Title: KickOff Meeting One BAT KTI Nr' 7085'2 DCPPNM
1Kick-Off Meeting One BATKTI Nr. 7085.2 DCPP-NM
ETH Hönggerberg, HCI G 541, April 14, 2005
2Modified Agenda
- 10.30 10.45 am Welcome and Introduction
- 10.45 11.30 am General Affairs and Project
Overview - 11.30 12.00 pm ZHW-CCP
- 12.00 12.30 pm EPFL-LC
- 12.30 1.00 pm ETHZ-NMW
- 1.00 2.00 pm Lunch
- 2.00 2.30 pm NTB-ImS
- 2.30 3.00 pm ETHZ-LTNT
- 3.00 3.30 pm Discussion about collaboration
between the project partners - 3.30 4.00 pm Potential Industrial Partners
- 4.00 4.15 pm Discussion and Other Business
- - Next meetings Date, Location
- - Feedback, Comments, Suggestions
3Agenda
10.30 10.45 am Welcome and Introduction 10.45
11.30 am General Affairs and Project
Overview 11.30 12.00 pm ZHW-CCP 12.00
12.30 pm EPFL-LC 12.30 1.00 pm ETHZ-NMW 1.00
2.00 pm Lunch 2.00 2.30 pm NTB-ImS 2.30
3.00 pm ETHZ-LTNT 3.00 3.30
pm Discussion about collaboration between the
project partners 3.30 4.00 pm Potential
Industrial Partners 4.00 4.15 pm Discussion
and Other Business - Next meetings Date,
Location - Feedback, Comments, Suggestions
4General Overview
- Project One-BAT approved for 1 year
- CHF 798500 (in 2 tranches)
- Conditions
- IP strategy established
- Contracts signed and handed to KTI
- Battery expert from industry involved in the
project - Preparation of concurrence analysis
- Project review with KTI after 6 months (? 2.
tranche) - presentation of intermediate results
- presentation of possible business models
(Wertschöpfungskette) - concurrence analysis
- Considerable changes of the project (partner,
plan, budget) have to be approved by KTI ?
information to Anja - KTI has to be informed in time about patent
application and issue of a patent - Required statements in publications and public
documents mitfinanziert durch die KTI - Signing of agreement for commercial utilization
of project results (latest 3 months after project
start), i.e. Framework and Coordination Agreement
? done
? done latest next week
? done
5New Features of KTI Discovery Projects
- Reports
- 1. controlling report due after 3 months
- afterward controlling reports every 6 months
- Final report at the end of the project
- Umsetzungsplan for project results (with final
report) - Umsetzungsaudit with KTI delegation (5-12
months after project end)
new
new
new
new
6Timetable Project Start June 05
Alternative project start May 05
7Meeting Organization
- One meeting about 3 weeks before controlling
report or review ? 4 meetings - Location 3 x ETH Zürich Hönggerberg, 1 x EPFL
Lausanne ? - Meeting minutes (? kick-off meeting Anja)
- Slides of meetings available on NMW homepage
- http//www.nonmet.mat.ethz.ch/research/OneBat
- each group sends slides (.ppt) to Daniel after
the meeting - each file will be password protected
- password ktionebat
- Liste of co-workers available on NMW homepage
8Financial General
- CHF 798500 for 12 months
- CHF 768500 for salary
- CHF 30000 for further expenses
- CHF 170000 from BFE ? (Dr. Hintermann)
- 1. tranche CHF 400000 for 6 months
- 2. tranche after project review with KTI
- Payment to principal applicant (ETHZ)
- ? form Auszahlungsbegehren to download from
NMW homepage http//www.nonmet.mat.ethz.ch/resear
ch/OneBat - Each group is responsible for ..
