Demands of Contracting Environment - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

Demands of Contracting Environment

Description:

Thus, some equipment had to be changed, causing many significant engineering ... Rest 30% recognises the practical and commercial problems posed to EC. ... – PowerPoint PPT presentation

Number of Views:72
Avg rating:3.0/5.0
Slides: 32
Provided by: mal9150
Category:

less

Transcript and Presenter's Notes

Title: Demands of Contracting Environment


1
Demands of Contracting Environment
  • Dr Abdullah Malik

2
What is an Engineering Contractor (EC)?
  • Traditional Approach Build only
  • Hiring a company who has a team of experienced
    engineers (Chemical/Mechanical/Civil/Electrical
    etc can vary with the field of work involved)
    to build large engineering set ups i.e.,
    Production plants for chemical and mechanical
    products mechanical part production system
  • Emerging Approach Build, Own and Operate
  • Hiring a company who has a team plus resources to
    fund the whole set up of Build Own and Operate

3
Typical EC Projects in Pakistan
  • PARCO
  • Motorway
  • Gwader Port
  • Airport
  • Fatima Fertilizer
  • Power Plants
  • Motor car assembly units

4
Emerging Approach
5
Key ECs Strengths
  • Holds library of equipment design and cost
  • May have carried out many similar projects
  • Holds equipment procurement data base
  • Strong project management and control systems in
    place
  • Capacity and capability to deliver the services

6
What an Engineering Contractor (EC) does?
  • Play a key role in the life-cycle of large
    multi-million dollar projects/facilities.
  • This is normally achieved in following stages
  • Development
  • Implementation

7
ECs Evolution in Oil Sector
  • 60s - A few oil companies ran their EPC
    themselves
  • 70s emerged international ECs
  • 80s oil price crisis led to huge redundancies
    leading to contracting out all detailed
    engineering work
  • Now ECs have become an indispensable part of
    the development and implementation of new
    processing facilities in oil, gas and
    petrochemical sectors.
  • Many ECs holds licence for certain process
    technologies

8
Future of an EC
  • World marketed energy consumption to grow by 40
    - same as per last 20 years means processing
    capacity to be doubled in the last decade
  • Oil Sector is already seeing an overheated
    contracting market for large Engineering and
    Construction Projects

9
Large EC ProjectKey Elements
  • Building large ECP is technically complex best
    illustrated by the high level of availability
  • Have high demands on the quality of the technical
    development and implementation
  • BUT
  • The risks are high !

10
The Institutional Partners
  • The owner of the facility
  • Contractors (EC)
  • Authorities
  • Customers and feedstock suppliers

11
The Project Life CycleDevelopment
  • Most critical part of project life cycle when
    location and main functionality parameters are
    defined ie project feasibility, alignment with
    clients business strategy and selection of
    preferred options
  • Detail of functionality, CAPEX, schedule and
    organisation are developed in stages
  • Confirm compliance with clients integrity
    management and personal safety standards,
    environmental legislation and HSE framework
  • Normally 1-3 of the total installed costs

12
Development Stage Demands
  • Define clear project objective
  • System control
  • Traceability of all design work i.e. data sheets,
    PIDs
  • Legislation directives ie SIL, HSE, EA
  • Hazard and Risks ie HAZOP/HAZAN
  • Whole life cycle analysis and process
    optimisation ie enhance process efficiency by
    minimising raw material, water, steam and energy
  • Doubled man-hours charged as the Bag is becoming
    heavier.

13
Team Triangle
Sales
Engineering
Proposal
14
The project Life CycleImplementation
  • Detailed engineering, procurement, construction
  • Following implementation a distinct reference
    point in the project life cycle is the start-up
    of the facility when the responsibility is
    transferred to operating company.

15
Typical ECs Task Force
Project Manager
Engineering Manager
Lead Piping Engineer
Lead Process Engineer
Lead EI Engineer
Lead Civil Engineer
Lead Mechanical Engineer
16
Engineers Level of Input
Chemical/Process
Civil/Structure
Mechanical/Piping
EI
Input Level
Execute - Detailed Engineering Construction
Commissioning and Operation
FEED
17
Contractual Arrangementskey attributes
  • A systemic organisational framework for
    institutional cooperation is required
  • Projects inherently require the ability to adapt
    to changes and uncertainly - this is important
    as to the long time nature of projects
  • This area is weak in Pakistan and requires built
    in provisions cater contractual flexibility for
    long duration projects like PSDP, facility
    development.

18
Key Institutional Attributes
  • Generally, in the world, ECs common observations
    are
  • EC Projects require competence to cope with risks
    and turbulence.
  • They become manageable through the design of
    strategic systems.
  • The infusion of governability.
  • The transformation of institutions.
  • The design of financial arrangements, and the
    building of ownercontractor relationships.

