Welcome to the Altair Conceptual Design Contract ACDC Preproposal Conference - PowerPoint PPT Presentation

1 / 65
About This Presentation
Title:

Welcome to the Altair Conceptual Design Contract ACDC Preproposal Conference

Description:

Welcome to the Altair Conceptual Design Contract (ACDC) Preproposal Conference ... ACDC will provide early industry engagement to help clearly define our concept ... – PowerPoint PPT presentation

Number of Views:233
Avg rating:3.0/5.0
Slides: 66
Provided by: jco9
Category:

less

Transcript and Presenter's Notes

Title: Welcome to the Altair Conceptual Design Contract ACDC Preproposal Conference


1
Welcome to the Altair Conceptual Design Contract
(ACDC) Preproposal Conference
  • Thursday, December 18 , 2008
  • NASA / Johnson Space Center (JSC) Gilruth Center,
    Alamo Ballroom
  • 900 AM 1200 PM

2
Agenda
  • Introduction 900 a.m.
  • Lee Pagel, Procurement Policy and Systems Office
  • Welcoming Remarks 910 a.m.
  • Debra Johnson, Director, JSC Office of
    Procurement
  • Dale Thomas, Deputy Program Manager,
    Constellation Program
  • Kathy Laurini, Project Manager, Altair Project
    Office
  • Altair Project Overview 930 a.m.
  • Clinton Dorris, Deputy Project Manager, Altair
    Project Office
  • Procurement Overview- Technical 940 a.m.
  • Brad Jones, SEB Chair, Altair Project Office
  • Procurement Overview - Contract and Pricing
    1030 a.m.
  • Lee Pagel - Contracts
  • Charles Bell - Pricing
  • Submit Questions / Break 1100 a.m.
  • Question Answer Session 1115 a.m.

3
Safety and Administrative Information
Fire Exits
  • Restrooms are in the hallway outside this
    ballroom
  • Fire exits are the front entrance and side exit
    doors. In the event of a fire, move at least 75
    ft. away from the building
  • Please adjust all cell phones and pagers to the
    Off or Vibrate setting

Fire Exit
Fire Exit
Restrooms
4
Disclaimer
  • This presentation is for information purposes
    only
  • This presentation is not to be construed as a
    comprehensive description of all solicitation
    requirements
  • To the extent there is inconsistency between this
    presentation and the ACDC Solicitation
    NNJ09BT112R, the solicitation governs

5
Purpose
  • The purpose of the ACDC Preproposal Conference
    is
  • To help Industry understand the Governments
    requirements
  • To address key aspects of the draft RFP
  • Seek industry feedback on the solicitation
  • Interested parties are invited to comment on all
    aspects of the draft RFP, including requirements,
    schedules, proposal instructions, and evaluation
    approaches by January 12, 2009
  • These Preproposal charts will be posted to the
    ACDC website http//procurement.jsc.nasa.gov/alt
    air/

6
Questions
  • Verbal questions during this presentation will
    not be answered however, interested parties may
    submit written questions using the forms provided
    which will be collected and answered as time
    permits at the end of the conference
  • After the conference concludes, interested
    parties may submit additional questions or
    comments via email to the Contracting Officer at
    timothy.a.boyes_at_nasa.gov
  • Anonymous questions may be submitted via the ACDC
    website at http//procurement.jsc.nasa.gov/altair
    /
  • Immediately following the conference, one-on-one
    sessions begin and continue on Friday

7
Welcome
Debra JohnsonDirector, JSC Office of Procurement
8
  • Dale Thomas
  • Deputy Manager, Constellation Program

9
Welcome
Kathy LauriniProject Manager, Altair Project
Office
10
Altair Project Objectives
  • Build a strong and efficient NASA team
  • Effectively execute NASA role as owner of the
    Altair design
  • Distributed across the agency
  • Understand Constellation requirements and derive
    Altair requirements
  • Seeking stable requirements set post-SRR/SDR
  • Identify an Altair vehicle configuration that
    meets all key driving requirements
  • Mature the design in preparation for System
    Definition Review (SDR)
  • Involve industry partners in several phases
  • Broad Area Announcement (BAA) study work
    completed in November 2008
  • Altair Conceptual Design Contracts provide
    industry input through System Definition Review
    (SDR)
  • Potential Future Contract(s) for completion of
    DDTE
  • ACDC will provide early industry engagement to
    help clearly define our concept of operations,
    requirements, interfaces and design concepts
    prior to prime contractor procurement activities
  • Participation on design team at all levels
  • Innovative design solutions
  • Highly successful program/project milestone
    reviews