- collecting their original receipts and
Buchungsbelege - spending the money in the anticipated time
frame (unused money has to be returned after the
project!) - completing their own financial report according
to form www.bbt.admin.ch/kti - Final financial report collected by Anja due May
31, 2006 (project start June 05)
9Financial Year 1
Total for 12 months CHF 798500.00
(without BFE contribution so far)
Further expenses
Salary
- ETHZ-NMW CHF 4500 CHF 328500
- EPFL-LC CHF 4500 CHF 120000
- NTB-ImS CHF 13500 CHF 140000
- ZHW-CCP CHF 3000 CHF 80000
- ETHZ-LTNT CHF 4500 CHF 100000
CHF 30000
CHF 768500
10Project Overview 1 Year
- WP 1 Fuel Cell Development NMW, EPFL, NTB
- WP 2 Gas Processing Unit Development LTNT, NTB
- WP 3 Thermal System Management NTB, ZHW, NMW,
EPFL, LTNT - WP 4 Product Development ? gt year 3 Industrial
Partner, all - WP 5 Project Management CERION
? WP, milestones, and deliverables have to be
adjusted to 1 year project 3, 6, 9, and 12 months
11WP1 Fuel Cell Development
- WP 1.1 Electrolyte
- Fabrication and characterization of dense CGO by
PVD (EPFL), spray pyrolysis and PLD (NMW) - Fabrication and characterization of YSZ
electrolytes by spray pyrolysis and PLD (NMW) - Deposition on two substrates Foturan and Si
(NMW, EPFL) - Membrane stress measurements as f(T, processing
parameters) (EPFL) - Milestones
- Month 3 - dense and crack-free electrolyte with
composition CGO 80/20 (NMW, EPFL) - - conductivity _at_ 500C-800C in air
characterized s gt 0.2 S/m _at_ 700C in air (NMW,
EPFL) - - microstructure characterized (NMW, EPFL)
- Month 6 - electrical characterization of free
standing membrane (NMW, EPFL) - - stress measurements as input for PEN design
optimization (EPFL) - - YSZ electrolytes characterized (NMW)
- Month 9 - stress measurements of NMW sampes
(EPFL) - Month 12 - 1000 h degradation characterization
(NMW) - Deliverables
- Month 6 - selected samples NMW ? EPFL for
stress measurements dimensions 4 or 1 cm x 3
cm, substrate Si or Foturan
12WP1 Fuel Cell Development (continued)
- WP 1.2 Anode
- Fabrication and characterization of NiO-CGO
(NMW, EPFL) - Investigation of deposition parameters in order
to obtain porous layers and good electrical
conductivity (NMW, EPFL) - Electrochemical characterization (NMW)
- Thermal stability (NMW, EPFL)
- Stress measurements (EPFL)
- Milestones
- Month 3 - crack-free Ni-CGO films, s gt 100
S/cm _at_ 600C, gt 30 porosity in reduced state
(NMW, EPFL) - Month 6 - electrochemical characterization of
NMW and EPFL films (NMW) - - thermal stability and degradation f(T, t)
(NMW, EPFL) - - stress measurements (EPFL)
- Month 9 - stress measurements of NMW samples
(EPFL) - Month 12 - anode electrochemically
characterized with overpotential lt 0.4 Wcm2 _at_
550C (NMW) - Deliverables
- Month 3 - selected samples from EPFL ? NMW for
electrochemical characterization dimensions to
be specified by U. Mücke, substrate YSZ
polished bulk pellet (from NMW) - Month 6 - selected samples from NMW ? EPFL for
stress measurements dimensions 4 or 1 cm x 3
cm, substrate Si or Foturan
13WP1 Fuel Cell Development (continued)
- WP 1.2 Cathode
- Fabrication and characterization of LSCF (NMW,
EPFL) - Investigation of deposition parameters in order
to obtain porous layers and good electrical
conductivity (NMW, EPFL) - Electrochemical characterization (NMW)
- Thermal stability (NMW, EPFL)
- Stress measurements (EPFL)
- Milestones
- Month 3 - crack-free LSCF films, s gt 100 S/cm
_at_ 600C, gt 20 porosity (NMW, EPFL) - Month 6 - electrochemical characterization of
NMW and EPFL films (NMW) - - stress measurements (EPFL)
- Month 9 - stress measurements of NMW samples
(EPFL) - - thermal stability and degradation f(T, t)
(NMW, EPFL) - Month 12 - cathode electrochemically
