DirRev of L0,Trig Install - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

DirRev of L0,Trig Install

Description:

... 4-Hybrid SVX4 string, N&S mini fuse panels, new Wiener PS, ... See W. Cooper's Talk. Director's Review Feb 3-4, 2005. 15. Installation Risk Analysis ... – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 18
Provided by: rpsm
Category:
Tags: dirrev | cooper | install | mini | trig

less

Transcript and Presenter's Notes

Title: DirRev of L0,Trig Install


1

Installation and TechnicalPhysics Commissioning
of DØ RunIIb Silicon Trigger Upgrades
Schedule Costs R.P. Smith for the DØ
Collaboration
2
Action Items from July 2004 Review
  • Understand Clearances for Layer Zero (in 2004
    Shutdown)
  • Incorporate Physics Commissioning in Installation
    Plans and Schedule
  • Review Manpower Estimates, articulate needs for
    extra-DØ help
  • Provide analysis of Installation Risks
  • Incorporate new information from L0 and
    Trigger hardware development teams, 2004 Shutdown
    experience

3
2004 Shutdown Activities Related to Installation
  • Upgrade Installation Infrastructure tasks
    accomplished during 2004 Shutdown (in CH or MCH)
  • L1 Cal None scheduled
  • L1 CalTrack begin mods of Muon PDT and
    Scintillator FEBs, terminate L1CTT transition
    and MTCxx cables
  • L1CTT - install parallel slice crate,
    controller, few DFEAs, cables for CTOC, CTT
  • L2 Beta None scheduled
  • L2 STT None scheduled
  • L0 Silicon L0 clearance survey, adapter card
    and 4-Hybrid SVX4 string, NS mini fuse panels,
    new Wiener PS, Interlock chassis
  • Online Move Online (DAQ, Oracle, NFS) to new
    host cluster

4
Beam-Off Time Paced by Silicon
  • Present Installation Schedule shows Tevatron
    Shutdown Time driven by Layer Zero Silicon
    Installation
  • Detector Not Removed From Collision Hall
  • 2004 Shutdown experiences verifying silicon
    clearance are leading to reconsiderations of
    installation plans gt Revising existing schedule!
  • Consideration of each installation step,
    appropriate (repeated) repositioning of End
    Calorimeter(s) and installation of precision
    fixturing, indicates L0 Installation requires 12
    weeks.
  • Resume Tevatron operations in week 13 with
    opportunity to re-enter CH during L0 technical
    commissioning.
  • 14th week required to close detector and make
    final survey
  • Workweeks are standard 40 hours, five days
  • Silicon installation dominates CH access time.
    Trigger Elements require lesser amounts of CH
    access in time shadow of L0.

5
Silicon Installation Milestone Overview
Current schedules for hardware elements forecast
T0. Forecasts lack schedule contingency.
Tevatron Downtime 14 weeks elapsed
6
L1 Cal Installation Task
Current schedules for hardware elements forecast
T0. Forecasts lack schedule contingency.
L1Cal Ready for Technical Commissioning 2
weeks before beam Resumes
7
Overall Schedule
Dotted Portions lt50 special runs for item
8
Installation Effort
Includes personnel not presently in D0 Group
Workweek Standard 5 days/40 hrs per week
9
Installation Effort
Includes personnel not presently in D0 Group
For assumed T0 this is week of 12/25
Workweek Standard 5 days/40 hrs per week
10
Installation Effort
For assumed T0 this is week of 12/25
11
Detector Gap Occupancy
For assumed T0 Tev on-week is obscured
Per Gap Limit 2
12
Identified Additional Manpower Needs
  • L0 Installation Expert Engineer Youri Orlov
  • L0 Installation Expert Instrumentalist Mike
    Roman
  • L0 Installation Expert Technicians Dave Butler,
    Dennis Graham
  • CTT Expert Jamieson Olson
  • Two Computer Science Professionals
  • L1 Cal University Engineers Dan Edmunds,
    Phillipe Laurens
  • Four Electrical Techs for two weeks for PDT mods
  • Costed in schedule, important to have the named
    individuals

13
Installation Costs
  • Burdened FY05/FY06 Installation Costs

14
Installation Risk Analysis
  • Schedule Risks from Unanticipated Difficulties
    Encountered during L0 Installation substantially
    ameliorated by
  • 2004 shutdown clearance survey
  • Experience with survey instruments in gaps
  • Handling of ECs and beampipe open-up/reclosing
  • Careful design of and practice with Installation
    Tooling beforehand
  • Involve personnel with previous DØ SMT experience
    where possible
  • No second shift or overtime work currently
    scheduled
  • MSProject Installation Management Tool
  • Risk from Accidental Handling Damage to L0 during
    Installation substantially ameliorated by
  • RunIIa Experience
  • Will develop detailed step-by-step plans for
    every aspect of the work
  • Involve personnel with previous DØ SMT experience
    where possible
  • No second shift or overtime work currently
    scheduled

See W. Coopers Talk
15
Installation Risk Analysis
  • Schedule Risk from prolonged Commissioning of
    L1Cal substantially ameliorated by
  • Careful non-invasive handling of fragile BLS
    cable installation (1280 coax cables under MCH1
    floor, gt15 years old)
  • Preparation of BLS/ADF patch panels to
    facilitate reconnection to new ADFs
  • Test Site on DAB Sidewalk full system to be
    operated using collider data input prior to
    shutdown
  • Test data at L2 and L3 thoroughly verified
  • Operating software to be exercised

16
Installation Risk Analysis
  • Schedule Risk from prolonged commissioning of
    L1CTT substantially ameliorated by
  • Parallel Chain Slice Test installed in 2004
    Shutdown to enable system level operation of real
    hardware (crate, crate controller, DFEA2s)
  • Full test of system software (download, monitor,
    diagnose)
  • Test that new hardware loaded with present
    doublet equations gives identical results to
    current trigger
  • Test/optimize (effic. vs rate) algorithms with
    real data
  • Schedule Risk from prolonged commissioning of
    L1CTM substantially ameliorated by
  • Single Button running in global runs with real
    production CalTrack boards prior to shutdown

17
Conclusions
  • Installation Management Team in place
  • SC-IPC up and running to monitor physics
    commissioning planning and manpower scheduling
  • Evolution of Schedule Continues
  • Tasks detailed to sixth sublevel
  • Resources (Effort, MS) loaded
  • WBS Dictionary and BOE in place
  • Timeline assumptions depend on availability of
    identified personnel
  • Schedule refinements underway as planning evolves
  • DØ prefers Tevatron shutdown that begins after
    all upgrade components are ready (to minimize
    integrated luminosity cost)
Write a Comment
User Comments (0)
About PowerShow.com