11
Altair Overview
Clinton DorrisDeputy Project Manager, Altair
Project Office
12
Constellation Program Fleet of Vehicles
Earth Departure Stage
Altair Lunar Lander
Orion Crew Exploration Vehicle
Ares I Crew Launch Vehicle
Ares V Cargo Launch Vehicle
13
Altair Mission Requirements
  • 3 Variants Sortie, Outpost, Cargo
  • 4 Crew
  • 7 Day Sortie
  • 210 Day Outpost
  • Deliver 500kg of cargo w/ crew
  • Return 100 kg (goal of 250kg) from the lunar
    surface
  • Airlock or Suitlock on Sortie missions only
  • Control Mass
  • Crewed missions control mass 45,000 kg
  • Cargo missions control mass 53,600 kg

14
Altair Configuration Variants
Outpost Variant Descent Module Ascent Module
Sortie Variant Descent Module Ascent
Module Airlock
Cargo Variant Descent Module Cargo on Upper Deck
15
Intent of Procurement
  • Strategic Goals
  • Enable a blend of NASA led design efforts with
    industry involvement through Altair Lunar Lander
    System Definition Review (SDR)
  • Using the following tenants
  • Develop an industry informed Altair reference
    design
  • (innovative solutions, design maturity, SRR/SDR
    products)
  • Products informed by production and manufacturing
    knowledge and experience
  • Lower Life Cycle Costs (Reduce reconciliation
    costs)
  • Supplement the Government team with capabilities
    currently not owned within the Agency
  • Holiday
  • Not intended to force industry to work over the
    holidays
  • We intentionally moved the schedule to the right
    to enable question development and submittal
    after the holidays
  • We will not be answering questions over the
    holidays

16
Procurement Overview- Technical
Brad JonesSEB Chair, Altair Project Office
17
Procurement Schedule
  • ACTIVITY DATE
  • PROCUREMENT STRATEGY MEETING Nov 02, 2008
  • ISSUE DRAFT RFP Dec 16, 2008
  • PRE-PROPOSAL CONFERENCE Dec 18, 2008
  • DRAFT RFP QUESTIONS DUE Jan 12, 2009
  • ISSUE RFP Jan 28, 2009
  • PROPOSALS DUE Feb 25, 2009
  • CONTRACT AWARD Jun 03, 2009

18
Contract Overview
Typical Firm Fixed Price
  • Proposing to this contract
  • Interested in breadth and depth of capabilities
  • Will be working as part of a team, data
    deliverables summarize this work
  • Variables
  • Price
  • Givens (Constant)
  • Content
  • Schedule

ACDC Firm Fixed Price
  • Givens (Constant)
  • Price - capped
  • Schedule
  • Variables
  • Content

19
Contract Implementation
  • Multiple Contractors Working as part of NASA led
    IPTs
  • Working together on common tasks
  • Working independently on separate tasks
  • Working independently on common tasks
  • Organized around Analysis Cycles and Milestone
    Reviews (CLINs)
  • Contract Execution
  • Content will be defined in the proposal, agreed
    upon in the contract
  • NASA using Technical Direction to re-define
    content as work progresses
  • Summary reports are the final deliverable for
    each CLIN (x10)

20
Altair Summary Schedule
FY2009 FY2010 FY2011
FY2012 FY2013 FY2014
7/2010 Program HLR SRR
Program/Project Milestones
Altair SDR 12/2011
Altair SRR 12/2010
LDAC-3
RAC-1
AC-1
AC-2
Altair Analysis Cycles
AC-3
Additional Analysis Cycles
Base Award
Option 1
Option 2
BAA
Altair Procurement
1
1
Altair Contractor Support
DDTE Contract
21
What Were Asking For (SOW)
  • Contractor Work Objectives
  • Provide products that will enable the Altair
    Project to
  • Re-evaluate the Altair configuration, and
    incorporate innovative solutions
  • Mature the lander technical design
  • Accomplish the SRR and SDR milestones
  • Contractor Provided Resources
  • Multiple, cooperating contractor teams
  • Each provides resources to supplement the NASA
    Altair team
  • Contractors tasks individual contractor team or
    as part of an integrated IPT
  • Collaborative workforce to each of the NASA-led
    IPTs (subsystems, SEI, Safety, TV, Ops,
    Manufacturability, etc.)
  • Key positions (each contractor)
  • Contractor Project Manager
  • Senior Project Integration Engineer
  • Senior Vehicle Engineer
  • Senior Systems Engineer
  • Contract Deliverables
  • Research and Development within Altair IPT
    environment
  • Multiple data deliverables (separate summary
    report per contractor) documenting work performed
    during each Analysis Cycle or Milestone Review
    period.

