Update on Project Prioritization Effort - PowerPoint PPT Presentation

About This Presentation
Title:

Update on Project Prioritization Effort

Description:

Title: IS&T Org Charts Author: Christine Cavanna Last modified by: johnc Created Date: 1/21/2004 8:12:51 PM Document presentation format: On-screen Show – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 9
Provided by: Christi752
Learn more at: http://web.mit.edu
Category:

less

Transcript and Presenter's Notes

Title: Update on Project Prioritization Effort


1
Update on Project Prioritization Effort
  • SAPbiz
  • 10 March 04

2
Presentation Outline
  • Current Status 2nd Meeting
  • Overview of Resource Model
  • Methodology
  • Resource problem
  • A-B-C Analysis
  • Future Direction Ongoing Process

3
Current Status
  • 2nd Meeting, 3/1
  • Attendance Grochow (Staff), Proj. Sponsors (1)
  • Problem Bring requirements, resources into
    equilibrium
  • Action from Meeting Further Analysis by Staff
  • Extend model to 36 months / equilibrium
  • Provide delay analysis
  • Bring Back Results to Group for Further
    Discussion

4
Resource Model
  • Resource Requirements from Project Managers
  • Available Staff from Providers (mainly AC)
  • Broken out by
  • Project, support/small projects
  • Skill, e.g. business analyst, ABAP, web
  • Organization / team
  • Result TBA by Project, Skill

5
Resource Model (cont.)
6
A-B-C Analysis
  • Break Out Projects By Major Scope Items
  • Characterize each item as
  • (A) Must have functionality
  • (B) Want to have functionality
  • (C) Enhancement / Extension to base functionality
  • Also as Regulatory, Budget Related, Other
  • Analyze Impact of BC Deferral, Project Delay or
    Cancellation.
  • Done With Project Managers, Reviewed by Sponsors

7
A-B-C Analysis (cont.)
  • Results
  • Most discussion on HR/Payroll, EHS, and Upgrade
  • No conclusions re delay or cut
  • Staff to analyze delay options again, and bring
    options to Group for discussion
  • JG Maybe we dont get to zero today, but well
    get closer.

8
Future Direction
  • Resolve Immediate Problem
  • Group Develops Options to Achieve Equilibrium
  • Delays and cuts preferred options
  • Review with Curry
  • Make Decision(s)
  • Group Evolves Into Ongoing Process, e.g.
    Quarterly Meetings