Title: Thubelisha Homes Presentation to the Portfolio Committee on Housing


1
Thubelisha HomesPresentation to the Portfolio
Committee on Housing
  • Presented by
  • Kevin Duncan
  • Chief Executive Officer
  • 10 May 2006

2
Agenda
  • Establishment of Thubelisha
  • Mandate
  • Funding Framework
  • Board members
  • Corporate Governance
  • Strategic Plans
  • Key Challenges
  • Delivery Challenges
  • Contributions to BNG/ASGISA
  • Employment Equity/Procurement
  • Way forward

3
Introduction
  • Established in 1997 as a Housing Support
    Institution of the National Department of Housing
  • CEO appointed in January 1999, operations
    commenced soon after
  • Section 21 company, registered under Section 3(a)
    of the PFMA with Independent Board of Directors
    and 3 classes of members
  • Original mandate was primarily to provide housing
    stock for Servcons Rightsizing programme
  • Ministers decision in October 2004 to
    rightsize the remaining Servcon portfolio
    in-situ, forced the creation of an alternative
    future for Thubelisha

4
Mandate
  • New mandate received on 22nd February 2006
  • To undertake the construction of affordable
    housing projects and related services
  • To provide project management services
  • Now required to do actual construction of houses
    and installation of engineering services
  • Requires a different business model to manage the
    higher risk profile associated with construction
    activities
  • Appointed as Implementing Agent for the Western
    Cape DoH on the N2 Gateway

5
Funding FrameworkInitial R50 million Grant
  • Used as a revolving fund to bridge finance
    project costs, and then later collect subsidies.
  • Reduced to R39 m due to R11 m in losses
    accumulated since inception
  • Included in the Debtors that still need to be
    collected from Provinces.

6
R30 million Capacitation Grant
  • Since 1 November 2005, R14m used for capacitation
    purposes including
  • Recruitment of new staff and salaries
  • Opening of new offices and office rentals
  • Marketing and communicating new role for
    Thubelisha
  • Travel costs
  • Telephones, equipment rental, capital expenditure
  • The balance will be spent on further recruitment,
  • capital expenditure, and installation of new IT
    systems in 2006/7.

7
Transfers from NDoH for Overhead Recovery
  • No transfers for overheads up to year 2006/7
  • Transfers are expected to take place quarterly
    starting from 1 April 2006

8
New Corporate Form
  • According to new legislation, public entities
    will not be allowed to be section 21 companies.
  • Thubelisha has made suggestions to the NDoH for a
    suitable new corporate form.
  • Whatever corporate form is approved will
    determine how Thubelisha will be capitalised.

9
Board of Directors
  • Mr D M Thompson (Chairman)
  • Mr J L Bartlett
  • Mr K C Duncan (CEO)
  • Ms C L Mdaka
  • Ms D E Moraka
  • Mr V P Maluleke
  • Mr P Chauke (recently resigned)
  • Mr W A Odendaal

10
Corporate Governance
  • Independent board with relevant committees that
    meet regularly
  • Audit 4x pa
  • Executive 12x pa
  • Investment 4x pa
  • Remuneration 2x pa
  • Reduced number of directors has necessitated
    urgent changes to Articles of Association

11
Corporate Governance contd.
  • More appropriate corporate form in accordance
    with Treasury/DPSA governance framework required
    for new mandate
  • Will also require transformation of Board in
    terms of appropriate skills
  • Generally compliant with King 2 Code

12
Corporate Governance contd.
  • PFMA non-compliant areas
  • Loans, guarantees other commitments
  • Investment of surplus funds with Corporation for
    Public Deposits
  • Audit Committee should not have same Chair as
    Board of Directors
  • Audit committee to meet annually with Auditor
    General
  • Payments in excess of R2,000 to be effected
    electronically

13
Scope of Activities
  • Land identification
  • Feasibility Studies
  • Project/technical audits
  • Construction of houses
  • Installation of engineering services
  • Project and Construction management
  • Subsidy and claims administration
  • Beneficiary relocations
  • Support organisation for managed PHPs
  • Community liaison
  • Accounts Administrator
  • Contractor development skills transfer
  • Turnkeys