22
How We Propose To Do This (SOW)
IPT Work
Summary Reports
SOW 2.2
Analysis Cycle (SOW 3.1)
SOW 2.3
AC/MS Process Descriptions
SOW 2.5
Milestones (SOW 3.2)
SOW 2.4
23
Altair Lunar Lander Project Office Organization
Altair Lunar Lander Project Office
Business Manager
Chief Engineer
  • Orion
  • Ares V
  • EVA
  • LSS
  • GO

Crew Representative
Project Liaisons
Operations Integration
Vehicle Engineering
Technology Integration
Safety, Reliability Quality Assurance
Test and Verification
Project Integration
Baseline Development
Risk Management
Integrated Vehicle Performance
Subsystem Management
24
Altair Lunar Lander Project Office Organization
25
Integrated Product Teams
  • Contractors will perform work in collaboration
    with Altair civil service personnel in Integrated
    Product Teams (IPTs)
  • Each IPT is led by an Altair civil servant
  • Not all IPTs are active in each analysis cycle,
    however, every IPT will be active at some point
    during the contract period.
  • Contractors must be capable of supporting each
    IPT when required.

26
Altair Conceptual Design Contract Schedule
Dec 09
June 10
Dec 10
June 12
Dec 12
Dec 08
June 11
Dec 11
June 09
Cx LC SRR July 2010
Review
SRR Prep
SRR Prep
Altair SRR December 2010
Review
Milestone Reviews
SDR Prep.
Altair SDR December 2011
Review
High-level vehicle architecture and configuration
trades
TAC-1
TAC-2
Vehicle architecture and configuration trades
(concluded)
DAC-4
Vehicle design maturation
Analysis Cycles
DAC-5
Vehicle design maturation
Planning phase precedes the Analysis Cycle
Vehicle design maturation
DAC-6
Vehicle design maturation
DAC-7
DAC-8
Contract Base Period
Option Year 1
Option Year 2
27
Content of Contract Deliverables
Altair Analysis Cycles (AC) Products (CLIN 0001)
  • Altair technical work is divided into 6 month
    Analysis Cycles (AC)
  • Each AC is a multi-step process with common, well
    defined products
  • Contractors are to provide analytical and review
    support to the following NASA owned products
    (this is representative, as tasks vary for each
    Analysis Cycle)

TAC-1
TAC-2
-- Risk modeling -- Risk identification --
Technical trade studies and analyses -- Subsystem
designs -- CAD models -- Schematics -- Master
Equipment Lists -- Powered Equipment Lists --
Consumables Analyses -- Integrated vehicle
performance -- Operations concept -- Systems
requirements document -- Interface requirements
documents --
DAC-4
-- -- -- -- -- -- -- -- -- --
-- -- -- -- -- -- -- -- -- --
Additional Analysis Cycles for Option Periods
-- -- -- -- -- -- -- --
28
Content of Contract Deliverables Contd
Altair Milestone Products (CLIN 0002)
  • Each major milestone (SRR, SDR, etc) requires a
    well defined set of products
  • Most are government produced and industry
    reviewed
  • Contractors are to provide analytical/review
    support to the following NASA owned products
    (this is representative, as tasks vary for each
    milestone review)
  • Program SRR
  • Altair Concept of Operations
  • Altair Mission Timeline
  • Altair Functional Flow Block Diagrams
  • Altair SRD
  • Altair-Orion IRD (draft)
  • Altair-Ares V IRD (draft)
  • Altair-Ground Ops IRD (draft)
  • Altair-Mission Ops IRD (draft)
  • Altair-C3I IRD (draft)
  • Altair-EVA IRD (draft)
  • Altair-PEPCI IRD (draft)
  • Technical Trades and Analyses
  • Launch Pad and Facilities Processing Plan
  • Technical Performance Measure Plan
  • Margin Management Plan
  • Earned Value Management Plan
  • Configuration Management Plan
  • Data Management Plan
  • Project SRR
  • Altair ICDs (draft)
  • Altair Master Verification and Validation
    Strategy
  • Project Documentation Tree
  • Altair Initial Preliminary FMEAs
  • Altair Preliminary Hazard Analyses
  • Altair Updated Project Risk Report
  • Technical Trades and Analyses
  • Altair IVDDD
  • Altair SPAR
  • Altair Structural Loads Data Book (draft)
  • Altair CAD Models
  • NPR 7123.1A and NPR 7120.5D Compliance Matrix
  • Master Test and Verification Plan
  • Contamination Control Plan
  • Quality Plan
  • Drawing Plan
  • Project SDR
  • EVM plan (final) 
  • CAD management plan (final)
  • EEE parts control plan (draft)
  • Materials control plan (draft)
  • Fastener control plan (draft)
  • Margins management plan (draft)
  • Software development plan (SDP) (draft) 
  • Altair Project Plan (final)
  • Altair Integrated Vehicle Design and Description
    Document (updated)
  • Technical Trades and Analyses
  • Altair Spacecraft Performance and Analysis
    Report
  • Altair Ops Concept (final)
  • Altair Mission Timeline Document (final)
  • Altair Flight Operations Data Book (draft)
  • Induced Environments Document (final)
  • CT Verification and Validation Plan (draft)
  • Subsystem Verification and Validation Plans
    (draft)
  • .