characterized with overpotential lt 0.4 Wcm2 _at_
550C (NMW) - Deliverables
- Month 3 - selected samples from EPFL ? NMW for
electrochemical characterization dimensions to
be specified by D. Beckel, substrate CGO
polished bulk pellet (from NMW) - Month 6 - selected samples from NMW ? EPFL for
stress measurements dimensions 4 or 1 cm x 3
cm, substrate Si or Foturan
14WP1 Fuel Cell Development (continued)
new
- WP 1.4 Microfabrication and Electrical
Contacting - Design of standard PEN including all
microfabrication steps (NTB, NMW, EPFL) - Design and fabrication of electrical contacts
(NTB, EPFL) - Microfabrication of PEN (NTB, EPFL)
- Integration of Ni grid ? thermally more stable
structures (EPFL) - Milestones
- Month 3 - design of standard PEN and of
electrical contacts available (NTB, NMW, EPFL) - - first microstructured PEN elements ready for
testing (NTB, NMW, EPFL) - - proof of concept for Ni grid (EPFL)
- Month 6 - re-design of PEN element and
electrical contacting (NTB, NMW, EPFL) - - Integration of Ni grid in process flow (EPFL)
- Month 12 - optimized, crack-free, stable
microstructured PEN elements (NTB, NMW, EPFL) - Deliverables
- Month 3 - first microstructured PEN element
NTB, EPFL ? NMW for testing dimensions to be
specified by U. Mücke - Month 6-12 - continuous supply of thin films
and PEN elements for testing NTB, NMW, EPFL
15WP1 Fuel Cell Development (continued)
- WP 1.5 PEN Integration and Testing
- Development of test rig for PEN characterization
(NMW) - Integration and Characterization of PEN (NMW)
- Milestones
- Month 3 - test rig for PEN characterization
operating (NMW) - Month 6 - first electochemical testing results
of integrated PENs (NMW, EPFL, NTB) - Month 9 - optimized electrochemical testing of
PEN structures (NMW) - Deliverables
Year 1 Milestone integrated fuel cell
performance 200 mW/cm2 _at_ 550C with external
electrical connections
16WP2 GPU Development
- WP 2.1 Reformer
- Design and modelling of reformer fuel
preheating, different approaches of microscale
fuel atomization, optimal microscale mixing of
fuel and air, steam reforming partial oxidation
(LTNT) - Catalytic material deposition in the micro-system
(NTB) - Development of process flows (NTB)
- Evaluation of design from processing point of
view (NTB) - Milestones
- Month 3 - first reformer design available (LTNT)
- Month 6 - modelled and evaluated reformer based
on 0.3 g/h butane in 2 cm3 with T max difference
50C (reformer modelled for methane) effect
of thermal conductivity of the reformer walls on
the reformer process, microchannels coated
with catalyst vs. porous catalyst (LTNT) - Month 12 - reformer demonstrator with
significant butane conversion rate _at_ 600C and
stable for feeds of 0.02 to 0.5 g/h butane
incl. gas chromatography (fabrication NBT,
testing LTNT) - Deliverables
- Month 3 - reformer design from LTNT ? NTB for
evaluation - Month 6 - final reformer design from LTNT ? NTB
for fabrication
17WP2 GPU Development (continued)
- WP 2.2 Post-combustor
- Development and testing of post-combustor
similar to reformer T homogeneity, pressure
drop, integration of Venturi nozzle checked in
order to pump air through the fuel cell stack
(LTNT) - Catalytic material deposition in the
micro-system (NTB) - Development of process flows (NTB)
- Fabrication of test device (NTB)
- Milestones
- Month 3 - first preliminary post-combustor
design available - Month 6 - improved designs of post-combustors
aiming for 0.3 g/h butane feed, fully oxidized in
1 cm3 _at_ 600C and max. pressure drop of 3 Pa
(LTNT) - Month 12 - first preliminary post-combustor
demonstrator aiming for significant oxidation
rate _at_ 600C and stable for feeds of 0.02 to 0.5
g/h butane (fabrication NBT, testing LTNT) - Deliverables
- Month 6 - designs of post-combustor from LTNT ?
