venture of Cleveland Cliffs
Inc. USA and Lurgi Metallurgie Germany to convert
iron ore to direct reduced iron with a
revolutionary new technology, The contractor then
claimed he himself could do the steel erection at
the original estimated cost, and was awarded the
contract. However, the estimate had been
unrealistic, causing him to aggressively claim
change order charges in order to cover his costs.
This gave rise to a lawsuit, in which the
contractor indeed won a claim of 20 million.
26Payment Terms
- Key attributes Contractors mostly receive a
515 down payment, allowing them to start the
job. Intermediate payments allow equipment
delivery, as contractors rarely have the cash
flows to pre-finance their suppliers. The final
510 payments are critical. They are frequently
tied to mechanical and/or final completion and to
passing performance tests and enable the client
to exercise maximum pressure on the contractor.
- Example In 1991, the British contractor Davy
McKee became insolvent as a consequence of the
contract conditions they had accepted in the
construction of the Emerald Field Oil platform in
the North Sea. Davy McKee had accepted a lump sum
contract of almost 100 million, payable in one
single instalment upon completion. Moreover, it
was their first project for this kind of
technology. When they ran into significant cost
overruns during execution, they could not obtain
an extension of their backup financing and were
forced to sell off successful businesses,
ultimately leading to the sale of the group to
the Norwegian conglomerate Kvaerner.
27Schedule
- Key Attributes Consistency in, and a shared
understanding of, the definition of the key
milestones (mechanical completion, function test,
cold commissioning and hot commissioning) are
vital to smooth project implementation. There has
been a recent tendency to compress project
schedules in order to improve the clients
project returns.
- Example When Union Miniere revamped its
Bulgarian copper smelter, a dispute arose about
the timeliness of the restart of one of the
copper converters. As the converters were key to
the economics of plant operation, every day of
the repair shutdown beyond the target period of
10 days was heavily penalized.
28Various Contract Types
- Fixed price Lump sum Turnkey (LSTK)
- Incentive based
- Cost Reimbursable
- The LSTK concept can address all drivers in one
contract with one party, achieving the clearest
risk and responsibility allocation and minimizing
interfaces.
29Contract Type Selection
- Depends on
- Type of Technology New or already been built
- Size of installation
- Risk levels
30Liability Limitation in Practice
- About 70 of the clients go for Fitness for
Purpose Liability - Rest 30 recognises the practical and commercial
problems posed to EC. - Unlikely to obtain cover for fitness for purpose
liability which could lead to the contractor
carrying the major uninsured risk consequently
EC prefer to go for reasonable skill and care.
31Concluding Observations
- Typically projects worth more than 100 million
are handled via EC - Professional and Prospective Engineers should be
aware of the typical requirement EC. - Formal training programmers should be organized
through mock projects with in academia - PEC has taken a good initiative by providing an
opportunity to introduce the subject. - This is only the tip of the iceberg and lot more
needs to be learnt through experience within an
EC environment.