29
RFP Addresses OCI
  • Provision L-15 in draft RFP describes potential
    OCIs raised by this acquisition and the steps
    taken by the Government to resolve them.
  • The Government believes it has taken adequate
    steps to avoid and/or mitigate all potential OCIs
    raised by this acquisition.
  • The cover letter to the draft RFP invites
    comments from industry on this provision and
    whether there is any OCI not yet addressed by the
    Government.
  • The offeror must explain the actions it intends
    to use to resolve any OCIs it finds in its own
    assessment. If any potential OCIs are identified
    by an offeror, they will be addressed prior to
    release of the final RFP.

30
Proposing to this Procurement
  • NASA has tailored the Mission Suitability factor
    to reflect the ACDC unique content
  • Mission Suitability is the most significant
    factor
  • Technical Approach is the most heavily weighted
    subfactor and provides detailed insight into your
    approach

31
Introduction to Technical Approach (TA) Subfactor
  • TA is your approach to executing the SOW, via the
    Contract Deliverables
  • Evaluated in three different ways (Check
    Section M for specific language)
  • Overall Plan for contract performance
  • Your Teams capabilities relative to large scale
    space vehicles
  • Understanding of broad technical implications
    inherent in example trades analyses
  • Data we will use to evaluate this (Check
    Section L for specific language)
  • TA1 Technical Approach to Line Items
  • Spreadsheet for each CLIN with Labor Resources
    allocated by IPT
  • Narrative Explanation of your reasoning for
    allocation chosen
  • Top-level narrative with overall approach
  • TA2 Capability for Designing, Developing, Mfg,
    Human Spaceflight Vehicles
  • Narrative description of facilities, experience,
    corporate capabilities
  • TA3 Representative Trades Analyses
  • Narrative plan, describing
  • General Approach to each trade
  • Your process for conducting each
  • How you will apply skills and resources to each

32
Introduction to Management Approach (MA)
Subfactor
  • MA is your Approach for organizing the work
  • Evaluated in three different ways (Check
    Section M for specific language)
  • Team Strategy for the work
  • Workforce strategy
  • Individual information for 4 identified critical
    positions
  • Subfactors examine management planning and
    capabilities in increasing levels of detail
  • Data we will use to evaluate this (Check
    Section L for specific language)
  • MA1 Organizational Strategy
  • Which subs or other corporate divisions, why
    chosen
  • Evidence that this has worked in past
  • MA2 Flexibility and Staffing
  • How will you perform in the ACDC environment?
  • How will you provide excellent labor resources
    over course of the contract?
  • MA3 Key Personnel
  • Resumes on the four Key Personnel identified

33
Procurement Overview- Contract Pricing
Lee PagelJSC Procurement Policy and Systems
Office
34
Contractual Highlights
  • Contract Type
  • Firm Fixed Price (FFP)
  • Full and Open competition
  • Utilizing NAICS Code 336414
  • Guided Missile and Space Vehicle Manufacturing
  • Size Standard 1,000 Employees
  • Period of Performance
  • Potential 3.5 years with a base period of 1.5
    years and the possibility for up to two years in
    options
  • Contract start date estimated for July, 2009
  • Place of Performance
  • Contractor Facility
  • Travel to JSC or other NASA Centers for selected
    meetings