NTB for fabrication
18WP2 GPU Development (continued)
- WP 2.3 Integration and Testing
- Development of test rig for GPU including gas
chromatography (LTNT) - Performance measurements gas mixtures, cocking
analysis, T distribution, pressure drop (LTNT) - Milestones
- Month 3 - design of test rig available (LTNT)
- Month 6 - test rig for reformer and
post-combustor for GPU performance incl. gas
chromatograph (LTNT) - Month 9 - performance measurements of GPU
(LTNT) - Month 12 - delivery of first reformer and
post-combustor designs aiming for compatibility
with heat exchanger and hot module processing
(LTNT) - Deliverables
- Month 3 - design from LTNT ? NBT
- Month 6 - NTB samples ? LTNT (Patrick checks
whether possible in month 6)
Addendum Beginning of June LTNT asks for data
(NMW, EPFL) for thermodynamic modelling ? perform
exergy analysis of power plant
- Year 1 Milestone
- Reformer with butane conversion rate gt 90 max.
600C, 0.3 g/h feed, lt 2 cm3, stable for 10 h - First post-combustor with fuel exhaust gas
oxidation gt 98 aiming for max. 600C, 0.3 g/h
feed, lt 2 cm3, pressure drop lt 2 Pa
19WP3 Thermal System Management
- WP 3.1 Thermal System Design
- Design and modelling of several thermal
insulation concepts with high efficiency (ZHW) - Benchmarking with respect to m-SOFC systems (ZHW)
- Implementation of finite element models heat
exchanger, dynamic insulation, gas processing
unit, fuel cell stack, interaction with the
environment mechanical analysis (ZHW) - Optimization of design (NTB, LTNT, ZHW)
- Milestones
- Month 3 - thermal insulation concept (Tinside
550C, Toutside 50C) (ZHW) - Month 12 - system integration concept incl.
thermal management concept heat exchanger design
compatible with GPU designs and
micro-fabrication (ZHW) - Deliverables
- Month 3 - design from ZHW ? NTB for fabrication
20WP3 Thermal System Management (cont.)
- WP 3.2 Fabrication Concept of Thermal System
- Validation of micro-fabrication processes (NTB)
- Design and implementation of test structures for
critical properties to characterize the thermal
situation (NTB) - Investigation of manufacturing possibilities of
highly efficient thermal insulation structures
(NTB) - Process development of first hot module (after
designs of fuel cell stack, GPU, heat exchanger
by modelling, production, testing (NTB) - Fabrication and testing of selected designs in
GPU test rig (NTB, LTNT) - Measurement of hot module global performance
(NTB) - Milestones
- Month 6 - test structures for validation of
critical points of the concept (T diff. 500C)
(NTB) - Month 9 - test results of first designs (LTNT)
- Month 12 - thermal system design demonstrator
with simulated heat sources (dummy stack,
reformer, post- combustor) (NTB) - Deliverables
- Month 6 - first samples of GPU from NTB ? LTNT
for testing
Year 1 Milestone Micro-fabricated hot module lt
10 cm3, thermal losses lt 2 W, with real reformer
and post-combustor data and simulated stack (1 W
electrical at 30 efficiency), functioning with
0.3 g/h butane, 10 g/h air feed
21WP5 Project Management
- WP 5.1 Industrial Collaboration (CERION)
- Contacting of companies regarding participation
in the project - Finding industrial battery expert for
accompanying the project - Milestones
- Month 3 - List of potential companies for
industrial collaboration - - Contact to industrial battery expert
established - Month 6 First contacts with the evaluated
industrial partners - Month 12 Contacts with potential industrial
partners interested in taking part in the project - WP 5.2 Business Implementation (CERION)
- Setting-up of business model
- Elaboration of concurrence analysis
- Milestones
- Month 6 Presentation of possible business
models and concurrence analysis - Month 12 Cost analysis and added value
scenarios in view of competing products
22WP5 Project Management (continued)
- WP 5.3 Meetings and Reviews (CERION)
