Title: DirRev of L0,Trig Install
1 Installation and TechnicalPhysics Commissioning
of DØ RunIIb Silicon Trigger Upgrades
Schedule Costs R.P. Smith for the DØ
Collaboration
2Action Items from July 2004 Review
- Understand Clearances for Layer Zero (in 2004
Shutdown) - Incorporate Physics Commissioning in Installation
Plans and Schedule - Review Manpower Estimates, articulate needs for
extra-DØ help - Provide analysis of Installation Risks
- Incorporate new information from L0 and
Trigger hardware development teams, 2004 Shutdown
experience
32004 Shutdown Activities Related to Installation
- Upgrade Installation Infrastructure tasks
accomplished during 2004 Shutdown (in CH or MCH) - L1 Cal None scheduled
- L1 CalTrack begin mods of Muon PDT and
Scintillator FEBs, terminate L1CTT transition
and MTCxx cables - L1CTT - install parallel slice crate,
controller, few DFEAs, cables for CTOC, CTT - L2 Beta None scheduled
- L2 STT None scheduled
- L0 Silicon L0 clearance survey, adapter card
and 4-Hybrid SVX4 string, NS mini fuse panels,
new Wiener PS, Interlock chassis - Online Move Online (DAQ, Oracle, NFS) to new
host cluster
4 Beam-Off Time Paced by Silicon
- Present Installation Schedule shows Tevatron
Shutdown Time driven by Layer Zero Silicon
Installation - Detector Not Removed From Collision Hall
- 2004 Shutdown experiences verifying silicon
clearance are leading to reconsiderations of
installation plans gt Revising existing schedule! - Consideration of each installation step,
appropriate (repeated) repositioning of End
Calorimeter(s) and installation of precision
fixturing, indicates L0 Installation requires 12
weeks. - Resume Tevatron operations in week 13 with
opportunity to re-enter CH during L0 technical
commissioning. - 14th week required to close detector and make
final survey - Workweeks are standard 40 hours, five days
- Silicon installation dominates CH access time.
Trigger Elements require lesser amounts of CH
access in time shadow of L0.
5Silicon Installation Milestone Overview
Current schedules for hardware elements forecast
T0. Forecasts lack schedule contingency.
Tevatron Downtime 14 weeks elapsed
6L1 Cal Installation Task
Current schedules for hardware elements forecast
T0. Forecasts lack schedule contingency.
L1Cal Ready for Technical Commissioning 2
weeks before beam Resumes
7Overall Schedule
Dotted Portions lt50 special runs for item
8Installation Effort
Includes personnel not presently in D0 Group
Workweek Standard 5 days/40 hrs per week
9Installation Effort
Includes personnel not presently in D0 Group
For assumed T0 this is week of 12/25
Workweek Standard 5 days/40 hrs per week
10Installation Effort
For assumed T0 this is week of 12/25
11Detector Gap Occupancy
For assumed T0 Tev on-week is obscured
Per Gap Limit 2
12Identified Additional Manpower Needs
- L0 Installation Expert Engineer Youri Orlov
- L0 Installation Expert Instrumentalist Mike
Roman - L0 Installation Expert Technicians Dave Butler,
Dennis Graham - CTT Expert Jamieson Olson
- Two Computer Science Professionals
- L1 Cal University Engineers Dan Edmunds,
Phillipe Laurens - Four Electrical Techs for two weeks for PDT mods
- Costed in schedule, important to have the named
individuals
13Installation Costs
- Burdened FY05/FY06 Installation Costs
14Installation Risk Analysis
- Schedule Risks from Unanticipated Difficulties
Encountered during L0 Installation substantially
ameliorated by - 2004 shutdown clearance survey
- Experience with survey instruments in gaps
- Handling of ECs and beampipe open-up/reclosing
- Careful design of and practice with Installation
Tooling beforehand - Involve personnel with previous DØ SMT experience
where possible - No second shift or overtime work currently
scheduled - MSProject Installation Management Tool
- Risk from Accidental Handling Damage to L0 during
Installation substantially ameliorated by - RunIIa Experience
- Will develop detailed step-by-step plans for
every aspect of the work - Involve personnel with previous DØ SMT experience
where possible - No second shift or overtime work currently
scheduled
See W. Coopers Talk
15Installation Risk Analysis
- Schedule Risk from prolonged Commissioning of
L1Cal substantially ameliorated by - Careful non-invasive handling of fragile BLS
cable installation (1280 coax cables under MCH1
floor, gt15 years old) - Preparation of BLS/ADF patch panels to
facilitate reconnection to new ADFs - Test Site on DAB Sidewalk full system to be
operated using collider data input prior to
shutdown - Test data at L2 and L3 thoroughly verified
- Operating software to be exercised
16Installation Risk Analysis
- Schedule Risk from prolonged commissioning of
L1CTT substantially ameliorated by - Parallel Chain Slice Test installed in 2004
Shutdown to enable system level operation of real
hardware (crate, crate controller, DFEA2s) - Full test of system software (download, monitor,
diagnose) - Test that new hardware loaded with present
doublet equations gives identical results to
current trigger - Test/optimize (effic. vs rate) algorithms with
real data - Schedule Risk from prolonged commissioning of
L1CTM substantially ameliorated by - Single Button running in global runs with real
production CalTrack boards prior to shutdown
17Conclusions
- Installation Management Team in place
- SC-IPC up and running to monitor physics
commissioning planning and manpower scheduling - Evolution of Schedule Continues
- Tasks detailed to sixth sublevel
- Resources (Effort, MS) loaded
- WBS Dictionary and BOE in place
- Timeline assumptions depend on availability of
identified personnel - Schedule refinements underway as planning evolves
- DØ prefers Tevatron shutdown that begins after
all upgrade components are ready (to minimize
integrated luminosity cost)