35
ACDC Firm Fixed Price
Typical Firm Fixed Price
  • Givens (Constant)
  • Content
  • Schedule
  • Variables
  • Price

ACDC Firm Fixed Price
  • Variables
  • Content
  • Givens (Constant)
  • Price capped
  • Schedule

36
ACDC Firm Fixed Price
  • Variables
  • Content
  • Specified in Attachment J-8
  • Drawn from SOW
  • Subject to Clause G.3, Technical Direction
  • Shifts Emphasis
  • Requiring Studies
  • Pursuit of Certain Lines of Inquiry
  • Within the general tasks and requirements in SOW
  • Does not increase price
  • Givens (Constant)
  • Price capped
  • Clause B.3
  • Schedule
  • Clause F.2

37
Sections A through G Highlights
  • Section A
  • Offeror to complete blocks 12 through 18 of the
    Standard Form 33
  • Section B
  • B.3 SCHEDULE OF SUPPLIES AND/OR SERVICES TO BE
    PROVIDED
  • Fill in proposed fixed price amount for each
    deliverable
  • Prices must match pricing model
  • Section D, E F - No unique contractual aspects
  • Section G
  • G.3 TECHNICAL DIRECTION
  • Standard NASA Clause
  • Due to the nature of this contract, NASA
    anticipates regular and extensive use of this
    clause

38
Section H Highlights
  • Section H
  • H.7 KEY PERSONNEL AND FACILITIES
  • Contractor fill in any proposed key personnel for
    positions indicated
  • Contractor shall notify CO reasonably in advance
    before replacing key personnel
  • H.8 ASSOCIATE CONTRACTOR AGREEMENTS
  • To achieve requirements of this contract, close
    coordination, cooperation and exchange of
    information with other contractors will be
    required
  • Contractor is responsible for establishing and
    documenting these ACAs

39
Section I Highlights
  • Section I
  • I.4 OPTION FOR INCREASED QUANTITY - SEPARATELY
    PRICED LINE ITEM
  • Permits exercise of Option CLINs on an individual
    basis
  • 1.7 RIGHTS IN DATAGENERAL
  • Unlimited rights to data first produced under
    this contract
  • In general, Limited Rights Data or Restricted
    Rights Software is not to be delivered without CO
    written permission
  • I.13 SECURITY REQUIREMENTS FOR UNCLASSIFIED IT
    RESOURCES
  • Contractor responsible for IT security for all
    systems connected to a NASA network or operated
    by a contractor for NASA, regardless of location
  • IT Security Plan to be provided by the Contractor
    within 30 days after authorization to proceed

40

Sections J K Highlights
  • Section J
  • Attachment J-1 DRDs
  • Attachment J-2 Applicable and Reference Docs
  • Attachment J-3 PIV Card Issuance Procedures
  • Attachment J-4 Safety Health Plan
  • Attachment J-5 Small Business Subcontracting Plan
  • Attachment J-6 Altair Operations Plan
  • Attachment J-7 Acronym List
  • Attachment J-8 Deliverable Item List
  • Section K
  • All section K provisions require offeror fill in

41
Evaluation Factors
  • SOURCE SELECTION APPROACH SEB procedures will
    be used per FAR Part 15.1
  • Evaluation of proposals based on the tradeoff
    process
  • Source Selection Authority will make selection
    based on three factors
  • Mission Suitability
  • Past Performance
  • Price
  • Mission Suitability is more important than Past
    Performance.
  • Mission Suitability and Past Performance
    individually are more important than Price.
  • Mission Suitability and Past Performance combined
    are significantly more important than Price.
  • Government has the option to
  • Make selection and award without discussions, or
  • Conduct discussions with all finalists, request
    Final Proposal Revisions (FPR) from each offeror
    and then make selection

42
Mission Suitability
  • Technical Approach 650 points
  • TA1 Technical Approach to Line Items
  • Requires complete plan to accomplish CLINs,
    including labor resources, BOE and technical
    approach
  • TA2 Capability for Designing, Developing, and
    Manufacturing human rated space vehicles
  • Approach and existing capabilities
  • TA3 Representative Trades and Analyses
  • Completeness, clarity, feasibility, adequacy of
    approach to sample trades
  • Management Approach 300 points
  • MA1 Organizational Strategy
  • Focuses on subcontracting strategy
  • MA2 Flexibility and Staffing
  • Evaluate approach to Altair environment Multiple
    Contractors, Open Data, changing Skill Mix and
    labor resource levels over time
  • Focuses on general workforce strategy
  • MA3 Key Personnel
  • Focuses on 4 identified position
  • Small Business Participation 50 points
  • SB1 Small Disadvantaged Business Participation
  • SB2 Small Business Subcontracting Plan