- Organisation of meetings monitor development,
check for achievements of milestones, overview of
system development, WP progressing towards
unified product - Organisation of review meetings Refine effort
distribution between partners and definition of
deliverables - Milestones
- Month 3 Meeting Controlling Report
- Month 6 Meeting Project Review with KTI
- Month 9 Meeting Controlling Report
- Month 12 Meeting Final Report Financial
Report -
- Year 1 Milestone
- Battery expert from industry is accompanying the
project - At least one industrial partner shows definite
interest in joining the project - (industrial partner has to be included in a
subsequent project by joining plausible the value
chain)
23Signing of Contract
- Principal investigator (PI) of each group signs
- Each PI signs each contract ? 7 signatures
24Agenda
- 10.30 10.45 am Welcome and Introduction
- 10.45 11.30 am General Affairs and Project
Overview - 11.30 12.00 pm ZHW-CCP
- 12.00 12.30 pm EPFL-LC
- 12.30 1.00 pm ETHZ-NMW
- 1.00 2.00 pm Lunch
- 2.00 2.30 pm NTB-ImS
- 2.30 3.00 pm ETHZ-LTNT
- 3.00 3.30 pm Discussion about collaboration
between the project partners - 3.30 4.00 pm Potential Industrial Partners
- 4.00 4.15 pm Discussion and Other Business
- - Next meetings Date, Location
- - Feedback, Comments, Suggestions
25Agenda
- 10.30 10.45 am Welcome and Introduction
- 10.45 11.30 am General Affairs and Project
Overview - 11.30 12.00 pm ZHW-CCP
- 12.00 12.30 pm EPFL-LC
- 12.30 1.00 pm ETHZ-NMW
- 1.00 2.00 pm Lunch
- 2.00 2.30 pm NTB-ImS
- 2.30 3.00 pm ETHZ-LTNT
- 3.00 3.30 pm Discussion about collaboration
between the project partners - 3.30 4.00 pm Potential Industrial Partners
- 4.00 4.15 pm Discussion and Other Business
- - Next meetings Date, Location
- - Feedback, Comments, Suggestions
26Potential Industrial Partners
- Ideal Profile
- Medium to large company (annual turn-over gt 500
MCHF) - Experienced with consumer products
- Possessing an extended distribution network
- Active in battery and/or portable electronic
products - Able of micro-systems mass production
Market - replacement product - add on
product
Processing Technology - Si semiconductor
technology - MEMS technology - Thin film
technology
27Potential Industrial Partners
- Potentially interesting candidates
- ST Microelectronics
- Micronas
- Infineon
- EPCOS
- Siemens
- Nokia
- Motorola
- Toshiba
- .
- Candidates not fulfilling all criteria
- Renata
- Leclanche
- UNAXIS
- Sulzer Metco
- Colibrys
- EM Marin
- SensoNor
- Sulzer HEXIS (declined)
- .
28Potential Industrial Battery Experts
- Ionity, D (Hans-Walter Praas) ? contacts in the
next few weeks - Alternatives
- Lithium Technology Corporation (LTC) USA, German
partner GAIA - Emmerich Batterie, D
- ????
29Agenda
- 10.30 10.45 am Welcome and Introduction
- 10.45 11.30 am General Affairs and Project
Overview - 11.30 12.00 pm ZHW-CCP
- 12.00 12.30 pm EPFL-LC
- 12.30 1.00 pm ETHZ-NMW
- 1.00 2.00 pm Lunch
- 2.00 2.30 pm NTB-ImS
- 2.30 3.00 pm ETHZ-LTNT
- 3.00 3.30 pm Discussion about collaboration
between the project partners - 3.30 4.00 pm Potential Industrial Partners
- 4.00 4.15 pm Discussion and Other Business
- - Next meetings Date, Location
- - Feedback, Comments, Suggestions
30Next Meetings Project Start June 05
1. Meeting cw 33 Thursday, August 11,
2005 ETHZ 2. Meeting cw 46 Thursday, November
17, 2005 ETHZ Project Review cw 50 Thursday,
December 8, 2005 ETHZ 3. Meeting cw 06 Thursday,
February 2, 2006 EPFL 4. Meeting cw 20 Thursday,
May 11, 2006 ETHZ
31Feedback, Comments, Suggestions .
- Presentations organized by WP and not by groups
- Reports
- short and concise
- focused on new results, milestones, and
deliverables - refer to publications, internal reports, theses,
patents, . - in English
- publications, internal reports, theses, patents
on NMW homepage (send to Anja) - Confirmation of invitation
- .