14
2005/06 Results
15
2005/06 Results
16
2005/06 Results
17
2005/06 Results
18
2005/06 Results
19
2005/06 Results
20
2005/06 Results
21
2005/06 Results
22
2005/06 Results
23
Key Strategic Objectives2006/07 08/09
  • Short term
  • To successfully re-brand Thubelisha by 30
    September 2006
  • To successfully restructure Thubelisha by 30 June
    2006
  • To secure 2 new mega projects under the UISP by
    30 September 2006
  • To reach agreement on a new corporate form by 30
    June 2006
  • To have the funding arrangements to support this
    Business Plan approved by NDoH, by 30 April 2006

24
Key Strategic Objectives2006/07 08/09
  • Medium Term
  • To contribute 20 of the national subsidised
    housing delivery by 31 March 2009
  • To be recognised by the NDoH as the Governments
    specialist implementing agent for mega projects

25
2006/07 - 08/09 Operational Indicators
26
2006/07 08/09Financial Indicators
27
BudgetsImplications Assumptions
  • Subsidy (sales) value and Cost Of Sales increase
    by 12 per annum
  • Various forms of tranche payments for all
    unblocking projects
  • No more P1 to P5 progress payments
  • Operating costs to be partially covered by annual
    transfers from NDoH R47m, R50m and R54m
  • Operating expenses increase by 9 per annum,
    compensation by 7
  • Mega projects increased share of total turnover
    34, 46, 49

28
Budgets Implications Assumptions cont.
  • Revenue recognised in accordance with AC 109
    stage of completion
  • 10 margin on unblocking projects
  • Zero margin on UISP projects, but monthly
    retainer and project management fee per unit
  • 4 fee on social other facilities
  • Accounts Receivable balance at 31 March 2006,
    collected by 31 March 2007

29
Key Challenges
  • Controls must not be compromised as a result of
    decentralised operations, and huge increase in
    Company output
  • New IT systems must be timeously developed and
    implemented
  • Brand awareness and public relations must be
    enhanced to obtain successful repositioning
  • Relationships with some Provinces and Local
    Authorities must be strengthened
  • Seen as a total solutions provider for
    socio-political problems, yet measured narrowly
    in terms of houses built

30
Key Challenges cont.
  • Management and controls of new construction
    activities need special attention to mitigate
    against new risk areas
  • Appropriate technical staff will be recruited at
    an affordable cost, and current staff retained,
    considering the demand for their skills
  • Additional funding will be made timeously
    available for projects under the UISP, to enable
    implementation as per the requirements of the BNG
  • Stakeholders must not have unreasonable
    expectations of what is realistically achievable

31
Contribution to BNG/ASGISA
  • Upgrading of informal settlements
  • Provision of social and community facilities
  • Social (medium density) Housing
  • Job creation
  • Unblocking of housing projects
  • Capacity building in Local Authorities
  • Rectification of houses built between 1994 and
    2002

32
Employment Equity
  • Thubelisha has adopted targets for employment
    equity as per the Construction Industry Charter
  • 30 black people at all management levels
  • 12 black women at all management levels
  • Black Africans, Coloureds and Indians i.t.o.
    BBBEE Act 53 of 2003

33
Employment Equity 2005/06
34
Employment Equity by Race
35
Employment Equity by Gender
36
Procurement
  • Our procurement targets are in line with the
    Construction Industry Charter.
  • Industry target is to achieve a weighted target
    of procurement spend from BBEEE suppliers of 70
    by December 2013.
  • Our goal is to increase the procurement of women
    service providers to 15, and HDIs to 30 in the
    next three years.

37
Way Forward
  • Reinstatement as a VAT vendor
  • Conversion to a more appropriate corporate form
  • Communiqué from Minister to Provinces and Local
    Authorities regarding Thubelishas new mandate
  • Standardisation of contractual agreements with
    Provinces, particularly in terms of tranche
    payment arrangements

38
  • Thank You