43
Section L Highlights-Proposal Arrangement (L.13,
L.14)
  • Volume I- Technical
  • Narrative Technical Approach, organized by
    subfactor
  • TA1 Technical Approach to Line Items
  • Technical Resources Templates BOEs and Technical
    Approach
  • CLIN Deliverable Labor Resources Excel
    Spreadsheets
  • TA2 Capability for Designing, Developing, and
    Manufacturing human rated space vehicles
  • TA3 Representative Trades and Analyses
  • Volume II- Management and Pricing
  • Narrative Management Approach, organized by
    subfactor
  • MA1 Organizational Strategy
  • MA2 Flexibility and Staffing
  • MA3 Key Personnel
  • SB1 Small Disadvantaged Business Participation
  • SB2 Small Business Subcontracting Plan
  • Price
  • Overall Pricing Narrative
  • Price Summary Spreadsheet
  • Volume III- Past Performance
  • Narrative and Past Performance Questionnaires

60 pages
30 pages
20 pages
44
Proposal Structure
Volume 1 Technical Approach TA1, TA2,
TA3 Pages 60 Copies 10 Excel Spreadsheets
not in page count limit.
Volume 2 Management Approach Pricing MA1, MA2,
MA3, SB1, SB2, PRICE Pages 30 Copies 10
Summary Excel Spreadsheet not in page count limit.
May be combined into one binder
Volume 3 Past Performance Pages 20 Copies
7 Delivered Early
Volume 4 Model Contract Pages No Limit Copies
7
Electronic Copies Copies 1 CDROM, 1USB
45
Other Section L Highlights
  • L.8 PROPOSAL MARKING AND DELIVERY
  • Provides detailed instructions on how to submit
    proposals to CO
  • Offerors are responsible to ensure proposals are
    delivered to screening station at JSC Central
    Receiving (Bld 421) prior to delivery to the CO
  • JSC Central Receiving is only accessible through
    Gate 4 (back gate off Space Center Blvd Bay
    Area Blvd)
  • Time for security screening can vary based on
    current levels of activity- so plan accordingly
  • Very important to understand this provision- ask
    questions if anything is not clear

46
Section L Highlights
  • L.14.3 PAST PERFORMANCE
  • Past Performance Narrative on 3 - 5 past
    contracts
  • Key Elements of the Past Performance evaluation
    are
  • Systems Engineering,
  • Manufacturing,
  • Vehicle Assembly and Checkout,
  • System/Vehicle Design and Integration,
  • System and Sub-system Certification for
    Human-rated Spaceflight,
  • Meeting Cost and Schedule Goals,
  • Customer Satisfaction
  • Includes specific paragraphs on Safety,
    Environmental, and Insurance history
  • Offerors with no previous experience shall so
    state
  • Past Performance Questionnaires to be submitted
    directly to the Government from 3 references
  • L.15 NOTICE OF POTENTIAL ORGANIZATIONAL CONFLICTS
    OF INTEREST

47
Highlights of Price Factor
  • Firm Fixed Price for each Contract Line Item
    (CLIN)
  • The Government will conduct price analysis and
    may also perform cost analysis of proposed prices
    in accordance with FAR
  • A single Price Summary Template is required by
    the RFP
  • Prices entered in Section B of your Model
    Contract will take precedence
  • over prices proposed in the Price Summary
    Template if they conflict
  • For each offeror the RFP sets a 42.2 price
    ceiling, the total of all CLIN prices
  • Proposed CLINS shall comply with RFPs Govt
    Fiscal Year funding profile

