Title: PRESENTATION ON CONDITIONAL GRANTS (Land Care) AND COMPREHENSIVE AGRICULTURAL SUPPORT PROGRAMME (CASP)
1PRESENTATION ON CONDITIONAL GRANTS (Land Care)
AND COMPREHENSIVE AGRICULTURAL SUPPORT PROGRAMME
(CASP)
2Land Care
3Projects
- 2004 2005
- Klipspruit River and wetlands clean up (Soweto)
- Mamelodi LandCare Resource Centre Permaculture
training - Mobilisation of civil society (Klipspruit)
- 2005 2006
- Dinokeng Alien Invasive plants removal
4Land Care Trends
Project Name Allocation ZAR X 103 Expenditure ZAR X 103 Variance explanation
2004-5 ( Total allocation R 1 785 000) 2004-5 ( Total allocation R 1 785 000) 2004-5 ( Total allocation R 1 785 000) 2004-5 ( Total allocation R 1 785 000)
Klipspruit 1 452 1 452 -
Mamelodi 148 0 Delays in signing of MoUs BP by Tshwane
Civil society 185 0 Province informed on additional funding in end of 2004
5Land Care Trends
2005-6 (Total allocation R 2 000 000) R 333 000 roll over 2005-6 (Total allocation R 2 000 000) R 333 000 roll over 2005-6 (Total allocation R 2 000 000) R 333 000 roll over 2005-6 (Total allocation R 2 000 000) R 333 000 roll over
Dinokeng 2 000 2 000
Mamelodi 148 148
Civil society 185 185
Total Landcare spending for 2005/2006 100. Total Landcare spending for 2005/2006 100. Total Landcare spending for 2005/2006 100. Total Landcare spending for 2005/2006 100.
6Non-financial outputs
Klipspruit Mamelodi Dinokeng
Activity Removal of waste Permaculture training Removal of alien vegetation
No of jobs/ beneficiaries 51 jobs created 25 people trained per year 135 jobs created
No of women employed 30 60 81
Partners DoA, JDA, Ward councilors DoA, City of Tshwane DoA, DWAF-WfW
Other outputs 40-50 tons removed pm Skills dev training Part of bigger initiative Value adding secondary industry
7Challenges
- 2004-5
- Expenditure for the mobilisation of civil
society only undertaken in 2005-6 due to the
fact that the Department was informed during
latter part of the 2004-5 year of additional
funds - Non-alignment of provincial and local
municipality process delays in implementation
of Mamelodi project to 2005-6 - 2005-6
- Delays in signing of MoUs and Business Plans with
Working for Water.
8Monitoring
- Weekly Site visits to monitor progress on
operations. - Declared Weeds and Invader Plants (DWIP)
committee meetings on a monthly monitors
progress and financial expenditure. - Expenditure reports (DoA) monthly.
- DORA (DoA) reports quarterly basis.
- EPWP reports (to GPTRPW, DEAT, DoA)- quarterly
basis.
9Compliance with monthly reporting
- Challenges of getting monthly reports are
addressed in DWIP forums and project steering
committees. - Cooperative governance partnership with DoA as
funders, GDACE as managers and DWAFF who assist
with operations.
10Business plans
- Submitted to the National Department of
Agriculture. - Signed in Nov/December.
11CASP
12PURPOSE
- To provide a status report to the Select
Committee on Finance in respect of the on-going
Land Care and CASP projects undertaken by GDACE. - To update the select committee on Finance about
the implementation of the 2005/06 Land Care and
CASP projects. - To highlight the challenges faced by the province
with regards to the preparations for the project
plans and ensuring compliance with DORA and the
funding agreement.
13BACKGROUND - CASP
- The budget for the 2005/6 financial year was R 5
727 000. - The grant per farmer is limited to R150 000.00.
- The grant can be higher or lower provided that a
feasibility study by the Agricultural Economists
in the Department indicates that the beneficiary
can generate an equal net income in a reasonable
time span with the produce from the commodities
for which the infrastructure is intended. - The purpose with the CASP conditional grants is
to provide grants to individual beginner farmers
for on-farm infrastructure and training. - 70 is spent on LRAD and 10 on Household Food
Security and 20 on other small and emerging
farmers.
14Expenditure pattern
2004/2005 Provincial CASP Expenditure. No rollover. 2005/06 Provincial CASP allocation Total Applications received Total Submitted for Procurement Total Committed (For which Orders were issued) Actual payments Total Amount to be Rolled over
R4,582,000 R 5,727,000 R 6,692,916 R 5,901,403 R 4,860,751 R 1,330,300 R 4 396 700
15CHALLENGES 1
- During 2004/2005 our main challenge was capacity
constraints. - (Agriculture has since been elevated to a Chief
Directorate with three Directors and capacity has
been expanded by 25). - Lack of positive collaboration with certain
service provider who demand upfront payment
before they can deliver the goods.
16CHALLENGES 2
- Lack of positive collaboration with certain
service provider who demand upfront payment
before they can deliver the goods. - Service providers are reluctant to responsibility
for delivery of goods. - Shortage of service providers in Gauteng with
specialized services as required by applicants. - The demand for on off-farm infrastructure by
emerging farmers is more than the available
budget.
17EXPLANATION OF THE ROLLOVER 1
- The first quarter of the financial year focussed
on rounding off activities of the 2004/05 CASP
financial year thus resulting in the delay in the
commencement of activities for the 2005/06
financial year. - Actual procurement commenced in the third quarter
as we streamlined processes of farmers needs
identification, identifying compliant service
providers, sourcing quotations and placing orders.
18EXPLANATION OF THE ROLLOVER
- Coordination and cooperation with service
providers negatively affected service delivery as
most service providers requested for upfront
payment while holding on to orders. This is
against procurement procedures. - The delays caused by the service providers who
mailed invoice resulted in delayed payments.
19PROPOSED REMEDIAL ACTIONS1
- As on 03-05-06 50 actual payments have gone
through the system. - The DLA (Department of Land Affairs) provided a
list of all restitution and LRAD projects in
Gauteng which should be considered for funding. - The Department is currently identifying a
dedicated manager whose focus will be the
unlocking of the procurement bottlenecks.
20PROPOSED REMEDIAL ACTIONS 2
- The branch is optimistic that upon unlocking
these bottlenecks we will be able to disburse the
grants. - The department will not only focus on Gauteng
service providers but will also source quotation
from other provinces.
21Monitoring
- Weekly Site visits by extension officers to
monitor progress on operations. - Expenditure reports (DoA) monthly.
- DORA (DoA) reports quarterly basis.
22Conclusion.