19
Typical Owner-Contractor Agreements Map
20
Generic Options for Contractor Selection
21
Key Drivers of a Contract Business Deal
22
Additional Hierarchical Contract Components
  • Conditions of effectiveness of contracts
  • Acceptance
  • Insurance
  • Force Majeure
  • Premature termination
  • Taxes
  • Applicable law
  • Dispute arbitration and resolution

23
Case Studies
  • Technical Specification
  • Quality of cost estimates
  • Payment Terms
  • Schedule

24
Technical Specification
  • Key Attributes The quality of the
    specifications includes adequacy and
    completeness (executable descriptions, not
    political statements), consistency between the
    technical and commercial part of annexes, and the
    clarity of scope, deadlines and the clients
    deliverables. The concreteness of the
    specifications documentation will heavily
    determine future change orders or claims, as it
    defines what is a changed requirement.
  • Example When building the worlds biggest
    sulfuric acid plant in Mount Isa, Australia - no
    clear profile was available of the variation of
    the SOx concentration in the off-gas of the four
    different smelters, information that was key to
    determine and control the specifications of the
    sulfuric acid plant. When the Sox profiles became
    available, specifications had already been
    defined for the acid plant construction
    contractor. Thus, some equipment had to be
    changed, causing many significant engineering
    change orders for which the contractor charged
    high fees. This significantly increased the cost
    and the delivery time of the plant.

25
Quality of Cost estimates
  • Key Attributes Ideally, the price and the
    quality of the underlying cost estimates should
    be perfectly consistent with the technical
    specifications, including an adequate cost
    contingency. The client should avoid to always go
    for the lowest bid.
  • Example The joint venture of Cleveland Cliffs
    Inc. USA and Lurgi Metallurgie Germany to convert
    iron ore to direct reduced iron with a
    revolutionary new technology, The contractor then
    claimed he himself could do the steel erection at
    the original estimated cost, and was awarded the
    contract. However, the estimate had been
    unrealistic, causing him to aggressively claim
    change order charges in order to cover his costs.
    This gave rise to a lawsuit, in which the
    contractor indeed won a claim of 20 million.

26
Payment Terms
  • Key attributes Contractors mostly receive a
    515 down payment, allowing them to start the
    job. Intermediate payments allow equipment
    delivery, as contractors rarely have the cash
    flows to pre-finance their suppliers. The final
    510 payments are critical. They are frequently
    tied to mechanical and/or final completion and to
    passing performance tests and enable the client
    to exercise maximum pressure on the contractor.
  • Example In 1991, the British contractor Davy
    McKee became insolvent as a consequence of the
    contract conditions they had accepted in the
    construction of the Emerald Field Oil platform in
    the North Sea. Davy McKee had accepted a lump sum
    contract of almost 100 million, payable in one
    single instalment upon completion. Moreover, it
    was their first project for this kind of
    technology. When they ran into significant cost
    overruns during execution, they could not obtain
    an extension of their backup financing and were
    forced to sell off successful businesses,
    ultimately leading to the sale of the group to
    the Norwegian conglomerate Kvaerner.

27
Schedule
  • Key Attributes Consistency in, and a shared
    understanding of, the definition of the key
    milestones (mechanical completion, function test,
    cold commissioning and hot commissioning) are
    vital to smooth project implementation. There has
    been a recent tendency to compress project
    schedules in order to improve the clients
    project returns.
  • Example When Union Miniere revamped its
    Bulgarian copper smelter, a dispute arose about
    the timeliness of the restart of one of the
    copper converters. As the converters were key to
    the economics of plant operation, every day of
    the repair shutdown beyond the target period of
    10 days was heavily penalized.

28
Various Contract Types
  • Fixed price Lump sum Turnkey (LSTK)
  • Incentive based
  • Cost Reimbursable
  • The LSTK concept can address all drivers in one
    contract with one party, achieving the clearest
    risk and responsibility allocation and minimizing
    interfaces.

29
Contract Type Selection
  • Depends on
  • Type of Technology New or already been built
  • Size of installation
  • Risk levels

30
Liability Limitation in Practice
  • About 70 of the clients go for Fitness for
    Purpose Liability
  • Rest 30 recognises the practical and commercial
    problems posed to EC.
  • Unlikely to obtain cover for fitness for purpose
    liability which could lead to the contractor
    carrying the major uninsured risk consequently
    EC prefer to go for reasonable skill and care.

31
Concluding Observations
  • Typically projects worth more than 100 million
    are handled via EC
  • Professional and Prospective Engineers should be
    aware of the typical requirement EC.
  • Formal training programmers should be organized
    through mock projects with in academia
  • PEC has taken a good initiative by providing an
    opportunity to introduce the subject.
  • This is only the tip of the iceberg and lot more
    needs to be learnt through experience within an
    EC environment.
Write a Comment
User Comments (0)
About PowerShow.com