Although CLIN 0001AG may be delivered during
FY13, funding for this CLIN should be FY12.
48
Highlights of Price Factor
Additional RFP information regarding fiscal year
funding profile
Funding obligated in one fiscal year may be used
to pay invoices in a subsequent fiscal year.
Invoice payments cannot exceed the cumulative
obligations to date. Your proposed total
contract value shall not exceed the price cap,
nor may CLIN prices exceed the cumulative funding
profile. Offerors shall assume that funding is
required no later than the delivery date of a
contract line item.
As stated in Section M of the RFP, price analysis
may include a comparison of the proposed price
and the value of the proposed resources,
resulting in a value assessment of products and
activities provided for the proposed price.
Proposals will be reviewed to ensure compliance
with RFP limits on total contract price and GFY
funding. Failure to comply with the total
contract price limit or GFY funding limitations
could result in a weakness, deficiency, or in an
offeror being ineligible for award
49
One-on-One Meetings
50
One-on-One Meetings
  • 30-minute one-on-one meetings with interested
    parties will be held in separate rooms December
    18 and 19
  • By appointment only, sign up by 1200 December
    18th
  • Schedule
  • December 18th from 100 500 p.m. Coronado
    Room (all booked)
  • December 19th from 800 500 p.m. San Jacinto
    Room

51
One-on-One Meetings-Acceptable Topics for
Discussion
  • The general purpose of the contemplated
    procurement
  • Any information about the Constellation Program /
    Altair Project that NASA has already made
    accessible to the public or is otherwise being
    made available to all potential offerors
  • Historical information about the general nature
    or scope of prior similar contracts whose
    requirements may be similarly addressed in whole
    or in part under the contemplated procurement
  • Information that describes the federal
    procurement process as defined in the Federal
    Acquisition Regulations (FAR), NASA FAR
    Supplement (NFS) or other published procurement
    policy documents
  • Procurement specific information already
    published such as information contained in the
    acquisition forecast, Statement of Work (SOW),
    and draft solicitation

52
One-on-One Meetings-Unacceptable Topics for
Discussion
  • Proprietary or confidential business information
    of contractor(s) or other business entities
    performing similar ongoing efforts
  • Privacy Act protected information such as
    existing contractor employees personal data
  • Trade Secrets Act protected information
  • Speculation on what the Government might be
    looking for in proposals
  • Different technical and management approaches
  • Technical efficiencies
  • Any particular Government emphasis
  • Performance of contractors providing similar
    requirements that could become competitors

53
Altair Conceptual Design Contract (ACDC)
  • Thank you for attending!
  • Visit the ACDC Web Site at
  • http//procurement.jsc.nasa.gov/Altair/

54
Backup Information
55
Deliverable Item List (DIL) ExampleAnalysis Cycle
56
Deliverable Item List (DIL) ExampleMilestone
Review
57
Contractor Planning Phase
Combined team Prioritized List NASA team
formulates Contractor work dist.
Key
Work Plan (Analysis Cycle Personnel Spreadsheet)
Contractor
Contractor Management
IPTs
NASA
Tasks/Analyses Proposal List
Approved Contractor Work Plans
IPTs
NASA Management
COTR
NASA Management
IPTs
Analysis Cycle Tasks Contractor Team Assignments
Technical Direction To Contractors
IPTs
Perform Analysis Cycle Tasks
Summary Report
IPTs
Contractor Team
Assemble Team POCs
Contractor Management
IPTs
58
Candidate Trade List For TAC-1 (Altair LDAC-3
output)
59
IPTs, Panels and Boards
Vehicle Configuration Decisions, Milestone Review
Products
Contractor
NASA
  • Project Control Board
  • Large configuration decisions
  • Decisions changing the balance of performance,
    cost, safety
  • Decisions that impact spacecraft functionality
  • Decisions that impact other Projects or Level II

NASA Altair Project Management
  • Vehicle Engineering Panel
  • Vehicle-level configuration decisions
  • Subsystem decisions
  • Project Integration Panel
  • Milestone review product decisions
  • Other Panels as necessary

Vehicle Engineering
Test Verification
Operations Integration
Technology Integration
Safety (SRQA)
Project Integration
  • Multiple IPTs
  • - NASA and Contractor personnel jointly
    participate in Integrated Product Teams
  • NASA-led with senior contractor personnel
  • Joint NASA and Contractor staffed

60
Mitigating OCI
  • Two risks have been identified
  • Biased ground rules Utilizing contractor
    expertise during lander design definition and
    maturation creates the risk of a contractor
    setting ground rules for a future contract
    competition that are biased in its favor.
  • Equal distribution of work Because work done
    under this contract will involve multiple
    contractors participating in an IPT design
    environment with the Government, and task orders
    will not be issued for each individual
    contractors work, there is a risk the Government
    will have to expend significant resources to
    ensure that work tasks are fairly assigned to the
    contractors.
  • Government took actions to avoid potential
    conflicts in the RFP
  • Utilizing multiple contractors to participate in
    IPTs and develop work products.
  • Maintaining NASA leadership of each IPT to filter
    and integrate feedback from all contractors to
    create Government products and requirements for
    use in a future competition. NASA will make all
    design decisions and retain all designs.
  • Developing a plan to monitor work done in each
    IPT and encourage communication across IPTs to
    ensure no contractor has a position of undue
    influence on the requirements of the lander
    vehicle.
  • Making all deliverable data available to the
    entire industry community and to all future DDTE
    contract offerors consistent with existing public
    release of data.

61
Contract Line Item (CLIN) Definition Plan
  • Clause B.3
  • Supplies Services
  • CLIN
  • Price
  • Delivery Date
  • Description

Contract
Section J, Attachment J-8 Deliverable Item
List 0001AA Products ----------
---------- Activities ---------- ----------
Section L Offeror to complete Attachment J-8,
IAW proposed approach
Reference
Instruction
Section C Statement of Work Paragraph
2, Contractor Work Scope
62
CLIN RE-Definition Plan
  • Clause B.3
  • Supplies Services
  • CLIN
  • Price
  • Delivery Date
  • Description

Contract
Section J, Attachment J-8 Deliverable Item
List 0001AA Products ----------
---------- Activities ---------- ----------
  • Clause G.4
  • Technical Direction
  • Redefines Products and Activities
  • No increase in price or delivery date
  • Within scope of SOW

Reference
Technical Direction
Section C Statement of Work Paragraph
2, Contractor Work Scope
63
Intent of TA1
  • TA1 Technical Approach to Line Items
  • Background
  • TA1 shows your capabilities, ability to apply
    resources to IPTs, how subs are used, and your
    approach to analysis cycles and program/project
    review milestones
  • Increases NASA confidence in successful
    performance
  • Overall Narrative
  • Overall information about how you plan to execute
    the CLINs
  • Could be information that you only want to
    describe once, but applies to all 10 CLINs
  • Technical Resources Information -- Organized by
    CLIN
  • Technical Approach Narrative
  • What are you going to do?
  • How are you going to do it?
  • Who (subs, prime) is going to do it?
  • What will be the result? (Products/Activities
    list also provided as Attachment J-8)
  • Basis of Estimate Narrative
  • What estimating methodology did you use for
    labor?
  • Why do you use the skill mix you use for this
    CLIN?
  • Why do you use the number of FTEs that you
    propose for this CLIN?
  • Resources -- Spreadsheet

64
Intent of TA2
  • TA2 Capability for Designing, Developing and
    Manufacturing human rated space vehicles
  • Background
  • TA2 shows your capabilities, experience, and
    facilities specific to human space flight
  • NASA seeks design partners that bring real-world
    knowledge of building space vehicle designs
  • NASA-led design to accommodate design constraints
    of manufacturing, testing, transportation, ground
    and flight operations
  • Narrative describes capabilities in
  • Design
  • Development
  • Manufacturing and Production
  • Test Facilities
  • Tooling
  • QA
  • Assembly Integration
  • Transportation
  • Also include specific previous programs and
    projects and how they utilized these capabilities
  • Evaluation Criteria
  • The Government will evaluate the Offerors
    proposed approach and existing capabilities for
    designing, developing and manufacturing human
    rated space vehicles

65
Intent of TA3
  • TA3 Representative Trades and Analyses
  • Background
  • Other evaluation factors primarily assess general
    approach, overall staffing and resource
    flexibility
  • A proposal element was needed to evaluate the
    contractors technical breadth, their technical
    approach to specific tasks, and the skills
    applied to specific sample tasks.
  • Each of the 5 sample tasks was chosen to examine
    specific abilities, breadth of understanding,
    innovative insights, the ability to construct a
    logical stepwise approach to dissecting the
    problem, and the ability to apply appropriate
    contractor internal and subcontractor resources
    to the task.
  • The 5 Trades and Analyses are
  • Lander Scavenging
  • Ascent Module/Airlock Configuration
  • Produceability and Manufacturability
  • Landing Gear Design
  • CG Management Mitigation
  • Evaluation Criteria
  • Definition of the scope of the analysis
  • Systems Approach -- Identification and
    understanding of any interdependencies
  • Identification of proper resources, including any
    subcontractors proposed
  • Consideration of alternative and innovative
    techniques and options
Write a Comment
User Comments (0)
About PowerShow.com